Lockwood Hydroelectric Facility
Water Street, Waterville, ME 4901Plant Summary Information
Lockwood Hydroelectric Facility is ranked #29 out of 50 hydroelectric power plants in Maine in terms of total annual net electricity generation.
Lockwood Hydroelectric Facility is comprised of 7 generators and generated 5.6 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Lockwood Hydroelectric Facility |
---|---|
Utility Name | Merimil Ltd Partnership |
Location | Kennebec County, ME |
Initial Operation Date | October 1985 |
Last Update | Dec 2023 |
Annual Generation | 23.7 GWh |
Annual Consumption | 88.2 k MMBtu |
Ranked #4,844 out of 11,835 Power Plants Nationwide | |
Ranked #711 out of 1,371 Water Power Plants Nationwide | |
Ranked #67 out of 161 Maine Power Plants | |
Ranked #29 out of 50 Maine Water Power Plants | |
Fuel Types | Water |
Map of Lockwood Hydroelectric Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lockwood Hydroelectric Facility.
Monthly Net Generation for Lockwood Hydroelectric Facility
Lockwood Hydroelectric Facility Details
Summary Information | |
---|---|
Plant Name | Lockwood Hydroelectric Facility (10066) |
Plant Address | Water Street, Waterville, ME 4901 |
Utility | Merimil Ltd Partnership (12401) |
Latitude, Longitude | 44.5467, -69.6292 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | October 1985 |
Annual Generation | 23.7 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 84-38-001 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | ISO New England Inc. (ISNE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Kennebec River |
Ash Impoundment | No |
Transmission / Distribution Owner | Central Maine Power Co (3266) ME |
Grid Voltage | 34.00 kV |
Energy Storage | No |
Generator GEN1 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator GEN2 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator GEN3 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator GEN4 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN5 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN6 Details Operating October 1985
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1985 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN7 Details Operating October 1988
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 2.4 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 2.2 MW |
Winter Capacity | 2.2 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1988 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Lockwood Hydroelectric Facility Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#701 | Georgia-Pacific Corp - Nekoosa Mill | Nekoosa, WI | 173.0 GWh |
#702 | Sacramento Municipal Util Dist | Sacramento, CA | 24.4 GWh |
#703 | Wailuku River Hydroelectric | Hilo, HI | 24.4 GWh |
#704 | Shoshone (CO) | Glenwood Springs, CO | 24.3 GWh |
#705 | Biron | Biron, WI | 24.3 GWh |
#706 | Opal Springs Hydro | Culver, OR | 24.2 GWh |
#707 | Menomonie | Menomonie, WI | 24.2 GWh |
#708 | Oswego Falls East | Fulton, NY | 24.2 GWh |
#709 | Lighthouse Hill | Altmar, NY | 24.2 GWh |
#710 | Stevens Point | Stevens Point, WI | 24.1 GWh |
#712 | Whiskeytown | Whiskeytown, CA | 23.5 GWh |
#713 | Deer Creek (UT) | Heber, UT | 23.4 GWh |
#714 | Rogers | Big Rapids, MI | 23.3 GWh |
#715 | Varick | Oswego, NY | 23.2 GWh |
#716 | Fairfax Falls | Fairfax, VT | 23.2 GWh |
#717 | Red Mountain | Fallbrook, CA | 23.1 GWh |
#718 | Byllesby 2 | Ivanhoe, VA | 22.9 GWh |
#719 | West End Dam Hydroelectric Project | Carthage, NY | 22.8 GWh |
#720 | Watertown | Watertown, NY | 22.8 GWh |
#721 | Wausau | Wausau, WI | 22.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lockwood Hydroelectric Facility.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Barefoot Solar | Fairfiled, ME | 4.1 GWh | 3.6 mi |
Beaver Ridge Wind | Freedom, ME | 10.3 GWh | 14.2 mi |
Benton Falls Associates | Benton, ME | 17.3 GWh | 4.3 mi |
Cenergy - Richards (CSG) | Fairfield, ME | 220.0 MWh | 6.8 mi |
Cenergy - Waterville (CSG) | Waterville, ME | 1.8 GWh | 2 mi |
Fairfield PV - BD Solar Fairfield LLC | Fairfield, ME | 8.2 GWh | 6.2 mi |
Hydro Kennebec Project | Winslow, ME | 69.6 GWh | 1.2 mi |
Messalonskee 2 (Oakland) | Oakland, ME | 12.9 GWh | 4 mi |
Messalonskee 3 | Oakland, ME | 7.3 GWh | 3 mi |
Messalonskee 5 | Waterville, ME | 5.1 GWh | 1.4 mi |
Oakland | Oakland, ME | 8.0 GWh | 3.5 mi |
Shawmut | Shawmut, ME | 36.7 GWh | 6.1 mi |
Sidney | Sidney, ME | 1.4 GWh | 8.2 mi |
Solar Mule, LLC | Oakland, ME | 2.0 GWh | 2.2 mi |
Somerset Plant | Skowhegan, ME | 485.5 GWh | 10.9 mi |
Three Corners Solar | Unity, ME | 48.3 GWh | 9.8 mi |
Unity Solar | Unity, ME | 7.3 GWh | 13.9 mi |
Waste Management Crossroads LFGTE | Norridgewock, ME | 19.5 GWh | 14.6 mi |
Webb Road Solar | Waterville, ME | 4.7 GWh | 3.6 mi |
Winslow PV - BD Solar 2 LLC | Winslow, ME | 10.9 GWh | 2.1 mi |