Hidalgo Energy Center
4005 N. Seminary Rd, Edinburg, TX 78539Plant Summary Information
Hidalgo Energy Center is ranked #55 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
Hidalgo Energy Center is comprised of 3 generators and generated 901.3 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Hidalgo Energy Center |
---|---|
Utility Name | Calpine Corp - Hidalgo |
Location | Hidalgo County, TX |
Initial Operation Date | June 2000 |
Last Update | Sep 2024 |
Annual Generation | 2.0 TWh |
Annual Consumption | 17.2 M MMBtu |
Ranked #515 out of 11,852 Power Plants Nationwide | |
Ranked #321 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #71 out of 754 Texas Power Plants | |
Ranked #55 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Hidalgo Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hidalgo Energy Center.
Monthly Net Generation for Hidalgo Energy Center
Hidalgo Energy Center Details
Summary Information | |
---|---|
Plant Name | Hidalgo Energy Center (55545) |
Plant Address | 4005 N. Seminary Rd, Edinburg, TX 78539 |
Utility | Calpine Corp - Hidalgo (2934) |
Latitude, Longitude | 26.34172, -98.17576 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | June 2000 |
Annual Generation | 2.0 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 00-3562-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | City Of McAllen |
Ash Impoundment | No |
Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | CALPINE TEXAS PIPELINE LP |
Pipeline Notes | NG was bought by Calpine from Duke/Conoco/Phillps last year |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator CTG1 Details Operating June 2000
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Jointly Owned |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | DUKE_CC1 |
Nameplate Capacity | 176.6 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 157 MW |
Winter Capacity | 165 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2000 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG2 Details Operating June 2000
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Jointly Owned |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | DUKE_GT2_CCU |
Nameplate Capacity | 176.6 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 159 MW |
Winter Capacity | 178 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | May 2023 |
Status | Operating |
---|---|
First Operation Date | June 2000 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG1 Details Operating June 2000
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Jointly Owned |
Duct Burners | No |
Nameplate Capacity | 198.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 177 MW |
Winter Capacity | 187 MW |
Minimum Load | 62 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | May 2023 |
Status | Operating |
First Operation Date | June 2000 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Pulverized Coal Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Hidalgo Energy Center Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Brownsville Public Utilities Board | P.O. Box 3270, Brownsville, TX 78523 | Generator CTG1 | 21.00% |
Calpine Corp - Hidalgo | 717 Texas Avenue, Suite 1000, Houston, TX 77002 | Generator CTG1 | 79.00% |
Brownsville Public Utilities Board | P.O. Box 3270, Brownsville, TX 78523 | Generator CTG2 | 21.00% |
Calpine Corp | 717 Texas Avenue, Houston, TX 77002 | Generator CTG2 | 79.00% |
Brownsville Public Utilities Board | P.O. Box 3270, Brownsville, TX 78523 | Generator STG1 | 21.00% |
Calpine Corp | 717 Texas Avenue, Houston, TX 77002 | Generator STG1 | 79.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#311 | Brooklyn Navy Yard Cogeneration | Brooklyn, NY | 2.1 TWh |
#312 | Louisiana 1 | Baton Rouge, LA | 2.8 TWh |
#313 | Freeport Energy | Freeport, TX | 2.1 TWh |
#314 | Midulla Generating Station | Bowling Green, FL | 2.1 TWh |
#315 | Texas City Power Plant | Texas City, TX | 2.1 TWh |
#316 | Jim Bridger | Point of Rocks, WY | 8.3 TWh |
#317 | Coyote Springs | Boardman, OR | 2.0 TWh |
#318 | Apache Station | Cochise, AZ | 2.2 TWh |
#319 | Bayou Cogen Plant | Pasadena, TX | 2.3 TWh |
#320 | Sand Hill | Austin, TX | 2.0 TWh |
#322 | Frontera Energy Center | Mission, TX | 2.0 TWh |
#323 | ANP Blackstone Energy Project | Blackstone, MA | 2.0 TWh |
#324 | Watson Cogeneration | Carson, CA | 2.4 TWh |
#325 | Mint Farm Generating Station | Longview, WA | 2.0 TWh |
#326 | Moselle | Moselle, MS | 2.0 TWh |
#327 | St Francis Energy Facility | Campbell, MO | 2.0 TWh |
#328 | Jackson Generating Station | Jackson, MI | 2.0 TWh |
#329 | Sweeny Cogen Facility | Old Ocean, TX | 2.6 TWh |
#330 | O W Sommers | San Antonio, TX | 1.9 TWh |
#331 | Cedar Bayou 4 | Eldon, TX | 1.9 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hidalgo Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Citrus City | Mission, TX | 645.0 MWh | 11 mi |
Frontera Energy Center | Mission, TX | 2.0 TWh | 16.6 mi |
HEB00038 | San Juan, TX | 241.0 MWh | 9.6 mi |
Hidalgo Wind Farm II | Edinburg, TX | 132.9 GWh | 19.8 mi |
Hidalgo Wind Farm LLC | McCook, TX | 687.8 GWh | 16.9 mi |
Los Vientos V Wind Power | Rio Grande City, TX | 334.6 GWh | 25 mi |
Magic Valley Generating Station | Edinburg, TX | 2.5 TWh | 0.9 mi |
Magic Valley Wind Farm I LLC | San Perlita, TX | 377.1 GWh | 31.4 mi |
Nebula Solar | La Feria, TX | 253.2 GWh | 29.1 mi |
Raymond Wind Farm, LLC | Lyford, TX | 611.8 GWh | 24.5 mi |
Red Gate Power Plant | Edinburg, TX | 247.7 GWh | 7.6 mi |
Ridge Rd | Alamo, TX | 684.0 MWh | 12.9 mi |
Rio Grande Valley Sugar Growers | Santa Rosa, TX | 92.0 MWh | 19.8 mi |
Santa Rosa | Santa Rosa, TX | 706.0 MWh | 23.1 mi |
Vancourt Solar Interconnections | La Feria, TX | 86.2 GWh | 29.1 mi |
WAL3320 | Palmhurst, TX | 368.0 MWh | 10.3 mi |
WAL3886 | Edinburg, TX | 372.0 MWh | 5.4 mi |
WAL452 | Mcallen, TX | 368.0 MWh | 8 mi |
WAL5165 | Alamo, TX | 391.0 MWh | 10.8 mi |
West Raymond Wind Farm LLC | Lyford, TX | 706.0 GWh | 11.6 mi |