Las Lomas Wind Project
TBD, Falcon, TX 78564Plant Summary Information
Las Lomas Wind Project is ranked #105 out of 218 wind farms in Texas in terms of total annual net electricity generation.
Las Lomas Wind Project generated 102.8 GWh during the 3-month period between July 2024 to October 2024.
Plant Name | Las Lomas Wind Project |
---|---|
Utility Name | Engie North America |
Location | Zapata County, TX |
Initial Operation Date | December 2020 |
Last Update | Oct 2024 |
Annual Generation | 502.9 GWh |
Annual Consumption | 1.9 M MMBtu |
Ranked #1,288 out of 11,866 Power Plants Nationwide | |
Ranked #349 out of 1,345 Wind Power Plants Nationwide | |
Ranked #239 out of 758 Texas Power Plants | |
Ranked #105 out of 218 Texas Wind Power Plants | |
Fuel Types | Wind |
Map of Las Lomas Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Las Lomas Wind Project.
Monthly Net Generation for Las Lomas Wind Project
Las Lomas Wind Project Details
Summary Information | |
---|---|
Plant Name | Las Lomas Wind Project (63101) |
Plant Address | TBD, Falcon, TX 78564 |
Utility | Engie North America (56201) |
Latitude, Longitude | 26.69842, -99.05745 |
Generation Dates on File | Dec 2020 to Oct 2024 |
Initial Operation Date | December 2020 |
Annual Generation | 502.9 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator WTG Details Operating December 2020
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 201.6 MW |
Summer Capacity | 201.6 MW |
Winter Capacity | 201.6 MW |
Minimum Load | 4.2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 48 |
Turbine Details | |
Number Of Turbines | 48 |
---|---|
Predominant Turbine Manufacturer | Goldwind |
Predominant Turbine Model Number | GW155/4200 |
Design Wind Speed | 16.5 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 361 |
Las Lomas Wind Project Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Las Lomas Wind Project, LLC | 1990 Post Oak BLVD., Suite 1900, Houston, TX 77056 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#339 | Panther Creek Wind Farm I | Big Spring, TX | 519.3 GWh |
#340 | Adair Wind Farm | Adair, IA | 518.0 GWh |
#341 | Bobcat Bluff Wind Project LLC | Archer, TX | 517.7 GWh |
#342 | Northern Colorado Wind LLC | Peetz, CO | 517.3 GWh |
#343 | Ironwood Wind | Spearville, KS | 514.3 GWh |
#344 | Limon Wind II | Limon, CO | 513.1 GWh |
#345 | Slate Creek Wind Project LLC | Geuda Springs, KS | 512.0 GWh |
#346 | Osage Wind, LLC | Burbank, OK | 511.9 GWh |
#347 | Elk City LLC | Sweetwater, OK | 508.1 GWh |
#348 | Logan Wind Energy | Peetz, CO | 505.5 GWh |
#350 | Deerfield Wind Energy, LLC | Kinde, MI | 500.9 GWh |
#351 | Ranchland Wind Project II | Cisco, TX | 499.4 GWh |
#352 | Montague Wind Power Facility LLC | Arlington, OR | 496.4 GWh |
#353 | Chickasaw Wind Farm | New Hampton, IA | 495.6 GWh |
#354 | Desert Wind Farm, LLC | Hertford, NC | 495.0 GWh |
#355 | Blue Summit Wind LLC | Vernon, TX | 492.6 GWh |
#356 | Goldthwaite Wind Energy Facility | Goldthwaite, TX | 490.1 GWh |
#357 | Thunder Spirit Wind, LLC | Hettinger, ND | 487.7 GWh |
#358 | Bruennings Breeze Wind Farm | Raymondville, TX | 486.9 GWh |
#359 | Shannon Wind | Windhorst, TX | 486.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Las Lomas Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alexis Solar, LLC | Encino, TX | 17.4 GWh | 52.5 mi |
Citrus City | Mission, TX | 645.0 MWh | 50.8 mi |
Falcon Dam & Power | Falcon Heights, TX | 30.6 GWh | 11.8 mi |
Frontera Energy Center | Mission, TX | 2.0 TWh | 53 mi |
Hidalgo Wind Farm II | Edinburg, TX | 130.2 GWh | 40.2 mi |
Hidalgo Wind Farm LLC | McCook, TX | 673.9 GWh | 43.1 mi |
Javelina Wind Energy II, LLC | MIRANDO, TX | 727.9 GWh | 52 mi |
Javelina Wind Energy, LLC | Mirando City, TX | 794.1 GWh | 43.1 mi |
Los Vientos V Wind Power | Rio Grande City, TX | 334.6 GWh | 36 mi |
Los Vientos Windpower III | Rio Grande City, TX | 461.0 GWh | 26.4 mi |
Los Vientos Windpower IV | Rio Grande City, TX | 472.6 GWh | 26.5 mi |
Magic Valley Generating Station | Edinburg, TX | 2.7 TWh | 59.1 mi |
Mars Solar | Bruni, TX | 23.0 GWh | 51.8 mi |
Mesteno | Rio Grande City, TX | 422.4 GWh | 22.7 mi |
Red Gate Power Plant | Edinburg, TX | 257.4 GWh | 57 mi |
Reloj del Sol Wind Farm | San Ygnacio, TX | 255.1 GWh | 30.7 mi |
Rio Bravo Windpower, LLC | Roma, TX | 326.8 GWh | 3.6 mi |
Sendero | Hebbronville, TX | 272.5 GWh | 34.4 mi |
WAL3320 | Palmhurst, TX | 368.0 MWh | 54.9 mi |
Whitetail | Oilton, TX | 166.7 GWh | 54.7 mi |