Logan City
351 W. 300 S., Logan, UT 84321Plant Summary Information
Logan City is ranked #17 out of 23 natural gas power plants in Utah in terms of total annual net electricity generation.
Logan City is comprised of 3 generators and generated 2.5 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Logan City |
---|---|
Utility Name | City of Logan - (UT) |
Location | Cache County, UT |
Initial Operation Date | July 2002 |
Last Update | Dec 2023 |
Annual Generation | 10.7 GWh |
Annual Consumption | 156.8 k MMBtu |
Ranked #5,797 out of 11,835 Power Plants Nationwide | |
Ranked #1,565 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #72 out of 121 Utah Power Plants | |
Ranked #17 out of 23 Utah Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Logan City
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Logan City.
Monthly Net Generation for Logan City
Logan City Details
Summary Information | |
---|---|
Plant Name | Logan City (4251) |
Plant Address | 351 W. 300 S., Logan, UT 84321 |
Utility | City of Logan - (UT) (11135) |
Latitude, Longitude | 41.72583, -111.8433 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | July 2002 |
Annual Generation | 10.7 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Logan - (UT) (11135) UT |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | QUESTAR GAS COMPANY |
Natural Gas Storage | No |
Generator 1 Details Operating July 2002
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 4.5 MW |
Winter Capacity | 5.2 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2002 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating July 2002
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 4.5 MW |
Winter Capacity | 5.2 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2002 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 3 Details Operating July 2002
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 4.5 MW |
Winter Capacity | 5.2 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2002 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Logan City Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1555 | Hancock | Commerce Twp, MI | 11.1 GWh |
#1556 | Regeneron Tarrytown | Tarrytown, NY | 11.0 GWh |
#1557 | Clifton | Clifton, KS | 11.0 GWh |
#1558 | Ivanpah 1 | Nipton, CA | 230.3 GWh |
#1559 | SCU000 El Camino Real Fuel Cell | Santa Clara, CA | 10.9 GWh |
#1560 | Coffeyville | Coffeyville, KS | 10.9 GWh |
#1561 | CH Resources Syracuse | Solvay, NY | 10.8 GWh |
#1562 | Lake One | Burbank, CA | 10.8 GWh |
#1563 | Foxwoods CoGen | Mashantucket, CT | 10.8 GWh |
#1564 | San Antonio Regional Hospital | Upland, CA | 10.7 GWh |
#1566 | Leaf River Cellulose LLC | New Augusta, MS | 422.9 GWh |
#1567 | OLS Energy Chino | Chino, CA | 10.7 GWh |
#1568 | Sycamore (IA) | Johnston, IA | 10.7 GWh |
#1569 | Santa Rita Jail Hybrid | Dublin, CA | 13.1 GWh |
#1570 | Borger Plant | Borger, TX | 45.6 GWh |
#1571 | Gowanus Gas Turbines Generating | Brooklyn, NY | 11.3 GWh |
#1572 | Holcomb | Holcomb, KS | 1.2 TWh |
#1573 | Malaga Power LLC | Fresno, CA | 10.5 GWh |
#1574 | UB Fuel Cell | Bridgeport, CT | 10.5 GWh |
#1575 | South District Wastewater Treatment Plt | Miami, FL | 21.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Logan City.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bountiful City | Bountiful, UT | 21.4 GWh | 58 mi |
Brigham City | Brigham, UT | 7.8 GWh | 17.3 mi |
Causey | South Fork, UT | 5.5 GWh | 32.4 mi |
Central Energy Plant USU | Logan, UT | 31.3 GWh | 2.3 mi |
Cutler Hydro | Collinston, UT | 96.2 GWh | 13.1 mi |
Echo Dam | Echo, UT | 12.9 GWh | 56.7 mi |
Gateway | Mountain Green, UT | 15.9 GWh | 40.7 mi |
Grace | Grace, ID | 72.9 GWh | 56.1 mi |
Hill AFB LFG Facility, Bldg #737 | Hill AFB, UT | 9.5 GWh | 41.7 mi |
Hydro II | Logan, UT | 17.9 GWh | 3.3 mi |
Mink Creek Hydro | Preston, ID | 10.5 GWh | 38.1 mi |
Oneida | Riverdale, ID | 42.4 GWh | 37.8 mi |
Pine View Dam | Ogden, UT | 4.4 GWh | 32.6 mi |
Pioneer | Ogden, UT | 18.7 GWh | 33.7 mi |
Rocket Solar, LLC | Corinne, UT | 140.0 GWh | 31.6 mi |
Sage Solar I-III | Randolph, UT | 135.3 GWh | 40.5 mi |
SF Auto T1 | Tremonton, UT | 141.0 MWh | 17.3 mi |
Steel Solar LLC | Plymouth, UT | 69.2 GWh | 20.6 mi |
Weber | South Weber, UT | 9.5 GWh | 40.7 mi |
Weber State University - Davis Campus PV | Layton, UT | 2.5 GWh | 43.9 mi |