Hillabee Energy Center
152 Brick Plant Road, Alexander City, AL 35010Plant Summary Information
Hillabee Energy Center is ranked #7 out of 75 power plants in Alabama in terms of total annual net electricity generation.
Hillabee Energy Center is comprised of 3 generators and generated 1.2 TWh during the 3-month period between May 2024 to August 2024.
Plant Name | Hillabee Energy Center |
---|---|
Utility Name | CER Generation LLC |
Location | Tallapoosa County, AL |
Initial Operation Date | June 2010 |
Last Update | Aug 2024 |
Annual Generation | 4.5 TWh |
Annual Consumption | 34.5 M MMBtu |
Ranked #241 out of 11,835 Power Plants Nationwide | |
Ranked #126 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #7 out of 75 Alabama Power Plants | |
Ranked #4 out of 36 Alabama Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Hillabee Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hillabee Energy Center.
Monthly Net Generation for Hillabee Energy Center
Hillabee Energy Center Details
Summary Information | |
---|---|
Plant Name | Hillabee Energy Center (55411) |
Plant Address | 152 Brick Plant Road, Alexander City, AL 35010 |
Utility | CER Generation LLC (55987) |
Latitude, Longitude | 33.00067, -85.90328 |
Generation Dates on File | Jun 2010 to Aug 2024 |
Initial Operation Date | June 2010 |
Annual Generation | 4.5 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | Alabama Power Co (195) AL |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | TRANSCONTINENTAL GAS PIPELINE |
Natural Gas Storage | No |
Generator HEC1 Details Operating June 2010
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 258.4 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 234.4 MW |
Winter Capacity | 261 MW |
Minimum Load | 145 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2010 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator HEC2 Details Operating June 2010
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 258.4 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 234.4 MW |
Winter Capacity | 261 MW |
Minimum Load | 145 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2010 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator HECS Details Operating June 2010
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 306 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 283.9 MW |
Winter Capacity | 293 MW |
Minimum Load | 70 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2010 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Hillabee Energy Center Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#116 | Keys Energy Center | Brandywine, MD | 4.7 TWh |
#117 | Potomac Energy Center, LLC | Leesburg, VA | 4.7 TWh |
#118 | Coughlin Power Station | St Landry, LA | 4.6 TWh |
#119 | Formosa Utility Venture Ltd | Point Comfort, TX | 4.7 TWh |
#120 | Kiamichi Energy Facility | Kiowa, OK | 4.6 TWh |
#121 | Fort St Vrain | Platteville, CO | 4.6 TWh |
#122 | High Desert Power Plant | Victorville, CA | 4.6 TWh |
#123 | Kendall County Generation Facility | Minooka, IL | 4.6 TWh |
#124 | Tenaska Virginia Generating Station | Scottsville, VA | 4.6 TWh |
#125 | Dearborn Industrial Generation | Dearborn, MI | 5.7 TWh |
#127 | Fox Energy Center | Wrightstown, WI | 4.5 TWh |
#128 | Morgan Energy Center | Decatur, AL | 4.5 TWh |
#129 | Lower Mount Bethel Energy | Bangor, PA | 4.4 TWh |
#130 | Channel Energy Center LLC | Pasadena, TX | 4.9 TWh |
#131 | Hill Top Energy Center, LLC | Carmichaels, PA | 4.4 TWh |
#132 | Dresden Energy Facility | Dresden, OH | 4.4 TWh |
#133 | Lowman Energy Center | Leroy, AL | 4.3 TWh |
#134 | Cane Run | Louisville, KY | 4.3 TWh |
#135 | Bosque County Peaking | Laquna Park, TX | 4.3 TWh |
#136 | Cricket Valley Energy | Dover, NY | 4.3 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hillabee Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AMEA Peaking | Sylacauga, AL | 46.3 GWh | 24.8 mi |
ANAD Solar Array | Anniston Army Depot, AL | 10.7 GWh | 43.4 mi |
Bartletts Ferry | Salem, AL | 397.0 GWh | 52.6 mi |
Calhoun Energy Center | Eastaboga, AL | 270.0 GWh | 40.8 mi |
E C Gaston | Wilsonville, AL | 3.9 TWh | 36.2 mi |
H Allen Franklin Combined Cycle | Smiths, AL | 12.3 TWh | 54.1 mi |
Harris Dam | Lineville, AL | 128.9 GWh | 24.4 mi |
International Paper Prattville Mill | Prattville, AL | 608.4 GWh | 52.1 mi |
Jordan Dam | Wetumpka, AL | 263.3 GWh | 33.4 mi |
Kimberly-Clark Solar | LaGrange, GA | 2.7 GWh | 50.4 mi |
LaFayette Solar Farm | LaFayette, AL | 166.8 GWh | 31.1 mi |
Lay Dam | Clanton, AL | 454.7 GWh | 35.8 mi |
Logan Martin Dam | Vincent, AL | 343.5 GWh | 38.6 mi |
Martin Dam | Dadeville, AL | 326.6 GWh | 22.1 mi |
Mitchell Dam | Verbena, AL | 409.4 GWh | 34.2 mi |
Thurlow Dam | Tallassee, AL | 222.2 GWh | 32.2 mi |
U S Alliance Coosa Pines | Coosa Pines, AL | 139.3 GWh | 34.6 mi |
Walter Bouldin Dam | Wetumpka, AL | 514.5 GWh | 36.3 mi |
West Point (GA) | West Point, GA | 198.7 GWh | 41.8 mi |
Yates Dam | Tallassee, AL | 118.8 GWh | 29.5 mi |