Kearsarge Ludlow LLC
640 West St, Ludlow, MA 1056Plant Summary Information
Kearsarge Ludlow LLC is ranked #99 out of 463 solar farms in Massachusetts in terms of total annual net electricity generation.
Kearsarge Ludlow LLC generated 1.6 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Kearsarge Ludlow LLC |
---|---|
Utility Name | Kearsarge Ludlow LLC |
Location | Hampden County, MA |
Initial Operation Date | December 2020 |
Last Update | Dec 2022 |
Annual Generation | 6.2 GWh |
Annual Consumption | 21.1 k MMBtu |
Ranked #7,113 out of 11,249 Power Plants Nationwide | |
Ranked #2,379 out of 5,158 Solar Power Plants Nationwide | |
Ranked #172 out of 573 Massachusetts Power Plants | |
Ranked #99 out of 463 Massachusetts Solar Power Plants | |
Fuel Types | Solar |
Map of Kearsarge Ludlow LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Kearsarge Ludlow LLC.
Monthly Net Generation for Kearsarge Ludlow LLC
Kearsarge Ludlow LLC Details
Summary Information | |
---|---|
Plant Name | Kearsarge Ludlow LLC (65688) |
Plant Address | 640 West St Ludlow, MA 1056 |
Utility | Kearsarge Ludlow LLC (64819) |
Latitude, Longitude | 42.20128, -72.49416 |
Generation Dates on File | Jan 2022 to Dec 2022 |
Initial Operation Date | December 2020 |
Annual Generation | 6.2 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF19-1392-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | ISO New England Inc. (ISNE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | NSTAR Electric Company (54913) MA |
Grid Voltage | 13.80 kV |
Energy Storage | No |
Generator LUD Details Operating December 2020
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 3.7 MW |
Summer Capacity | 3.7 MW |
Winter Capacity | 3.7 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | Yes |
Virtual Net Metering DC Capacity | 3.7 MW |
Kearsarge Ludlow LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2369 | Putnam Erikson 2 | Eatonton, GA | 6.2 GWh |
#2370 | Dodge Holdco Solar CSG | Kasson, MN | 6.2 GWh |
#2371 | WEB Brookfield | Brookfield, MA | 6.2 GWh |
#2372 | The City of Vineland at North Vineland | Vineland, NJ | 6.2 GWh |
#2373 | Progress Solar III, LLC | Maxton, NC | 6.2 GWh |
#2374 | Kihei Solar Farm | Kihei, HI | 6.2 GWh |
#2375 | Aries Community Solar | Claremont, MN | 6.2 GWh |
#2376 | Progress Solar II, LLC | Fairmont, NC | 6.2 GWh |
#2377 | Yadkin 601 Farm | Yadkinville, NC | 6.2 GWh |
#2378 | Palmer | Palmer, MA | 6.2 GWh |
#2380 | Morin Solar 2013 LLC | Warren, MA | 6.2 GWh |
#2381 | Weymouth Solar Plant | La Verne, CA | 6.2 GWh |
#2382 | Valley Center | Valley Center, CA | 6.2 GWh |
#2383 | Aerojet I | Rancho Cordova, CA | 6.2 GWh |
#2384 | Held Solar Project | Waite Park, MN | 6.2 GWh |
#2385 | DEC Phase II at Georgetown | Georgetown, DE | 6.2 GWh |
#2386 | Durham Solar | Durham, NC | 6.2 GWh |
#2387 | Buckhorn Solar Plant | Paragonah, UT | 6.1 GWh |
#2388 | Onyx - Brockton Thatcher Landfill Solar CSG | Brockton, MA | 6.1 GWh |
#2389 | Partridgeville Hybrid CSG | Athol, MA | 6.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Kearsarge Ludlow LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Ameresco Chicopee Energy | Chicopee, MA | 21.3 GWh | 3.4 mi |
CED Chicopee Solar | Chicopee, MA | 5.5 GWh | 2.9 mi |
Chicopee | Chicopee, MA | 2.8 GWh | 1.6 mi |
Chicopee River Solar | Springfield, MA | 3.1 GWh | 4.6 mi |
Chicopee Solar | Chicopee, MA | 5.2 GWh | 4.7 mi |
Collins Facility | Wilbraham, MA | 5.5 GWh | 4.8 mi |
Cottage Street Solar Facility | Springfield, MA | 4.0 GWh | 4.5 mi |
Granby LFG | Granby, MA | 3.5 GWh | 3.3 mi |
Granby Solar, LLC CSG | Granby, MA | 5.6 GWh | 2.3 mi |
Huxley Solar | Ludlow, MA | 71.0 MWh | 0.8 mi |
Indian Orchard | Indian Orchard, MA | 8.0 GWh | 2.9 mi |
Indian Orchard PV Facility | Springfield, MA | 2.9 GWh | 3.5 mi |
Kearsarge Granby | Granby, MA | 4.1 GWh | 1.7 mi |
Ludlow Landfill | Ludlow, MA | 3.4 GWh | 1.5 mi |
Ludlow Site 72 - Conti | Ludlow, MA | 2.7 GWh | 3.5 mi |
Masspower | Indian Orchard, MA | 240.1 GWh | 3.4 mi |
Oak Street Solar | Springfield, MA | 5.7 GWh | 3.6 mi |
Putts Bridge | Ludlow, MA | 16.1 GWh | 3 mi |
Redbridge | Wilbraham, MA | 16.2 GWh | 4.7 mi |
Stony Brook | Ludlow, MA | 24.2 GWh | 0.9 mi |