Hurricane City Power
526 West 600 North, Hurricane, UT 84737Plant Summary Information
Hurricane City Power is ranked #21 out of 23 natural gas power plants in Utah in terms of total annual net electricity generation.
Hurricane City Power is comprised of 8 generators and generated 809.7 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Hurricane City Power |
---|---|
Utility Name | Hurricane City Power |
Location | Washington County, UT |
Initial Operation Date | December 1999 |
Last Update | Dec 2023 |
Annual Generation | 3.5 GWh |
Annual Consumption | 53.6 k MMBtu |
Ranked #8,599 out of 11,835 Power Plants Nationwide | |
Ranked #1,790 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #102 out of 121 Utah Power Plants | |
Ranked #21 out of 23 Utah Natural Gas Power Plants | |
Fuel Types | Natural Gas : 97.3% Distillate Fuel Oil : 2.7% |
Previous Operator |
Hurricane Power Committee (2013 to 2014) Hurricane City Power (2015 to 2023) |
Map of Hurricane City Power
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hurricane City Power.
Monthly Net Generation for Hurricane City Power
Hurricane City Power Details
Summary Information | |
---|---|
Plant Name | Hurricane City Power (57899) |
Plant Address | 526 West 600 North, Hurricane, UT 84737 |
Utility | Hurricane City Power (9128) |
Latitude, Longitude | 37.18556, -113.2975 |
Generation Dates on File | Jan 2011 to Dec 2023 |
Initial Operation Date | December 1999 |
Annual Generation | 3.5 GWh |
Fuel Types | Natural Gas : 97.3% Distillate Fuel Oil : 2.7% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | NA |
Ash Impoundment | No |
Transmission / Distribution Owner | Hurricane City Power (9128) UT |
Grid Voltage | 7.20 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | Other - See pipeline notes. |
Pipeline Name | Other - Please explain in pipeline notes below. |
Pipeline Notes | Dominion Energy |
Generator 2 Details Standby December 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 1.7 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | December 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Combustion Technology | No |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 3 Details Standby December 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 1.7 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | December 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Combustion Technology | No |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 1 Details Standby November 2001
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 1.7 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | November 2001 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Combustion Technology | No |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 4 Details Operating July 2004
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 1.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2004 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 5 Details Operating July 2004
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 1.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2004 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 6 Details Operating June 2006
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 1.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2006 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 7 Details Operating May 2007
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 1.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 2007 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 8 Details Operating May 2007
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | Mona |
RTO ISO Location Designation For Reporting Wholesale Sales Data | Mona |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 1.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 2007 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Hurricane City Power Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1780 | Geneva Generation Facility | Geneva, IL | 3.7 GWh |
#1781 | Powerton | Pekin, IL | 2.0 TWh |
#1782 | North Loop | Tucson, AZ | 3.6 GWh |
#1783 | Winnetka | Winnetka, IL | 3.8 GWh |
#1784 | Harrisburg Facility | Harrisburg, PA | 93.2 GWh |
#1785 | Overlook Medical Center | Summit, NJ | 3.6 GWh |
#1786 | AT&T San Diego | San Diego, CA | 3.5 GWh |
#1787 | Mosinee Mill | Mosinee, WI | 118.3 GWh |
#1788 | Yankee Street | Centerville, OH | 4.7 GWh |
#1789 | Kemper County | De Kalb, MS | 3.4 GWh |
#1791 | Wellington 1 | Wellington, KS | 3.4 GWh |
#1792 | Broshco Fabricated Products | Mansfield, OH | 3.3 GWh |
#1793 | Waters River | Peabody, MA | 4.3 GWh |
#1794 | Loyola University Health Plant | Maywood, IL | 3.3 GWh |
#1795 | Rockwood | Brawley, CA | 3.9 GWh |
#1796 | Arkalon Ethanol LLC | Liberal, KS | 3.2 GWh |
#1797 | C W Burdick | Grand Island, NE | 5.1 GWh |
#1798 | Kinmundy | Patoka, IL | 3.2 GWh |
#1799 | Swift Creek Chemical Complex | White Springs, FL | 71.9 GWh |
#1800 | William Floyd School District | Mastic Beach, NY | 3.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hurricane City Power.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Beryl Solar Plant | Beryl, UT | 6.1 GWh | 36.7 mi |
Bloomington Power Plant | Bloomington, UT | 200.0 MWh | 20.7 mi |
Bloomington Solar I | St George, UT | 2.3 GWh | 20.7 mi |
Cove Mountain Solar | Beryl, UT | 156.5 GWh | 35 mi |
Cove Mountain Solar 2 | Beryl, UT | 317.3 GWh | 36.4 mi |
Enterprise Solar, LLC | Newcastle, UT | 230.1 GWh | 35.9 mi |
Fiddler's Canyon #1 | Cedar City, UT | 6.9 GWh | 39.1 mi |
Fiddler's Canyon #2 | Cedar City, UT | 6.9 GWh | 42.1 mi |
Fiddler's Canyon 3 | Cedar City, UT | 7.3 GWh | 38 mi |
Granite Mountain Solar East, LLC | Cedar City, UT | 211.2 GWh | 40.9 mi |
Iron Springs Solar, LLC | Cedar City, UT | 214.0 GWh | 37.9 mi |
Millcreek Power Generation | St. George, UT | 118.6 GWh | 13.1 mi |
Quail Creek Hydro Plant #1 | Hurricane, UT | 10.8 GWh | 3.3 mi |
Quichapa 1 | Cedar City, UT | 7.6 GWh | 33 mi |
Quichapa 2 | Cedar City, UT | 7.4 GWh | 33.8 mi |
Quichapa 3 | Cedar City, UT | 7.5 GWh | 32.2 mi |
Solomon Generating Facility | St. George, UT | 35.3 GWh | 18.2 mi |
St George Red Rock | St George, UT | 675.0 MWh | 15.8 mi |
Veyo Heat Recovery Project | Gunlock, UT | 45.8 GWh | 28 mi |
Washington City Electric Generation | Washington, UT | 4.1 GWh | 8.1 mi |