High Springs Solar Power Plant
N.W. 174th Ave, High Springs, FL 32643Plant Summary Information
High Springs Solar Power Plant is ranked #42 out of 171 solar farms in Florida in terms of total annual net electricity generation.
High Springs Solar Power Plant generated 38.3 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | High Springs Solar Power Plant |
---|---|
Utility Name | Duke Energy Florida, LLC |
Location | Alachua County, FL |
Initial Operation Date | April 2023 |
Last Update | Sep 2024 |
Annual Generation | 143.3 GWh |
Annual Consumption | 517.6 k MMBtu |
Ranked #2,725 out of 11,852 Power Plants Nationwide | |
Ranked #416 out of 5,655 Solar Power Plants Nationwide | |
Ranked #112 out of 279 Florida Power Plants | |
Ranked #42 out of 171 Florida Solar Power Plants | |
Fuel Types | Solar |
Map of High Springs Solar Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for High Springs Solar Power Plant.
Monthly Net Generation for High Springs Solar Power Plant
High Springs Solar Power Plant Details
Summary Information | |
---|---|
Plant Name | High Springs Solar Power Plant (65172) |
Plant Address | N.W. 174th Ave, High Springs, FL 32643 |
Utility | Duke Energy Florida, LLC (6455) |
Latitude, Longitude | 29.81002, -82.63984 |
Generation Dates on File | Apr 2023 to Sep 2024 |
Initial Operation Date | April 2023 |
Annual Generation | 143.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Florida Inc (FPC) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Duke Energy Florida, LLC (6455) FL |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Generator PV1 Details Operating April 2023
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 74.9 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 74.9 MW |
Winter Capacity | 74.9 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2023 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 100.5 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
High Springs Solar Power Plant Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#406 | Blue Heron Solar | Clewiston, FL | 145.0 GWh |
#407 | Regulus Solar Project | Bakersfield, CA | 144.5 GWh |
#408 | Palmer Solar | Fountain, CO | 144.1 GWh |
#409 | Santa Fe Solar Power Plant | Archer, FL | 143.9 GWh |
#410 | Rodeo Solar Center | Arcadia, FL | 143.9 GWh |
#411 | Prairie Creek FL | TBD, FL | 143.8 GWh |
#412 | Indian River Solar Center | Vero Beach, FL | 143.7 GWh |
#413 | Sunflower County | Ruleville, MS | 143.6 GWh |
#414 | Magnolia Springs Solar Center | Green Cove Springs, FL | 143.5 GWh |
#415 | Longbow Solar, LLC | Liverpool, TX | 143.4 GWh |
#417 | Centerfield Cooper Solar, LLC | Chesterfield, SC | 142.9 GWh |
#418 | Eastover Solar | Eastover, SC | 142.2 GWh |
#419 | Encino Solar Energy Center | Rio Rancho Estates, NM | 142.2 GWh |
#420 | Palm Bay Solar | Palm Bay, FL | 142.0 GWh |
#421 | Dileo Solar | Clifton, TX | 142.0 GWh |
#422 | Pecan Solar | Pleasant Hill, NC | 141.8 GWh |
#423 | Cotton Creek Solar Energy Center | McDavid, FL | 141.7 GWh |
#424 | Everglades Solar Energy Center | Homestead, FL | 141.7 GWh |
#425 | Trent River Solar, LLC | Pollocksville, NC | 141.3 GWh |
#426 | Innovative Solar 46 | Hope Mills, NC | 141.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding High Springs Solar Power Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bell Ridge Solar | Trenton, FL | 186.2 GWh | 7.6 mi |
Butler Plaza | Gainesville, FL | 2.0 GWh | 20.2 mi |
Columbia Solar Power Plant | Fort White, FL | 145.2 GWh | 6 mi |
County Line Renewable Energy Center | High Springs, FL | 18.0 GWh | 2.2 mi |
Deerhaven Generating Station | Gainesville, FL | 692.0 GWh | 15.5 mi |
Deerhaven Renewable | Gainesville, FL | 274.3 GWh | 14.9 mi |
Echo River Solar | Live Oak, FL | 152.5 GWh | 36.2 mi |
Egret Solar Center | Glen St. Mary, FL | 140.4 GWh | 42.5 mi |
Hardeetown Solar Power Plant | Chiefland, FL | 150.8 GWh | 25.5 mi |
Hildreth Solar Power Plant | O'Brien, FL | 162.9 GWh | 15.3 mi |
Horizon Solar Energy Center | Hawthorne, FL | 117.9 GWh | 36.3 mi |
John R Kelly | Gainesville, FL | 603.3 GWh | 22.2 mi |
Northern Preserve Solar | Glen St. Mary, FL | 117.9 GWh | 39 mi |
Santa Fe Solar Power Plant | Archer, FL | 143.9 GWh | 23.5 mi |
Solar Park Gainesville, LLC | Gainesville, FL | 1.5 GWh | 19.6 mi |
South Energy Center | Gainesville, FL | 44.0 GWh | 21.6 mi |
Sunshine Gateway Solar Energy Center | Lake City, FL | 128.0 GWh | 33.8 mi |
Trenton Solar Power Plant | Trenton, FL | 136.3 GWh | 17.2 mi |
Union Springs Solar Center | Lake Butler, FL | 145.7 GWh | 23.2 mi |
University of Florida | Gainesville, FL | 377.2 GWh | 21 mi |