Kansas River Project
500 South Powerhouse Road, Lawrence, KS 66044Plant Summary Information
Kansas River Project is ranked #1 out of 1 hydroelectric power plants in Kansas in terms of total annual net electricity generation.
Kansas River Project is comprised of 11 generators and generated 3.0 GWh during the 3-month period between December 2023 to March 2024.
Plant Name | Kansas River Project |
---|---|
Utility Name | Bowersock Mills & Power Co |
Location | Douglas County, KS |
Initial Operation Date | January 1920 |
Last Update | Mar 2024 |
Annual Generation | 13.8 GWh |
Annual Consumption | 47.1 k MMBtu |
Ranked #5,397 out of 11,249 Power Plants Nationwide | |
Ranked #850 out of 1,354 Water Power Plants Nationwide | |
Ranked #75 out of 145 Kansas Power Plants | |
Ranked #1 out of 1 Kansas Water Power Plants | |
Fuel Types | Water |
Map of Kansas River Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Kansas River Project.
Monthly Net Generation for Kansas River Project
Kansas River Project Details
Summary Information | |
---|---|
Plant Name | Kansas River Project (10279) |
Plant Address | 500 South Powerhouse Road Lawrence, KS 66044 |
Utility | Bowersock Mills & Power Co (2048) |
Latitude, Longitude | 38.97402, -95.23508 |
Generation Dates on File | Jun 2001 to Mar 2024 |
Initial Operation Date | January 1920 |
Annual Generation | 13.8 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 91-112-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Kansas River |
Ash Impoundment | No |
Transmission / Distribution Owner | Evergy Kansas Central, Inc (22500) KS |
Grid Voltage | 240.00 kV |
Energy Storage | No |
Generator 1 Details Operating January 1920
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.4 MW |
Minimum Load | 0.1 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | January 1920 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator 2 Details Operating July 1922
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.3 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | July 1922 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 3 Details Operating July 1922
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.3 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | July 1922 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 4 Details Operating July 1922
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.3 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | July 1922 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 5 Details Operating July 1922
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | July 1922 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 6 Details Operating May 1925
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Minimum Load | 0.2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | May 1925 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 7 Details Operating May 1925
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | `KACYBOWERSOCK |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Minimum Load | 0.2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | May 1925 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 10 Details Operating December 2012
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 1.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.3 MW |
Winter Capacity | 1.3 MW |
Minimum Load | 0.9 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 11 Details Operating December 2012
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 1 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.8 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 8 Details Operating December 2012
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 1 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.8 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 9 Details Operating December 2012
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | KACYBOWERSOCK |
RTO ISO Location Designation For Reporting Wholesale Sales Data | KACYBOWERSOCK |
Nameplate Capacity | 1.3 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.3 MW |
Winter Capacity | 1.3 MW |
Minimum Load | 0.9 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Kansas River Project Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#840 | Stillwater Hydro Electric Project | Stillwater, NY | 14.2 GWh |
#841 | Norway Point Hydropower Project | Alpena, MI | 14.2 GWh |
#842 | Weeks Falls | North Bend, WA | 14.0 GWh |
#843 | Allegan Dam | Allegan, MI | 14.0 GWh |
#844 | Island Park | Island Park, ID | 14.0 GWh |
#845 | Drop 5 | Calexico, CA | 14.0 GWh |
#846 | Wilbur | Elizabethon, TN | 13.9 GWh |
#847 | Big Creek Water Works | Hyampom, CA | 13.8 GWh |
#848 | Pine | Florence, WI | 13.8 GWh |
#849 | Silvis | Ketchikan, AK | 13.8 GWh |
#851 | Park Mill | Marinette, WI | 13.7 GWh |
#852 | Waterport | Waterport, NY | 13.7 GWh |
#853 | Fourth Branch Hydroelectric Facility | Waterford, NY | 13.6 GWh |
#854 | Elkhart | Elkhart, IN | 13.6 GWh |
#855 | Austin | Austin, TX | 13.6 GWh |
#856 | Rochester 5 | Rochester, NY | 13.6 GWh |
#857 | Gross Hydro Plant | Boulder, CO | 13.5 GWh |
#858 | Brassua Hydroelectric Project | Rockwood, ME | 13.5 GWh |
#859 | Quail Creek Hydro Plant #1 | Hurricane, UT | 13.3 GWh |
#860 | Penacook Upper Falls Hydro | Penacook, NH | 13.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Kansas River Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Baldwin City Plant No 1 | Baldwin City, KS | 20.5 MWh | 14 mi |
Baldwin City Plant No 2 | Baldwin City, KS | 489.1 MWh | 14.6 mi |
BPU Solar Farm | Kansas City, KS | 1.9 GWh | 31.8 mi |
Burlingame | Burlingame, KS | 33.5 MWh | 35.7 mi |
Gardner Energy Center | Gardner, KS | 41.2 MWh | 21 mi |
Grand Ave Plant | Kansas City, MO | 44.4 GWh | 36.4 mi |
Hawthorn | Kansas City, MO | 2.8 TWh | 42 mi |
Holton | City of Holton, KS | 1.1 GWh | 43.6 mi |
Iatan | Weston, MO | 4.9 TWh | 35.4 mi |
Lawrence Energy Center | Lawrence, KS | 1.9 TWh | 2.9 mi |
Nearman Creek | Kansas, KS | 857.4 GWh | 31.8 mi |
Northeast (MO) | Kansas City, MO | 13.1 GWh | 37.6 mi |
Osawatomie | Miami, KS | 50.0 GWh | 35.4 mi |
Osawatomie City of | Osawatomie, KS | 47.8 MWh | 35.8 mi |
Osawatomie Power Plant North Sub | Osawatomie, KS | 38.8 MWh | 35.9 mi |
Osawatomie Power Plant South Sub | Osawatomie, KS | 21.5 MWh | 36.4 mi |
Ottawa | Ottawa, KS | 705.3 MWh | 24.9 mi |
Quindaro | Kansas, KS | 10.9 GWh | 34.2 mi |
Waste Management Rolling Meadows LFGTE | Topeka, KS | 49.7 GWh | 30 mi |
West Gardner | Johnson, KS | 181.6 GWh | 18.6 mi |