Lonesome Creek Station
2648 140th Ave NW, Alexander, ND 58831Plant Summary Information
Lonesome Creek Station is ranked #8 out of 56 power plants in North Dakota in terms of total annual net electricity generation.
Lonesome Creek Station is comprised of 6 generators and generated 270.3 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Lonesome Creek Station |
---|---|
Utility Name | Basin Electric Power Coop |
Location | McKenzie County, ND |
Initial Operation Date | November 2013 |
Last Update | Dec 2023 |
Annual Generation | 1.2 TWh |
Annual Consumption | 12.0 M MMBtu |
Ranked #670 out of 11,852 Power Plants Nationwide | |
Ranked #412 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #8 out of 56 North Dakota Power Plants | |
Ranked #2 out of 6 North Dakota Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Lonesome Creek Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lonesome Creek Station.
Monthly Net Generation for Lonesome Creek Station
Lonesome Creek Station Details
Summary Information | |
---|---|
Plant Name | Lonesome Creek Station (57943) |
Plant Address | 2648 140th Ave NW, Alexander, ND 58831 |
Utility | Basin Electric Power Coop (1307) |
Latitude, Longitude | 47.79667, -103.57861 |
Generation Dates on File | Nov 2013 to Dec 2023 |
Initial Operation Date | November 2013 |
Annual Generation | 1.2 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | McKenzie Electric Coop Inc (12087) ND |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | NORTHERN BORDER P L CO |
Natural Gas Storage | No |
Generator 01 Details Operating November 2013
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG1_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS1 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2013 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 02 Details Operating January 2015
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG2_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS2 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2015 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 03 Details Operating January 2015
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG3_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS3 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2015 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 04 Details Operating May 2017
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG4_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS4 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2017 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 05 Details Operating May 2017
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG5_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS5 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2017 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 06 Details Operating October 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUELONESMCKUNG6_UNIT_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAUE.BEPM.LCS6 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 40 MW |
Winter Capacity | 45 MW |
Minimum Load | 30 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 2021 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Lonesome Creek Station Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#402 | Riverton | Riverton, KS | 1.2 TWh |
#403 | Sim Gideon | Bastrop, TX | 1.2 TWh |
#404 | ExxonMobil Baytown Refinery | Baytown, TX | 1.2 TWh |
#405 | Armstrong | Shelocta, PA | 1.2 TWh |
#406 | Panoche Energy Center | Firebaugh, CA | 1.2 TWh |
#407 | Palomar Energy | Escondido, CA | 1.2 TWh |
#408 | Grays Ferry Cogeneration | Philadelphia, PA | 1.2 TWh |
#409 | Port Westward Unit 2 | Clatskanie, OR | 1.2 TWh |
#410 | Big Sandy | Louisa, KY | 1.2 TWh |
#411 | E F Barrett | Island Park, NY | 1.2 TWh |
#413 | Graham | Graham, TX | 1.2 TWh |
#414 | Tiger Bay | Ft. Meade, FL | 1.1 TWh |
#415 | Shell Deer Park | Deer Park, TX | 1.4 TWh |
#416 | Air Products Port Arthur | Port Arthur, TX | 1.2 TWh |
#417 | Riverside (OK) | Jenks, OK | 1.1 TWh |
#418 | Wilkes | Avinger, TX | 1.1 TWh |
#419 | Johnson County | Cleburne, TX | 1.1 TWh |
#420 | Bowline Point | West Haverstraw, NY | 1.1 TWh |
#421 | Cope | Cope, SC | 1.6 TWh |
#422 | Little Gypsy | La Place, LA | 1.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lonesome Creek Station.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Antelope Valley | Beulah, ND | 5.1 TWh | 86.4 mi |
Aurora Wind Project | Tioga, ND | 1.0 TWh | 68 mi |
Brady II Wind Energy Center | Dickinson, ND | 634.1 GWh | 89.9 mi |
Brady Wind Energy Center | Dickinson, ND | 615.5 GWh | 88.2 mi |
Burke Wind, LLC | Bowbells, ND | 813.0 GWh | 79.1 mi |
Cedar Hills Wind Farm | Rhame, ND | 52.3 GWh | 107.5 mi |
Coyote | Beulah, ND | 2.3 TWh | 91.4 mi |
Culbertson Generation Station | Culbertson, MT | 316.6 GWh | 47.2 mi |
Diamond Willow Wind Facility | Baker, MT | 82.1 GWh | 108.9 mi |
Glen Ullin Energy Center | Glen Ullin, ND | 443.0 GWh | 100.5 mi |
Glen Ullin Station 6 | Glen Ullin, ND | 38.0 GWh | 108.8 mi |
Glendive GT | Glendive, MT | 1.5 GWh | 74.7 mi |
Lewis & Clark | Richland, MT | 12.7 GWh | 28.1 mi |
Lindahl Wind Project, LLC | Tioga, ND | 546.2 GWh | 58.9 mi |
OREG 1 Inc | Culbertson, MT | 147.0 GWh | 47.6 mi |
OREG 2 Inc | Culbertson, MT | 106.4 GWh | 47.6 mi |
Pioneer Generation Station | Williston, ND | 1.5 TWh | 34.7 mi |
Sidney MT Plant | Sidney, MT | 4.4 GWh | 26.4 mi |
Sunflower Wind Project | Mandan, ND | 433.2 GWh | 96.7 mi |
Thunder Spirit Wind, LLC | Hettinger, ND | 487.7 GWh | 128.2 mi |