8900 Highway 6, Missouri City, TX 77459Plant Summary Information
HEB00110 is ranked #278 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
HEB00110 is comprised of 3 generators and generated 53.8 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | HEB00110 |
---|---|
Utility Name | Texas Microgrid, LLC |
Location | Fort Bend County, TX |
Initial Operation Date | September 2017 |
Last Update | Dec 2023 |
Annual Generation | 244.0 MWh |
Annual Consumption | 3.8 k MMBtu |
Ranked #11,234 out of 11,835 Power Plants Nationwide | |
Ranked #2,078 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #715 out of 749 Texas Power Plants | |
Ranked #278 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of HEB00110
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for HEB00110.
Monthly Net Generation for HEB00110
HEB00110 Details
Summary Information | |
---|---|
Plant Name | HEB00110 (65269) |
Plant Address | 8900 Highway 6, Missouri City, TX 77459 |
Utility | Texas Microgrid, LLC (64449) |
Latitude, Longitude | 29.53658, -95.53628 |
Generation Dates on File | Jan 2021 to Dec 2023 |
Initial Operation Date | September 2017 |
Annual Generation | 244.0 MWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | CenterPoint Energy (8901) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | SIENERGY LP |
Natural Gas Storage | No |
Generator H1101 Details Operating September 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator H1102 Details Operating September 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator H1103 Details Operating September 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
HEB00110 Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2068 | WAL5612 | Houston, TX | 264.0 MWh |
#2069 | SPI Anderson 2 | Anderson, CA | 141.6 GWh |
#2070 | Martinsville LFG Generator | Martinsville, VA | 262.0 MWh |
#2071 | WAL504 | Galveston, TX | 262.0 MWh |
#2072 | WAL2724 | Pasadena, TX | 255.0 MWh |
#2073 | Walt Bailey Bioenergy Facility | Washington, DC | 57.0 GWh |
#2074 | WAL565 | Corsicana, TX | 249.0 MWh |
#2075 | WAL4526 | Houston, TX | 249.0 MWh |
#2076 | MM West Covina | West Covina, CA | 39.9 GWh |
#2077 | Oberlin (OH) | Oberlin, OH | 292.0 MWh |
#2079 | BUC00040 | Katy, TX | 243.0 MWh |
#2080 | HEB00038 | San Juan, TX | 241.0 MWh |
#2081 | Kent County Waste to Energy Facility | Grand Rapids, MI | 96.5 GWh |
#2082 | Ebensburg Power | Ebensburg, PA | 285.1 GWh |
#2083 | Oroville Cogeneration LP | Oroville, CA | 235.0 MWh |
#2084 | WAL768 | Katy, TX | 230.0 MWh |
#2085 | Sycamore (WI) | Madison, WI | 229.0 MWh |
#2086 | WAL414 | Wichita Falls, TX | 227.0 MWh |
#2087 | HEB00054 | Houston, TX | 220.0 MWh |
#2088 | WAL3432 | Desoto, TX | 218.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding HEB00110.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Braes Bayou Plant | Richmond, TX | 352.1 GWh | 6.4 mi |
Brotman Power Station | Rosharon, TX | 380.8 GWh | 13.4 mi |
Friendswood Energy | Houston, TX | 88.2 GWh | 9.2 mi |
FTBLID2 | Sugarland, TX | 1.8 GWh | 6.6 mi |
HEB00063 | Pearland, TX | 429.0 MWh | 8.9 mi |
HO Clarke Generating | Houston, TX | 421.8 GWh | 9.1 mi |
Jack Fusco Energy Center | Thompsons, TX | 3.2 TWh | 6.9 mi |
Mckeever | Fresno, TX | 578.0 MWh | 3.9 mi |
OTHERNFBWA | Houston, TX | 178.0 MWh | 12.7 mi |
Petra Nova Carbon Capture Cogen | Thompsons, TX | 109.0 GWh | 7.3 mi |
Southwick | Houston, TX | 367.0 MWh | 11 mi |
TECO CHP-1 | Houston, TX | 106.3 GWh | 14.2 mi |
W A Parish | Thompsons, TX | 11.6 TWh | 6.8 mi |
WAL2993 | Sugar Land, TX | 319.0 MWh | 8.4 mi |
WAL3302 | Houston, TX | 369.0 MWh | 10 mi |
WAL3572 | Pearland, TX | 146.0 MWh | 9.3 mi |
WAL3584 | Houston, TX | 297.0 MWh | 13.6 mi |
WAL546 | Richmond, TX | 291.0 MWh | 13.6 mi |
WAL772 | Houston, TX | 287.0 MWh | 14.4 mi |
Westhollow Technology Center | Houston, TX | 21.8 GWh | 14.5 mi |