LCEC Generation LLVC
2023 Power Plant Lane, Lovington, NM 88260Plant Summary Information
LCEC Generation LLVC is ranked #17 out of 19 natural gas power plants in New Mexico in terms of total annual net electricity generation.
LCEC Generation LLVC is comprised of 5 generators and generated 10.4 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | LCEC Generation LLVC |
---|---|
Utility Name | Western Farmers Elec Coop, Inc |
Location | Lea County, NM |
Initial Operation Date | February 2012 |
Last Update | Dec 2023 |
Annual Generation | 44.1 GWh |
Annual Consumption | 501.6 k MMBtu |
Ranked #4,023 out of 11,835 Power Plants Nationwide | |
Ranked #1,133 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #60 out of 137 New Mexico Power Plants | |
Ranked #17 out of 19 New Mexico Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
LCEC Generation LLC (2013 to 2013) Western Farmers Elec Coop, Inc (2014 to 2023) |
Map of LCEC Generation LLVC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for LCEC Generation LLVC.
Monthly Net Generation for LCEC Generation LLVC
LCEC Generation LLVC Details
Summary Information | |
---|---|
Plant Name | LCEC Generation LLVC (57872) |
Plant Address | 2023 Power Plant Lane, Lovington, NM 88260 |
Utility | Western Farmers Elec Coop, Inc (20447) |
Latitude, Longitude | 32.97806, -103.32389 |
Generation Dates on File | Feb 2012 to Dec 2023 |
Initial Operation Date | February 2012 |
Annual Generation | 44.1 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Lea County Electric Coop, Inc (10817) NM |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | NEW MEXICO GAS COMPANY |
Natural Gas Storage | No |
Generator UNIT1 Details Operating February 2012
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WFEC_LC_GAS_PLANT |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WFEC_LC_GAS_PLANT |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator UNIT2 Details Operating February 2012
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WFEC_LC_GAS_PLANT |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WFEC_LC_GAS_PLANT |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator UNIT3 Details Operating February 2012
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WFEC_LC_GAS_PLANT |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WFEC_LC_GAS_PLANT |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator UNIT4 Details Operating February 2012
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WFEC_LC_GAS_PLANT |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WFEC_LC_GAS_PLANT |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator UNIT5 Details Operating February 2012
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WFEC_LC_GAS_PLANT |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WFEC_LC_GAS_PLANT |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
LCEC Generation LLVC Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1123 | Marshall Energy Facility | Calvert City, KY | 46.0 GWh |
#1124 | California Institute of Technology | Pasadena, CA | 45.5 GWh |
#1125 | Glass House Camarillo Cultivation | Camarillo, CA | 45.4 GWh |
#1126 | Feather River Energy Center | Yuba City, CA | 45.2 GWh |
#1127 | Blacksand Generating Facility | Brea, CA | 45.1 GWh |
#1128 | Ormond Beach | Oxnard, CA | 44.9 GWh |
#1129 | Otter Creek Ethanol Poet - Ashton | Ashton, IA | 44.8 GWh |
#1130 | R M Schahfer | Wheatfield, IN | 1.7 TWh |
#1131 | Harrington | Amarillo, TX | 2.4 TWh |
#1132 | Coalinga Cogeneration Facility | Coalinga, CA | 44.4 GWh |
#1134 | Aberdeen CT | Aberdeen, SD | 44.3 GWh |
#1135 | South Energy Center | Gainesville, FL | 44.0 GWh |
#1136 | Osawatomie | Miami, KS | 44.0 GWh |
#1137 | Bristol Myers Squibb Lawrenceville | Lawrenceville, NJ | 43.9 GWh |
#1138 | Hartford Hospital Cogeneration | Hartford, CT | 43.8 GWh |
#1139 | Tres City Power LLC | Victoria, TX | 43.4 GWh |
#1140 | Hibbing | Hibbing, MN | 68.3 GWh |
#1141 | Fuel Cell 3245 Yates Avenue | Bronx, NY | 43.3 GWh |
#1142 | Lawrence County Station | Mitchell, IN | 43.2 GWh |
#1143 | NCSU CCUP Cogeneration Plant | Raleigh, NC | 43.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding LCEC Generation LLVC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Anderson Wind I | Hagerman, NM | 17.6 GWh | 31 mi |
Anderson Wind II | Hagerman, NM | 35.2 GWh | 31.5 mi |
Cunningham | Hobbs, NM | 1.7 TWh | 18.4 mi |
Frankel | Andrews, TX | 645.0 MWh | 51.9 mi |
Hobbs Generating Station | Hobbs, NM | 3.5 TWh | 17.3 mi |
Jumbo Hill Wind Project | Andrews, TX | 588.6 GWh | 46.4 mi |
Lapetus | Andrews, TX | 184.7 GWh | 52.1 mi |
Maddox | Hobbs, NM | 659.1 GWh | 18.3 mi |
Middle Daisy | Lovington, NM | 7.3 GWh | 2.7 mi |
Mustang Station | Denver City, TX | 2.1 TWh | 33.7 mi |
Mustang Station Unit 4 | Denver City, TX | 853.8 GWh | 33.6 mi |
Oso Grande Wind Farm | Maljamar, NM | 540.3 GWh | 20.1 mi |
Prospero Solar | Andrews, TX | 746.0 GWh | 55.4 mi |
SPS2 Jal | Jal, NM | 18.9 GWh | 55.5 mi |
SPS3 Lea | Eunice, NM | 23.0 GWh | 35.1 mi |
SPS4 Monument | Monument, NM | 22.3 GWh | 20.5 mi |
Sterling I Wind Farm | Tatum, NM | 116.5 GWh | 26.7 mi |
Wasson CO2 Removal Plant | Denver City, TX | 137.2 GWh | 32.9 mi |
Wildcat Ranch Wind Project | Morton, TX | 663.2 GWh | 43.5 mi |
Wildcat Wind | Lovington, NM | 56.5 GWh | 2.8 mi |