IBM West
3112 Valleyhigh Drive NW, Rochester, MN 55901Plant Summary Information
IBM West is ranked #52 out of 76 distillate fuel oil power plants in Minnesota in terms of total annual net electricity generation.
IBM West is comprised of 2 generators and generated 7.2 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | IBM West |
---|---|
Utility Name | Rochester Public Utilities |
Location | Olmsted County, MN |
Initial Operation Date | October 2005 |
Last Update | Dec 2023 |
Annual Generation | 34.0 MWh |
Annual Consumption | 392 MMBtu |
Ranked #11,605 out of 11,835 Power Plants Nationwide | |
Ranked #970 out of 1,262 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #718 out of 736 Minnesota Power Plants | |
Ranked #52 out of 76 Minnesota Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of IBM West
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for IBM West.
Monthly Net Generation for IBM West
IBM West Details
Summary Information | |
---|---|
Plant Name | IBM West (56269) |
Plant Address | 3112 Valleyhigh Drive NW, Rochester, MN 55901 |
Utility | Rochester Public Utilities (16181) |
Latitude, Longitude | 44.0587, -92.5119 |
Generation Dates on File | Jan 2007 to Dec 2023 |
Initial Operation Date | October 2005 |
Annual Generation | 34.0 MWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Rochester Public Utilities (16181) MN |
Grid Voltage | 161.00 kV |
Energy Storage | No |
Generator 1 Details Standby October 2005
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.5 MW |
Uprate/Derate Completed | No |
Status | Standby |
---|---|
Synchronized To Transmission Grid | Yes |
First Operation Date | October 2005 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 2 Details Standby October 2005
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.5 MW |
Uprate/Derate Completed | No |
Status | Standby |
---|---|
Synchronized To Transmission Grid | Yes |
First Operation Date | October 2005 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
IBM West Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#960 | Bushnell | Bushnell, IL | 36.0 MWh |
#961 | Farmer City | Farmer City, IL | 36.0 MWh |
#962 | St. Mary's Hospital For Children | Bayside, NY | 36.0 MWh |
#963 | Fairfax | Fairfax, MN | 35.3 MWh |
#964 | Pratt 2 | Pratt, KS | 226.0 MWh |
#965 | Burwell | Burwell, NE | 35.0 MWh |
#966 | Johnson | Johnson, KS | 35.0 MWh |
#967 | Mount Sinai Beth Israel | New York, NY | 35.0 MWh |
#968 | Yankee Street | Centerville, OH | 4.7 GWh |
#969 | University of Arizona - Biosphere 2 | Oracle, AZ | 118.0 MWh |
#971 | Albert Einstein College of Medicine | Bronx, NY | 34.0 MWh |
#972 | Alexandria | Alexandria, MN | 34.0 MWh |
#973 | Jackson Cntr Peaking | Jackson Center, OH | 34.0 MWh |
#974 | Albemarle Hospital Unit | Albemarle, NC | 33.0 MWh |
#975 | Wilber | Wilber, NE | 33.0 MWh |
#976 | Shawville | Shawville, PA | 1.8 TWh |
#977 | Unalaska Power Module | Unalaska, AK | 33.0 MWh |
#978 | Interstate | Springfield, IL | 39.5 GWh |
#979 | Lake Mills | Lake Mills, IA | 32.0 MWh |
#980 | Elk River City of | Elk River, MN | 32.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding IBM West.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
4710 Hosting | Rochester, MN | 30.0 MWh | 1 mi |
Bear Grove Solar | Byron, MN | 1.4 GWh | 6.1 mi |
Cascade Creek | Rochester, MN | 38.7 GWh | 2.1 mi |
Crux Community Solar | Kasson, MN | 2.0 GWh | 9.1 mi |
DodgeSun CSG | Kasson, MN | 9.5 GWh | 8.9 mi |
Franklin Heating Station | Rochester, MN | 57.1 GWh | 3.5 mi |
Hwy 14 Holdco Solar CSG | Byron, MN | 7.1 GWh | 4.7 mi |
Lange Solar | Byron, MN | 1.4 GWh | 6.7 mi |
Maston Garden Solar | Kasson, MN | 1.7 GWh | 8.9 mi |
Novel Bartel Solar CSG | Byron, MN | 1.8 GWh | 8.3 mi |
Novel Byron Solar CSG | Byron, MN | 1.8 GWh | 6.3 mi |
Novel DeCook Solar CSG | Byron, MN | 1.9 GWh | 6.5 mi |
Novel Wayne Solar LLC CSG | Mantorville, MN | 2.0 GWh | 12 mi |
Olmsted Waste Energy | Rochester, MN | 39.5 GWh | 4.6 mi |
Rochester Hydro | Mazeppa, MN | 10.3 GWh | 10.8 mi |
Saint Marys Hospital Power Plant | Rochester, MN | 52.2 GWh | 3.1 mi |
Tweite Community Solar LLC | Byron, MN | 2.1 GWh | 8.4 mi |
Water Reclamation Plant | Rochester, MN | 2.6 GWh | 2.2 mi |
Westside Energy Station | Rochester, MN | 48.4 GWh | 2.4 mi |
Westside Solar | Rochester, MN | 17.4 GWh | 1.9 mi |