Hollygrove CSG
7233 Route 104A, Red Creek, NY 13143Plant Summary Information
Hollygrove CSG is ranked #216 out of 378 solar farms in New York in terms of total annual net electricity generation.
Hollygrove CSG generated 929.7 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Hollygrove CSG |
---|---|
Utility Name | Nautilus Solar Solutions |
Location | Wayne County, NY |
Initial Operation Date | December 2018 |
Last Update | Dec 2022 |
Annual Generation | 3.3 GWh |
Annual Consumption | 12.1 k MMBtu |
Ranked #8,540 out of 11,249 Power Plants Nationwide | |
Ranked #3,496 out of 5,158 Solar Power Plants Nationwide | |
Ranked #525 out of 748 New York Power Plants | |
Ranked #216 out of 378 New York Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
Forefront Power, LLC (2019 to 2020) Nautilus Solar Solutions (2021 to 2022) |
Map of Hollygrove CSG
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hollygrove CSG.
Monthly Net Generation for Hollygrove CSG
Hollygrove CSG Details
Summary Information | |
---|---|
Plant Name | Hollygrove CSG (63051) |
Plant Address | 7233 Route 104A Red Creek, NY 13143 |
Utility | Nautilus Solar Solutions (61227) |
Latitude, Longitude | 43.26034, -76.7217 |
Generation Dates on File | Jan 2019 to Dec 2022 |
Initial Operation Date | December 2018 |
Annual Generation | 3.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Rochester Gas & Electric Corp (16183) NY |
Grid Voltage | 21.00 kV |
Energy Storage | No |
Generator 32 Details Operating December 2018
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 2 MW |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Tilt Angle | 25 |
DC Net Capacity | 3 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | Yes |
Virtual Net Metering DC Capacity | 3 MW |
Hollygrove CSG Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3486 | Richmond Hayes Solar | Augusta, GA | 3.3 GWh |
#3487 | Turner Rd Community Solar Project | Baldwin, NY | 3.3 GWh |
#3488 | Syncarpha Hancock I CSG | Hancock, MA | 3.3 GWh |
#3489 | Chanel Piscataway Rooftop | Piscataway, NJ | 3.3 GWh |
#3490 | Pool Brook Rd Community Solar Farm | Laurens, NY | 3.3 GWh |
#3491 | Rail Trail | Great Barrington, MA | 3.3 GWh |
#3492 | Mt. Morris Solar CSG | Polo, IL | 3.3 GWh |
#3493 | Howland CSG | Sandy Creek, NY | 3.3 GWh |
#3494 | Musgrave East Solar Farm | Aurora, NY | 3.3 GWh |
#3495 | SCE-Snowline-Duncan Road (North) | Phelan, CA | 3.3 GWh |
#3497 | Rantoul Solar | Rantoul, IL | 3.3 GWh |
#3498 | Quincy II Solar Garden | Aurora, CO | 3.3 GWh |
#3499 | Bashaw Solar CSG 1, LLC | Newbury, MA | 3.3 GWh |
#3500 | Matrix Buildings A&B (Perth Amboy) Solar | Perth Amboy, NJ | 3.3 GWh |
#3501 | Podunk Road CSG | Enfield, NY | 3.3 GWh |
#3502 | Chester CSG | Chester, NY | 3.3 GWh |
#3503 | Duke Building 87 | Indianapolis, IN | 3.3 GWh |
#3504 | NSE Camber Solar PS11 LLC (CSG) | Sterling, CO | 3.3 GWh |
#3505 | Amazon TUS2 | Tucson, AZ | 3.3 GWh |
#3506 | Madera 1 PV | Madera, CA | 3.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hollygrove CSG.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Anheuser-Busch Baldwinsville | Baldwinsville, NY | 2.0 GWh | 17.2 mi |
Brickchurch Solar | North Rose, NY | 3.6 GWh | 13 mi |
Donati Solar | Seneca Falls, NY | 2.0 GWh | 22.1 mi |
Fulton Hydro | Fulton, NY | 5.8 GWh | 15.8 mi |
Granby | Fulton, NY | 32.6 GWh | 15.7 mi |
Indeck Oswego Energy Center | Oswego, NY | 14.2 GWh | 18.6 mi |
Minetto | Minetto, NY | 27.3 GWh | 15.8 mi |
Onondaga County- Clearwater | Oswego, NY | 2.8 GWh | 15.6 mi |
Oswego County - Fulton Solar | Fulton, NY | 2.6 GWh | 19.9 mi |
Oswego County Energy Recovery | Fulton, NY | 7.4 GWh | 16.1 mi |
Oswego Falls East | Fulton, NY | 24.3 GWh | 15.9 mi |
Oswego Falls West | Fulton, NY | 4.1 GWh | 15.8 mi |
Oswego Harbor Power | Oswego, NY | 50.7 GWh | 16.7 mi |
Phoenix Hydro Project | Phoenix, NY | 11.8 GWh | 21.2 mi |
Sangolqui Solar | Seneca Falls, NY | 3.8 GWh | 21.9 mi |
Sithe Independence Station | Oswego, NY | 5.3 TWh | 21.2 mi |
Town of Williamson Landfill PV | Williamson, NY | 1.6 GWh | 22.8 mi |
Varick | Oswego, NY | 17.6 GWh | 16.9 mi |
Volney II | Fulton, NY | 4.7 GWh | 19.3 mi |
Williamson | Williamson, NY | 1.9 GWh | 20.4 mi |