Kahoka
255 N Washington, Kahoka, MO 63445Plant Summary Information
Kahoka is ranked #38 out of 47 distillate fuel oil power plants in Missouri in terms of total annual net electricity generation.
Kahoka is comprised of 8 generators and generated 3.3 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Kahoka |
---|---|
Utility Name | City of Kahoka |
Location | Clark County, MO |
Initial Operation Date | January 1941 |
Last Update | Dec 2023 |
Annual Generation | 17.0 MWh |
Annual Consumption | 450 MMBtu |
Ranked #11,687 out of 11,835 Power Plants Nationwide | |
Ranked #1,061 out of 1,262 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #113 out of 120 Missouri Power Plants | |
Ranked #38 out of 47 Missouri Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of Kahoka
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Kahoka.
Monthly Net Generation for Kahoka
Kahoka Details
Summary Information | |
---|---|
Plant Name | Kahoka (2138) |
Plant Address | 255 N Washington, Kahoka, MO 63445 |
Utility | City of Kahoka (9973) |
Latitude, Longitude | 40.4225, -91.7206 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | January 1941 |
Annual Generation | 17.0 MWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | Union Electric Co - (MO) (19436) MO |
Grid Voltage | 34.50 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | LIBERTY ENERGY DBA LIBERTY UTILITIES |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator 3 Details Operating January 1941
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 0.2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.2 MW |
Winter Capacity | 0.2 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 1941 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 6 Details Operating January 1952
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 0.7 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | January 1952 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 7 Details Standby January 1956
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.8 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | No |
---|---|
First Operation Date | January 1956 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | DFO / NG |
---|
Generator 8 Details Standby September 1969
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 1.5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.4 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 0.7 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | No |
---|---|
First Operation Date | September 1969 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | DFO / NG |
---|
Generator 9 Details Standby July 1982
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 0.9 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.8 MW |
Winter Capacity | 0.9 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | No |
---|---|
First Operation Date | July 1982 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | DFO / NG |
---|
Generator 10 Details Operating July 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 1.1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.1 MW |
Winter Capacity | 1.1 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 11 Details Operating July 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 1.1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.1 MW |
Winter Capacity | 1.1 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 12 Details Operating September 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | NA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 1.1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.1 MW |
Winter Capacity | 1.1 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Kahoka Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1051 | NYP-Lower Manhattan Hospital | New York, NY | 19.0 MWh |
#1052 | University of Michigan | Ann Arbor, MI | 222.0 GWh |
#1053 | HVCC Cogen Plant | Troy, NY | 13.2 GWh |
#1054 | Princeton University Cogeneration | Princeton, NJ | 58.7 GWh |
#1055 | Olmsted Waste Energy | Rochester, MN | 39.5 GWh |
#1056 | Hugoton 2 | Hugoton, KS | 18.6 MWh |
#1057 | Truman | Truman, MN | 18.0 MWh |
#1058 | Lockheed Martin Solar | Orlando, FL | 3.0 GWh |
#1059 | Alliant SBD 9403 Aegon DC | Cedar Rapids, IA | 17.6 MWh |
#1060 | St John | St. John, KS | 17.0 MWh |
#1062 | Seldovia | Seldovia, AK | 17.0 MWh |
#1063 | Bloomfield | Bloomfield, IA | 16.0 MWh |
#1064 | Anadarko | Woodsfield, OH | 16.0 MWh |
#1065 | Gilbert | Milford, NJ | 26.8 GWh |
#1066 | Danville Kentuck Road Plant | Ringgold, VA | 15.7 MWh |
#1067 | Meade | Meade, KS | 105.0 MWh |
#1068 | Dayton (IA) | Dayton, IA | 15.0 MWh |
#1069 | Cashton | Cashton, WI | 15.0 MWh |
#1070 | Fredonia | Fredonia, KS | 15.0 MWh |
#1071 | Hillsboro | Hillsboro, ND | 15.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Kahoka.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bloomfield | Bloomfield, IA | 16.0 MWh | 41.8 mi |
Bloomfield Municipal Utilities Solar | Bloomfield, IA | 2.1 GWh | 44.5 mi |
Burlington (IA) | Burlington, IA | 6.4 GWh | 38.6 mi |
Cardinal Point Wind | Sciota, IL | 540.6 GWh | 52.2 mi |
Galesburg Solar Array | Oquawka, IL | 2.8 GWh | 53.1 mi |
High Prairie Wind Farm | Queen City, MO | 880.9 GWh | 42 mi |
JM Huber at Quincy | Quincy, IL | 2.4 GWh | 42.5 mi |
Keokuk | Keokuk, IA | 834.9 GWh | 18.4 mi |
La Plata | La Plata, MO | 19.0 MWh | 49 mi |
McDonough Solar 1, LLC CSG | Blandinsville, IL | 4.3 GWh | 46.6 mi |
Memphis | Memphis, MO | 8.0 MWh | 24.3 mi |
Mt Pleasant | Mt Pleasant, IA | 59.0 MWh | 39 mi |
NLMU Wind | New London, IA | 4.7 GWh | 40.6 mi |
Ottumwa City of | Ottumwa, IA | 5.3 GWh | 54.8 mi |
Roquette America | Keokuk, IA | 189.2 GWh | 17.3 mi |
Shelbina Power #1 | Shelbina, MO | 7.0 MWh | 53.2 mi |
Shelbina Power #2 | Shelbina, MO | 31.0 MWh | 53.2 mi |
Shelbina Power #3 | Shelbina, MO | 8.0 MWh | 53.1 mi |
Sullivan B Community Solar LLC | Macomb, IL | 2.0 GWh | 56.9 mi |
Wapello Solar LLC | Wapello, IA | 219.2 GWh | 58 mi |