Limelight Solar II LLC
2600 Cannons Campground Road, Spartanburg, SC 29307Plant Summary Information
Limelight Solar II LLC is ranked #96 out of 107 solar farms in South Carolina in terms of total annual net electricity generation.
Limelight Solar II LLC generated 783.7 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Limelight Solar II LLC |
---|---|
Utility Name | Limelight Solar II LLC |
Location | Spartanburg County, SC |
Initial Operation Date | December 2019 |
Last Update | Dec 2022 |
Annual Generation | 3.2 GWh |
Annual Consumption | 11.7 k MMBtu |
Ranked #8,657 out of 11,249 Power Plants Nationwide | |
Ranked #3,600 out of 5,158 Solar Power Plants Nationwide | |
Ranked #158 out of 189 South Carolina Power Plants | |
Ranked #96 out of 107 South Carolina Solar Power Plants | |
Fuel Types | Solar |
Map of Limelight Solar II LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Limelight Solar II LLC.
Monthly Net Generation for Limelight Solar II LLC
Limelight Solar II LLC Details
Summary Information | |
---|---|
Plant Name | Limelight Solar II LLC (63241) |
Plant Address | 2600 Cannons Campground Road Spartanburg, SC 29307 |
Utility | Limelight Solar II LLC (63016) |
Latitude, Longitude | 34.99389, -81.87819 |
Generation Dates on File | Dec 2019 to Dec 2022 |
Initial Operation Date | December 2019 |
Annual Generation | 3.2 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF17-1045 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Carolinas (DUK) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Duke Energy Carolinas, LLC (5416) NC |
Grid Voltage | 23.90 kV |
Energy Storage | No |
Generator SCLL Details Operating December 2019
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 2 MW |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 25 |
DC Net Capacity | 2.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Limelight Solar II LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3590 | Time Warner Cable Enterprises - Martino | Rome, NY | 3.2 GWh |
#3591 | Limerick Road Solar Farm | Shelburne, VT | 3.2 GWh |
#3592 | Villa Roma Rd #1 | Delaware, NY | 3.2 GWh |
#3593 | IMPA Pendleton Solar Park | Pendleton, IN | 3.2 GWh |
#3594 | Amsterdam South | Amsterdam, NY | 3.2 GWh |
#3595 | Deer Creek 2 | Shingle Springs, CA | 3.2 GWh |
#3596 | Tulare 1 and 2 | Tulare, CA | 3.2 GWh |
#3597 | Hinsdale Solar PV | Hinsdale, MA | 3.2 GWh |
#3598 | Hadley 2 Solar, LLC CSG | Hadley, MA | 3.2 GWh |
#3599 | GSPP Devens, LLC | Ayer, MA | 3.2 GWh |
#3601 | Rose Hill | Rose Hill, NC | 3.2 GWh |
#3602 | Ashby Solar, LLC CSG | Fitchburg, MA | 3.2 GWh |
#3603 | Griffith | Griffith, IN | 3.2 GWh |
#3604 | Carver CSG | Carver, MA | 3.2 GWh |
#3605 | Lawrence Brook | Morristown, VT | 3.2 GWh |
#3606 | ENGIE 2020 ProjectCo-WI1 LLC | Fond Du Lac, WI | 3.2 GWh |
#3607 | Concord Farm | Concord, NC | 3.2 GWh |
#3608 | Timonium Fairgrounds | Timonium, MD | 3.2 GWh |
#3609 | ESA Smithfield | Smithfield, NC | 3.2 GWh |
#3610 | Gilead Sciences La Verne Rooftop Solar | La Verne, CA | 3.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Limelight Solar II LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AGA TAG Solar III LLC | Spartanburg, SC | 4.1 GWh | 9.3 mi |
Atood II | Cowpens, SC | 4.4 GWh | 4.7 mi |
ATOOD Solar III LLC | Spartanburg, SC | 3.7 GWh | 9.3 mi |
Ballenger Road Solar A | Inman, SC | 4.0 GWh | 13.7 mi |
Beetle Solar | Mooresboro, NC | 6.6 GWh | 17.5 mi |
BMW Manufacturing Co | Greer, SC | 34.4 GWh | 18.3 mi |
Broad River Energy Center | Gaffney, SC | 315.0 GWh | 18.1 mi |
Broad River Solar, LLC | Mooresboro, NC | 103.0 GWh | 15.2 mi |
Charlotte Solar | Forest City, NC | 9.2 GWh | 18.8 mi |
Cherokee County Cogen | Gaffney, SC | 450.0 GWh | 16 mi |
Clifton Dam 3 Power Station | Converse, SC | 4.3 GWh | 2.5 mi |
Gaston Shoals | Blacksburg, SC | 21.7 GWh | 18.7 mi |
James E. Rogers Energy Complex | Cliffside, NC | 5.8 TWh | 17 mi |
Limelight Solar I, LLC | Spartanburg, SC | 3.9 GWh | 6.9 mi |
Limelight Solar III, LLC | Spartanburg, SC | 7.5 GWh | 6.3 mi |
Mohea Solar Energy Center, LLC | Gaffney, SC | 8.0 GWh | 15.8 mi |
Rutherford Farm | Forest City, NC | 151.6 GWh | 18.4 mi |
Spartanburg Water System | Chesnee, SC | 2.4 GWh | 9.5 mi |
Upper Pacolet Hydro | Pacolet, SC | 5.2 GWh | 9 mi |
Wellford Renewable Energy Plant | Spartanburg, SC | 309.0 MWh | 14.3 mi |