Plant Summary Information

Henry Miller RD is ranked #728 out of 747 solar farms in California in terms of total annual net electricity generation.

Henry Miller RD generated 158.7 MWh during the 3-month period between September 2022 to December 2022.

Plant NameHenry Miller RD
Utility NameHenry Miller Reclamation District
LocationMerced County, CA
Initial Operation DateOctober 2018
Last Update Dec 2022
Annual Generation 593.0 MWh
Annual Consumption 2.0 k MMBtu
Ranked #10,452 out of 11,249 Power Plants Nationwide
Ranked #5,029 out of 5,158 Solar Power Plants Nationwide
Ranked #1,466 out of 1,501 California Power Plants
Ranked #728 out of 747 California Solar Power Plants
Fuel Types Solar

Map of Henry Miller RD

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Henry Miller RD.

Create Your Account Today

Monthly Net Generation for Henry Miller RD

Henry Miller RD Details

Summary Information
Plant NameHenry Miller RD (66492)
Plant Address7767 Santa Rita Grade Dos Palos, CA 93620
UtilityHenry Miller Reclamation District (65537)
Latitude, Longitude37.0543, -120.63523
Generation Dates on FileJan 2022 to Dec 2022
Initial Operation DateOctober 2018
Annual Generation 593.0 MWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeWater Supply and Irrigation Systems (22131)
Sector Commercial Non-CHP (4)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerPacific Gas & Electric Co. (14328) CA
Grid Voltage 12.00 kV
Energy StorageNo

Generator HMRD1 Details Operating October 2018

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity1.5 MW
Summer Capacity1.5 MW
Winter Capacity1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateOctober 2018
Combined Heat & Power No
Sector NameCommercial Non-CHP (4)
Energy SourceSolar
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Solar Details
Fixed TiltYes
Azimuth Angle180
Tilt Angle30
DC Net Capacity1.9 MW
Crystalline SiliconYes
Net Metering AgreementYes
Net Metering DC Capacity1.9 MW
Virtual Net Metering AgreementNo

Henry Miller RD Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#5019Jefferson SolarHartsville, SC658.0 MWh
#5020Coxsackie SolarCoxsackie, NY651.0 MWh
#5021Crown Cooling FacilityBrawley, CA650.3 MWh
#5022Arba Solar Energy StorageHamlet, NC618.0 MWh
#5023Three CreeksParrish, FL637.0 MWh
#5024CSU Fresno Solar ProjectFresno, CA635.0 MWh
#5025NES Rutgers SolarLakewood, NJ634.1 MWh
#5026Francis Scott Key MallFrederick, MD633.4 MWh
#5027Van Epps SolarFultonville, NY619.0 MWh
#5028Mariani Packing Vacaville SolarVacaville, CA608.6 MWh
#50306685 Santa Barbara CtElkridge, MD589.0 MWh
#5031Yolo County Solar ProjectWoodland, CA585.7 MWh
#5032CSP Los AngelesLancaster, CA585.0 MWh
#5033KDC Solar TC Little Patuxent WWTP LLCWest Friendship, MD572.0 MWh
#5034Staples La Mirada, CALa Mirada, CA571.1 MWh
#5035Los Alamos PV SiteLos Alamos, NM561.0 MWh
#5036KDC Solar TC George Howard LLCWest Friendship, MD558.0 MWh
#5037Fourmile CreekAltha, FL548.0 MWh
#5038Fremont CA AutoFactoryFremont, CA545.0 MWh
#5039Chuckawalla Valley State PrisonBlythe, CA544.1 MWh

Nearby Power Plants

Below are closest 20 power plants surrounding Henry Miller RD.

Plant NamePlant LocationAnnual GenerationDistance
2097 Helton Solar ProjectMerced, CA3.5 GWh21.8 mi
Adera SolarChowchilla, CA27.5 GWh17.7 mi
Ampersand Chowchilla Biomass LLCChowchilla, CA58.4 GWh21.6 mi
Broadway 3 - UC Merced 1Merced, CA1.8 GWh24.2 mi
Chowchilla IIChowchilla, CA25.9 GWh21.6 mi
Diamond H Dairy PowerChowchilla, CA11.4 GWh14.7 mi
Dos PalosDos Palos, CA1.7 GWh5 mi
El Nido FacilityEl Nido, CA47.8 GWh12.1 mi
Firebaugh-CCS-PV-1Firebaugh, CA1.9 GWh22.1 mi
Five H Farms Solar ArrayMerced, CA1.5 GWh19.4 mi
Merced 1 PVLos Banos, CA7.6 GWh14.1 mi
Merced Solar LLCMerced, CA4.5 GWh16.9 mi
Mission Solar LLCMerced, CA4.5 GWh17 mi
Oro LomaOro Loma, CA55.0 GWh12.4 mi
Quinto Solar PV ProjectGustine, CA293.1 GWh23.6 mi
Sun Harvest Solar NDP1Dos Palos, CA4.0 GWh1 mi
Vega SolarLos Banos, CA49.1 GWh13.5 mi
Wonderful FirebaughFirebaugh, CA4.8 GWh23 mi
Wonderful Orchards - New ColumbiaFirebaugh, CA11.0 GWh23.6 mi
Wright Solar ParkLos Banos, CA482.3 GWh18 mi