Intel Folsom Phase 3

1900 Prairie City Road, Folsom, CA 95630

Plant Summary Information

Intel Folsom Phase 3 is ranked #307 out of 747 solar farms in California in terms of total annual net electricity generation.

Intel Folsom Phase 3 generated 2.4 GWh during the 3-month period between September 2022 to December 2022.

Plant NameIntel Folsom Phase 3
Utility NameTesla Inc.
LocationSacramento County, CA
Initial Operation DateApril 2016
Last Update Dec 2022
Annual Generation 9.4 GWh
Annual Consumption 33.6 k MMBtu
Ranked #6,102 out of 11,249 Power Plants Nationwide
Ranked #1,683 out of 5,158 Solar Power Plants Nationwide
Ranked #848 out of 1,501 California Power Plants
Ranked #307 out of 747 California Solar Power Plants
Fuel Types Solar

Map of Intel Folsom Phase 3

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Intel Folsom Phase 3.

Create Your Account Today

Monthly Net Generation for Intel Folsom Phase 3

Intel Folsom Phase 3 Details

Summary Information
Plant NameIntel Folsom Phase 3 (61152)
Plant Address1900 Prairie City Road Folsom, CA 95630
UtilityTesla Inc. (60947)
Latitude, Longitude38.64596, -121.16262
Generation Dates on FileApr 2016 to Dec 2022
Initial Operation DateApril 2016
Annual Generation 9.4 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityBalancing Authority of Northern California (BANC)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerSacramento Municipal Util Dist (16534) CA
Grid Voltage 1.00 kV
Energy StorageNo

Generator PV1 Details Operating April 2016

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipWholly Owned by Other Entity
Nameplate Capacity5.2 MW
Summer Capacity5.2 MW
Winter Capacity5.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 2016
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solar Details
Single Axis TrackingYes
Azimuth Angle272
Tilt Angle5
DC Net Capacity6.5 MW
Crystalline SiliconYes
Net Metering AgreementYes
Net Metering DC Capacity6.5 MW
Virtual Net Metering AgreementNo

Intel Folsom Phase 3 Plant Owners

Owner NameAddressOwnership
Three Rivers Solar I, LLC6800 Dumbarton Circle, Fremont, CA 94555100.00%

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#1673Vance Solar Farm, LLCKittrell, NC9.4 GWh
#1674Koppelman Sun CSGEagle Lake, MN9.4 GWh
#1675Flemming Solar Center LLCGreenville, NC9.4 GWh
#1676Langdon Solar Farm, LLCFour Oaks, NC9.4 GWh
#1677Innovative Solar 63, LLCSnow Hill, NC9.4 GWh
#1678Schell Solar FarmGarysburg, NC9.4 GWh
#1679Yanceyville Farm 3, LLCBlanch, NC9.4 GWh
#1680Syncarpha Puddon I Hybrid CSGNorthbridge, MA9.2 GWh
#1681Springfield Solar 1 LLCStrafford, MO9.4 GWh
#16821001 Ebenezer Church SolarStateRoad, NC9.4 GWh
#1684Nick SolarLiberty, NC9.4 GWh
#1685Walters Solar (FLS 260)Orrum, NC9.4 GWh
#1686Pate FarmRed Springs, NC9.4 GWh
#1687Misenheimer FarmRichfield, NC9.3 GWh
#1688Spicewood Solar Farm LLCEagle Springs, NC9.3 GWh
#1689IFF Union Beach ProjectUnion Beach, NJ9.3 GWh
#1690Vicksburg SolarHenderson, NC9.3 GWh
#1691Alpha Value SolarHertford, NC9.3 GWh
#1692Mariposa Solar Center LLCStanley, NC9.3 GWh
#1693Newfield Community Solar LLCNewfield, NY9.3 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Intel Folsom Phase 3.

Plant NamePlant LocationAnnual GenerationDistance
Aerojet IRancho Cordova, CA6.2 GWh2.2 mi
Aerojet IIRancho Cordova, CA4.0 GWh2.6 mi
Blue Shld Of Cal- El Dorado Hlls Mtr BEl Dorado Hills, CA3.3 GWh4.8 mi
Broadridge CogenEl Dorado Hills, CA15.3 GWh6 mi
Deer Creek 2Shingle Springs, CA3.2 GWh9.7 mi
Dept of General Services -FTBSacramento, CA5.6 GWh11.2 mi
El Dorado Solar, LLCEl Dorado Hills, CA4.6 GWh5.6 mi
FAA NorCal TRACONMather AFB, CA1.7 GWh7.9 mi
FolsomFolsom, CA904.8 GWh4.2 mi
Folsom SP and CSP SacramentoRepresa, CA2.7 GWh2.8 mi
Intel FolsomFolsom, CA1.6 GWh0.6 mi
Intel Folsom Phase 2Folsom, CA1.6 GWh0.2 mi
Kiefer LandfillSloughhouse, CA69.7 GWh9.3 mi
McClellan (CA)Sacramento, CA4.0 GWh12.5 mi
NimbusFolsom, CA47.4 GWh3.2 mi
Rancho Cordova Medical OfficesRancho Cordova, CA2.4 GWh8.4 mi
RE Dillard 1 LLCSloughhouse, CA6.8 GWh12.3 mi
RE Dillard 2 LLCSloughhouse, CA7.0 GWh12.5 mi
RE Dillard 3 LLCSloughhouse, CA7.0 GWh12.8 mi
US GSA - SacramentoSacramento, CA2.4 GWh13.1 mi