Linden Cogen Plant
RR & Chemico Ave, Linden, NJ 7036Plant Summary Information
Linden Cogen Plant is ranked #3 out of 378 power plants in New Jersey in terms of total annual net electricity generation.
Linden Cogen Plant is comprised of 9 generators and generated 1.5 TWh during the 3-month period between May 2024 to August 2024.
Plant Name | Linden Cogen Plant |
---|---|
Utility Name | EFS Cogen Holdings I LLC |
Location | Union County, NJ |
Initial Operation Date | March 1992 |
Last Update | Aug 2024 |
Annual Generation | 5.9 TWh |
Annual Consumption | 60.5 M MMBtu |
Ranked #170 out of 11,835 Power Plants Nationwide | |
Ranked #78 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #3 out of 378 New Jersey Power Plants | |
Ranked #1 out of 55 New Jersey Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.4% Other Gas : 0.6% |
Map of Linden Cogen Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Linden Cogen Plant.
Monthly Net Generation for Linden Cogen Plant
Linden Cogen Plant Details
Summary Information | |
---|---|
Plant Name | Linden Cogen Plant (50006) |
Plant Address | RR & Chemico Ave, Linden, NJ 7036 |
Utility | EFS Cogen Holdings I LLC (3890) |
Latitude, Longitude | 40.6322, -74.2156 |
Generation Dates on File | Jan 2001 to Aug 2024 |
Initial Operation Date | March 1992 |
Annual Generation | 5.9 TWh |
Fuel Types | Natural Gas : 99.4% Other Gas : 0.6% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 90-65-014 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 90-65-014 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP CHP (3) |
Water Source | NA |
Ash Impoundment | No |
Transmission / Distribution Owner | Consolidated Edison Co-NY Inc (4226) NY |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name |
TRANSCONTINENTAL GAS PIPELINE Other - Please explain in pipeline notes below. |
Pipeline Notes | Texas Eastern Transmission Corporation |
Natural Gas Storage | No |
Generator GTG1 Details Operating March 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 47.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 94.62 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 94.5 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator GTG2 Details Operating March 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 47.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 94.62 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 94.5 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator GTG4 Details Operating March 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 47.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 94.62 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 94.5 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator STG1 Details Operating March 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 25 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG2 Details Operating March 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 25 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GTG3 Details Operating April 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 47.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 94.62 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 94.5 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator GTG5 Details Operating April 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.7 MW |
Winter Capacity | 100.8 MW |
Minimum Load | 47.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 94.62 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 94.5 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator STG3 Details Operating April 1992
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 95.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 98.6 MW |
Winter Capacity | 101.2 MW |
Minimum Load | 25 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 1992 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Waste/Other Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GTG6 Details Operating January 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 212.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 164.8 MW |
Winter Capacity | 202.9 MW |
Minimum Load | 80 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2002 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 165.1 MW |
Net Winter Capacity With Natural Gas | 184.2 MW |
Net Summer Capacity With Oil | 160.3 MW |
Net Winter Capacity With Oil | 191.8 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Linden Cogen Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#68 | Lake Side Power Plant | Vineyard, UT | 6.1 TWh |
#69 | Santan | Gilbert, AZ | 6.0 TWh |
#70 | Hamilton Liberty | Towanda, PA | 6.0 TWh |
#71 | Montgomery County | Willis, TX | 6.0 TWh |
#72 | Midlothian Energy Facility | Midlothian, TX | 6.0 TWh |
#73 | Taft Cogeneration Facility | Hahnville, LA | 6.0 TWh |
#74 | Acadia Energy Center | Eunice, LA | 5.9 TWh |
#75 | Lake Charles Power | West Lake, LA | 5.9 TWh |
#76 | Hickory Run Energy Station | New Castle, PA | 5.9 TWh |
#77 | W S Lee | Williamston, SC | 5.9 TWh |
#79 | Lamar Power Project | Paris, TX | 5.7 TWh |
#80 | Doswell Energy Center | Ashland, VA | 5.7 TWh |
#81 | Oneta Energy Center | Broken Arrow, OK | 5.7 TWh |
#82 | Belews Creek | Belews Creek, NC | 8.6 TWh |
#83 | Lake Road Generating Plant | Dayville, CT | 5.7 TWh |
#84 | St Joseph Energy Center | New Carlisle, IN | 5.6 TWh |
#85 | Cottonwood Energy Project | Deweyville, TX | 5.6 TWh |
#86 | Zeeland Generating Station | Zeeland, MI | 5.6 TWh |
#87 | E B Harris Electric Generating Plant | Autaugaville, AL | 5.5 TWh |
#88 | Channelview Cogeneration Plant | Channelview, TX | 5.5 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Linden Cogen Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Allied Beverages Elizabeth | Elizabeth, NJ | 5.4 GWh | 3.1 mi |
Amazon JFK8 Solar Project | Staten Island, NY | 460.0 MWh | 1.7 mi |
Arthur Kill Generating Station | Staten Island, NY | 1.1 TWh | 2.9 mi |
Bay Avenue CDG | Elizabeth, NJ | 56.0 MWh | 4.2 mi |
Bayway Refinery | Linden, NJ | 70.1 GWh | 0.5 mi |
Community Foodbank of NJ | Hillside, NJ | 950.0 MWh | 4.5 mi |
DG Infineum | Linden, NJ | 2.5 GWh | 1.2 mi |
Elizabeth Seaport Bldg A Solar | Elizabeth, NJ | 2.0 GWh | 3.3 mi |
IGS Solar I - EWR5 | Avenel, NJ | 903.0 MWh | 4 mi |
IGS Solar I - EWR6 | Avenel, NJ | 801.0 MWh | 4 mi |
IOS - ERW9 | Carteret, NJ | 5.1 GWh | 2.6 mi |
Jersey Gardens Phase 1 | Elizabeth, NJ | 1.9 GWh | 3 mi |
Jersey Gardens Phase 2 | Elizabeth, NJ | 2.3 GWh | 3 mi |
Kenilworth Energy Facility | Kenilworth, NJ | 152.8 GWh | 4.4 mi |
Linden Hawk Rise Solar CSG | Linden, NJ | 6.2 GWh | 2.5 mi |
Linden Solar Farm | Linden, NJ | 3.8 GWh | 0.8 mi |
Merck Rahway Power Plant | Rahway, NJ | 42.8 GWh | 2.8 mi |
Ports Newark 8201 Solar | Newark, NJ | 14.0 MWh | 4.2 mi |
PSEG Linden Generating Station | Linden, NJ | 5.2 TWh | 0.8 mi |
Union County Resource Recovery | Rahway, NJ | 303.8 GWh | 3.4 mi |