HEB00063
TBD, Pearland, TX 77584Plant Summary Information
HEB00063 is ranked #188 out of 298 natural gas power plants in Texas in terms of total annual net electricity generation.
HEB00063 is comprised of 4 generators and generated 94.6 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | HEB00063 |
---|---|
Utility Name | Texas Microgrid, LLC |
Location | Brazoria County, TX |
Initial Operation Date | June 2017 |
Last Update | Dec 2023 |
Annual Generation | 429.0 MWh |
Annual Consumption | 6.6 k MMBtu |
Ranked #10,916 out of 11,623 Power Plants Nationwide | |
Ranked #1,908 out of 2,187 Natural Gas Power Plants Nationwide | |
Ranked #655 out of 769 Texas Power Plants | |
Ranked #188 out of 298 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of HEB00063
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for HEB00063.
Monthly Net Generation for HEB00063
HEB00063 Details
Summary Information | |
---|---|
Plant Name | HEB00063 (66549) |
Plant Address | TBD, Pearland, TX 77584 |
Utility | Texas Microgrid, LLC (64449) |
Latitude, Longitude | 29.55952, -95.39038 |
Generation Dates on File | Jan 2022 to Dec 2023 |
Initial Operation Date | June 2017 |
Annual Generation | 429.0 MWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | NA |
Ash Impoundment | |
Transmission / Distribution Owner | CenterPoint Energy (8901) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | CENTERPOINT ENERGY ENTEX |
Natural Gas Storage | No |
Generator H0631 Details Operating June 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Unit Code | H063 |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator H0632 Details Operating June 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Unit Code | H063 |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator H0633 Details Operating June 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Unit Code | H063 |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator H0634 Details Operating June 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Unit Code | H063 |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2017 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
HEB00063 Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1898 | Red Wing | Red Wing, MN | 110.3 GWh |
#1899 | Tom G Smith | Lake Worth, FL | 444.0 MWh |
#1900 | Wellesley College Central Utility Plant | Wellesley, MA | 480.2 MWh |
#1901 | Covanta Delaware Valley | Chester, PA | 532.9 GWh |
#1902 | HEB00092 | Victoria, TX | 473.0 MWh |
#1903 | Covanta Lake County Energy | Okahumpka, FL | 85.4 GWh |
#1904 | Northwest Community Hospital | Arlington Heights, IL | 467.0 MWh |
#1905 | Hopewell Cogeneration NJ | Pennington, NJ | 433.0 MWh |
#1906 | Harbec Energy | Ontario, NY | 977.0 MWh |
#1907 | HEB00095 | Laredo, TX | 432.0 MWh |
#1909 | HEB00591 | Round Rock, TX | 425.0 MWh |
#1910 | HEB_CPS00085 | San Antonio, TX | 422.0 MWh |
#1911 | Hopewell Power Station | Hopewell, VA | 345.0 GWh |
#1912 | Seadrift Coke LP | Port Lavaca, TX | 22.7 GWh |
#1913 | WAL791 | Alice, TX | 409.0 MWh |
#1914 | WAL5713 | Laredo, TX | 409.0 MWh |
#1915 | HEB00069 | Corpus Christi, TX | 407.0 MWh |
#1916 | WAL744 | Humble, TX | 404.0 MWh |
#1917 | WAL2257 | Houston, TX | 404.0 MWh |
#1918 | WAL3297 | Houston, TX | 402.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding HEB00063.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Friendswood Energy | Houston, TX | 88.2 GWh | 7.1 mi |
HEB00054 | Houston, TX | 220.0 MWh | 8.9 mi |
HEB00110 | Missouri City, TX | 244.0 MWh | 8.9 mi |
HO Clarke Generating | Houston, TX | 468.0 GWh | 7 mi |
Houston Plant | Houston, TX | 12.4 GWh | 13.2 mi |
Mckeever | Fresno, TX | 578.0 MWh | 6.4 mi |
Rice University | Houston, TX | 18.6 GWh | 11.2 mi |
Southwick | Houston, TX | 367.0 MWh | 2.9 mi |
TECO CHP-1 | Houston, TX | 106.3 GWh | 10 mi |
Texas Petrochemicals | Houston, TX | 236.3 GWh | 12.6 mi |
The Methodist Hospital, Gas Turbine | Houston, TX | 13.8 GWh | 10.4 mi |
Tortolas | Alvin, TX | 2.1 GWh | 12.2 mi |
WAL3302 | Houston, TX | 369.0 MWh | 13.2 mi |
WAL3425 | Houston, TX | 287.0 MWh | 10.4 mi |
WAL3510 | Pearland, TX | 162.0 MWh | 9.3 mi |
WAL3572 | Pearland, TX | 146.0 MWh | 0.5 mi |
WAL3584 | Houston, TX | 297.0 MWh | 12.2 mi |
WAL462 | Alvin, TX | 324.0 MWh | 13.5 mi |
WAL5612 | Houston, TX | 264.0 MWh | 11.8 mi |
WAL872 | Pearland, TX | 296.0 MWh | 6.5 mi |