Keystone Dam
23115 West Wekiwa Rd, Sand Springs, OK 74063Plant Summary Information
Keystone Dam is ranked #9 out of 10 hydroelectric power plants in Oklahoma in terms of total annual net electricity generation.
Keystone Dam is comprised of 2 generators and generated 14.8 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Keystone Dam |
---|---|
Utility Name | USCE-Tulsa District |
Location | Tulsa County, OK |
Initial Operation Date | May 1968 |
Last Update | Dec 2023 |
Annual Generation | 92.8 GWh |
Annual Consumption | 360.4 k MMBtu |
Ranked #3,265 out of 11,852 Power Plants Nationwide | |
Ranked #371 out of 1,371 Water Power Plants Nationwide | |
Ranked #99 out of 126 Oklahoma Power Plants | |
Ranked #9 out of 10 Oklahoma Water Power Plants | |
Fuel Types | Water |
Map of Keystone Dam
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Keystone Dam.
Monthly Net Generation for Keystone Dam
Keystone Dam Details
Summary Information | |
---|---|
Plant Name | Keystone Dam (2984) |
Plant Address | 23115 West Wekiwa Rd, Sand Springs, OK 74063 |
Utility | USCE-Tulsa District (27470) |
Latitude, Longitude | 36.1508, -96.2517 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | May 1968 |
Annual Generation | 92.8 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Arkansas River |
Ash Impoundment | No |
Transmission / Distribution Owner | Southwestern Power Administration (17716) |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator 1 Details OA May 1968
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 35 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 40 MW |
Winter Capacity | 40 MW |
Minimum Load | 25 MW |
Uprate/Derate Completed | No |
Status | OA |
---|---|
First Operation Date | May 1968 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator 2 Details Operating May 1968
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 35 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 40 MW |
Winter Capacity | 40 MW |
Minimum Load | 25 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 1968 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Keystone Dam Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#361 | Cutler Hydro | Collinston, UT | 96.2 GWh |
#362 | Bennetts Bridge | Altmar, NY | 96.0 GWh |
#363 | Clarence Cannon | Monroe City, MO | 95.9 GWh |
#364 | Petenwell | Necedah, WI | 95.5 GWh |
#365 | South Colton | Colton, NY | 95.4 GWh |
#366 | South Holston | Bristol, TN | 94.6 GWh |
#367 | Fort Patrick Henry | Kingsport, TN | 94.4 GWh |
#368 | Lawrence Hydroelectric Associates | Lawrence, MA | 94.2 GWh |
#369 | Holcombe | Holcombe, WI | 93.6 GWh |
#370 | Sullivan | West Linn, OR | 93.4 GWh |
#372 | Dale Hollow | Celina, TN | 92.8 GWh |
#373 | Faraday | Estacada, OR | 92.5 GWh |
#374 | Melton Hill | Lenoir City, TN | 91.5 GWh |
#375 | Navajo Dam | Farmington, NM | 91.4 GWh |
#376 | Alamo | Pearblossom, CA | 91.3 GWh |
#377 | Control Gorge | Bishop, CA | 91.0 GWh |
#378 | Lookout Shoals | Statesville, NC | 90.3 GWh |
#379 | Wallenpaupack | Drumore, PA | 90.2 GWh |
#380 | Monroe Street | Spokane, WA | 89.1 GWh |
#381 | Lake Dorothy Hydroelectric Project | Juneau, AK | 88.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Keystone Dam.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Chouteau | Pryor, OK | 6.7 TWh | 54.6 mi |
Cushing | Cushing, OK | 575.0 MWh | 31.5 mi |
Fort Gibson | Fort Gibson, OK | 140.4 GWh | 60.5 mi |
GREC | Chouteau, OK | 3.4 TWh | 53.7 mi |
Green Country Energy LLC | Jenks, OK | 4.1 TWh | 21.2 mi |
Kaw Hydro | Ponca City, OK | 8.6 GWh | 53.4 mi |
Markham | Locust Grove, OK | 123.5 GWh | 59.9 mi |
Muskogee | Fort Gibson, OK | 2.7 TWh | 60.3 mi |
Northeastern | Oologah, OK | 3.9 TWh | 36.3 mi |
Oneta Energy Center | Broken Arrow, OK | 5.7 TWh | 32.4 mi |
Osage Wind, LLC | Burbank, OK | 511.9 GWh | 45.8 mi |
Pawhuska | Pawhuska, OK | 375.0 MWh | 36.2 mi |
Ponca City | Ponca City, OK | 31.0 GWh | 60.8 mi |
Riverside (OK) | Jenks, OK | 1.1 TWh | 19.6 mi |
Sooner | Red Rock, OK | 1.5 TWh | 49.3 mi |
Stillwater Energy Center | Stillwater, OK | 88.4 GWh | 43.8 mi |
Thunder Ranch Wind Project | Marland, OK | 995.5 GWh | 55.9 mi |
Tulsa | Tulsa, OK | 214.3 GWh | 14.7 mi |
Tulsa LFG LLC | Sand Springs, OK | 16.7 GWh | 3.7 mi |
Weleetka | Weleetka, OK | 7.1 GWh | 57.5 mi |