Labadie
226 Labadie Power Plant Road, Labadie, MO 63055Plant Summary Information
Labadie is ranked #31 out of 11,852 power plants nationwide in terms of total annual net electricity generation.
Labadie is comprised of 4 generators and generated 4.0 TWh during the 3-month period between June 2024 to September 2024.
Plant Name | Labadie |
---|---|
Utility Name | Union Electric Co - (MO) |
Location | Franklin County, MO |
Initial Operation Date | June 1970 |
Last Update | Sep 2024 |
Annual Generation | 15.5 TWh |
Annual Consumption | 178.5 M MMBtu |
Ranked #31 out of 11,852 Power Plants Nationwide | |
Ranked #2 out of 132 Subbituminous Coal Power Plants Nationwide | |
Ranked #1 out of 120 Missouri Power Plants | |
Ranked #1 out of 9 Missouri Subbituminous Coal Power Plants | |
Fuel Types | Subbituminous Coal : 99.9% |
Map of Labadie
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Labadie.
Monthly Net Generation for Labadie
Labadie Details
Summary Information | |
---|---|
Plant Name | Labadie (2103) |
Plant Address | 226 Labadie Power Plant Road, Labadie, MO 63055 |
Utility | Union Electric Co - (MO) (19436) |
Latitude, Longitude | 38.56224, -90.83769 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | June 1970 |
Annual Generation | 15.5 TWh |
Fuel Types | Subbituminous Coal : 99.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Missouri River |
Ash Impoundment | Yes Lined Operating |
Transmission / Distribution Owner | Union Electric Co - (MO) (19436) MO |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator 1 Details Operating June 1970
Technology | Conventional Steam Coal |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | AMMO.LABADIE1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | AMMO.LABADIE1 |
Nameplate Capacity | 573.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 593 MW |
Winter Capacity | 616 MW |
Minimum Load | 290 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 1970 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Subbituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | OVER |
Pulverized Coal Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating June 1971
Technology | Conventional Steam Coal |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | AMMO.LABADIE2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | AMMO.LABADIE2 |
Nameplate Capacity | 573.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 593 MW |
Winter Capacity | 616 MW |
Minimum Load | 289 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 1971 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Subbituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | OVER |
Pulverized Coal Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 3 Details Operating August 1972
Technology | Conventional Steam Coal |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | AMMO.LABADIE3 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | AMMO.LABADIE3 |
Nameplate Capacity | 621 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 593 MW |
Winter Capacity | 616 MW |
Minimum Load | 280 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1972 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Subbituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | OVER |
Pulverized Coal Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 4 Details Operating August 1973
Technology | Conventional Steam Coal |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | AMMO.LABADIE4 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | AMMO.LABADIE4 |
Nameplate Capacity | 621 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 593 MW |
Winter Capacity | 616 MW |
Minimum Load | 287 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1973 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Subbituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | OVER |
Pulverized Coal Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Labadie Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Subbituminous Coal.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1 | James H Miller Jr | Quinton, AL | 17.1 TWh |
#3 | Martin Lake | Tatum, TX | 10.8 TWh |
#4 | Monroe (MI) | Monroe, MI | 12.9 TWh |
#5 | W A Parish | Thompsons, TX | 11.5 TWh |
#6 | Colstrip | Colstrip, MT | 9.2 TWh |
#7 | J H Campbell | West Olive, MI | 7.5 TWh |
#8 | Sherburne County | Becker, MN | 7.3 TWh |
#9 | Scherer | Juliette, GA | 7.0 TWh |
#10 | Laramie River Station | Wheatland, WY | 7.0 TWh |
#11 | Fayette Power Project | La Grange, TX | 7.0 TWh |
#12 | Gerald Gentleman | Sutherland, NE | 6.8 TWh |
#13 | Baldwin Energy Complex | Baldwin, IL | 6.4 TWh |
#14 | Jim Bridger | Point of Rocks, WY | 8.3 TWh |
#15 | Springerville | Springerville, AZ | 6.3 TWh |
#16 | J K Spruce | San Antonio, TX | 6.1 TWh |
#17 | Nebraska City | Nebraska City, NE | 6.0 TWh |
#18 | Jeffrey Energy Center | St. Mary's, KS | 5.7 TWh |
#19 | La Cygne | La Cygne, KS | 5.7 TWh |
#20 | Independence Steam Electric Station | Newark, AR | 5.6 TWh |
#21 | Comanche (CO) | Pueblo, CO | 5.7 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Labadie.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AES Belleville Solar LLC | Belleville, IL | 17.3 GWh | 44.9 mi |
Anheuser-Busch St Louis | St. Louis, MO | 40.5 GWh | 34 mi |
Callaway | Fulton, MO | 9.4 TWh | 52.6 mi |
Edwardsville Solar II | Edwardsville, IL | 4.0 GWh | 48.6 mi |
Freeburg | Freeburg, IL | 230.0 MWh | 50.8 mi |
Granite City Works | Granite City, IL | 497.2 GWh | 39.4 mi |
IKEA St. Louis 410 | St. Louis, MO | 241.0 MWh | 32.4 mi |
Meramec | St. Louis, MO | 165.0 GWh | 29.3 mi |
Milam Gas Recovery | East St. Lois, IL | 19.3 GWh | 38.7 mi |
Montgomery County Community Solar Center | New Florence, MO | 11.2 GWh | 38.9 mi |
O'Fallon Renewable Energy Center | O'Fallon, MO | 5.3 GWh | 20.2 mi |
Red Bud | Red Bud, IL | 123.0 MWh | 51.3 mi |
Renewable Energy Center at BJH | St Louis, MO | 1.4 GWh | 31.7 mi |
Rush Island | Festus, MO | 609.2 GWh | 43.1 mi |
SCS American Bottoms 009885 Sauget, LLC | Sauget, IL | 3.0 GWh | 35.4 mi |
Sioux | West Alton, MO | 3.1 TWh | 38.3 mi |
Southwestern Bell Telephone | St. Louis, MO | 52.0 MWh | 35.1 mi |
Trigen St. Louis | St Louis, MO | 84.6 GWh | 35.8 mi |
Venice | Venice, IL | 13.7 GWh | 36.4 mi |
Waterloo | Waterloo, IL | 462.0 MWh | 39.9 mi |