Lily Solar Hybrid
7901 FM 1390, Scurry, TX 75158Plant Summary Information
Lily Solar Hybrid is ranked #46 out of 161 solar farms in Texas in terms of total annual net electricity generation.
Lily Solar Hybrid generated 113.1 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Lily Solar Hybrid |
---|---|
Utility Name | Lily Solar, LLC |
Location | Kaufman County, TX |
Initial Operation Date | September 2021 |
Last Update | Aug 2024 |
Annual Generation | 315.7 GWh |
Annual Consumption | 1.2 M MMBtu |
Ranked #1,778 out of 11,835 Power Plants Nationwide | |
Ranked #142 out of 5,643 Solar Power Plants Nationwide | |
Ranked #332 out of 749 Texas Power Plants | |
Ranked #46 out of 161 Texas Solar Power Plants | |
Fuel Types | Solar |
Map of Lily Solar Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lily Solar Hybrid.
Monthly Net Generation for Lily Solar Hybrid
Lily Solar Hybrid Details
Summary Information | |
---|---|
Plant Name | Lily Solar Hybrid (63892) |
Plant Address | 7901 FM 1390, Scurry, TX 75158 |
Utility | Lily Solar, LLC (63549) |
Latitude, Longitude | 32.53327, -96.42899 |
Generation Dates on File | Jun 2021 to Aug 2024 |
Initial Operation Date | September 2021 |
Annual Generation | 315.7 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Rayburn Country Elec Coop, Inc (18589) TX |
Grid Voltage | 138.00 kV |
Energy Storage | Yes |
Generator LILY Details Operating October 2021
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 146.7 MW |
Summer Capacity | 146.7 MW |
Winter Capacity | 146.7 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Time From Cold Shutdown To Full Load | 1H |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Dual Axis Tracking | No |
Bifacial | Yes |
Azimuth Angle | 90 |
Tilt Angle | 90 |
DC Net Capacity | 180.9 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator LILYB Details Operating October 2021
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 50 MW |
Summer Capacity | 50 MW |
Winter Capacity | 50 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 80.5 |
---|---|
Maximum Charge Rate | 50 MW |
Maximum Discharge Rate | 50 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 75 |
Storage Enclosure Type | CS |
Arbitrage | P |
Frequency Regulation | Yes |
Voltage Or Reactive Power Support | Yes |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Lily Solar Hybrid Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#132 | McFarland A Solar and Storage | Dateland, AZ | 324.3 GWh |
#133 | Newport Solar Project | Newport, AR | 330.0 GWh |
#134 | Texas Solar Nova 2 | Spur, TX | 328.9 GWh |
#135 | Campo Verde Solar | El Centro, CA | 328.6 GWh |
#136 | CA Flats Solar 150, LLC | Shandon, CA | 327.9 GWh |
#137 | American Kings Solar, LLC | Lemoore, CA | 323.7 GWh |
#138 | Quitman II Solar | Quitman, GA | 322.4 GWh |
#139 | Fort Powhatan Solar | Disputanta, VA | 320.2 GWh |
#140 | ANSON Solar Center, LLC | Anson, TX | 318.9 GWh |
#141 | Horizon Solar | Pearsall, TX | 317.8 GWh |
#143 | Cove Mountain Solar 2 | Beryl, UT | 317.3 GWh |
#144 | Oak Ridge Solar | Oak Ridge, LA | 313.8 GWh |
#145 | Maverick Solar 7, LLC | Desert Center, CA | 312.8 GWh |
#146 | Edwards Sanborn E2 | Mojave, CA | 294.1 GWh |
#147 | Big Cypress Solar, LLC | Crawfordsville, AR | 311.3 GWh |
#148 | Elora Solar | Elora, TN | 309.7 GWh |
#149 | Bernard Creek Solar | Hungerford, TX | 309.3 GWh |
#150 | Sun Streams 2 | Hassayampa, AZ | 309.0 GWh |
#151 | SR DeSoto I, LLC | DeSoto, GA | 308.4 GWh |
#152 | Pike Solar Hybrid | Fountain, CO | 307.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lily Solar Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Ameresco Dallas LLC | Dallas, TX | 27.8 GWh | 14.9 mi |
Briar Creek Solar 1 | Corsicana, TX | 235.0 GWh | 33.5 mi |
Ellis Solar LLC | Midlothian, TX | 122.1 GWh | 36.7 mi |
Elm Branch Solar 1 | Bardwell, TX | 287.2 GWh | 26.3 mi |
Ennis Power Company LLC | Ennis, TX | 1.4 TWh | 20.6 mi |
Forney Energy Center | Forney, TX | 9.9 TWh | 15.8 mi |
Lake Hubbard | Sunnyvale, TX | 899.7 GWh | 22 mi |
Midlothian Energy Facility | Midlothian, TX | 6.0 TWh | 37.1 mi |
Mountain Creek | Dallas, TX | 654.1 GWh | 32.3 mi |
OTHERBenEKDallas | Dallas, TX | 107.0 MWh | 31.6 mi |
Ray Olinger | Navada, TX | 117.4 GWh | 37 mi |
Trinidad (TX) | Trinidad, TX | 330.6 GWh | 34.1 mi |
Verizon Hidden Ridge Solar Project | Irving, TX | 3.0 MWh | 38.6 mi |
WAL2667 | Dallas, TX | 62.0 MWh | 23.5 mi |
WAL3224 | Garland, TX | 268.0 MWh | 23.5 mi |
WAL3285 | Cedar Hill, TX | 371.0 MWh | 30.5 mi |
WAL3406 | Dallas, TX | 291.0 MWh | 37.1 mi |
WAL3432 | Desoto, TX | 218.0 MWh | 26.6 mi |
WAL565 | Corsicana, TX | 249.0 MWh | 29.9 mi |
WAL896 | Grand Prairie, TX | 352.0 MWh | 36.6 mi |