Haystack Wind Project, LLC
81613 569th Avenue, Carroll, NE 68723Plant Summary Information
Haystack Wind Project, LLC is ranked #13 out of 116 power plants in Nebraska in terms of total annual net electricity generation.
Haystack Wind Project, LLC generated 104.8 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Haystack Wind Project, LLC |
---|---|
Utility Name | Haystack Wind Project, LLC |
Location | Wayne County, NE |
Initial Operation Date | March 2022 |
Last Update | Sep 2024 |
Annual Generation | 811.7 GWh |
Annual Consumption | 3.0 M MMBtu |
Ranked #866 out of 11,852 Power Plants Nationwide | |
Ranked #127 out of 1,345 Wind Power Plants Nationwide | |
Ranked #13 out of 116 Nebraska Power Plants | |
Ranked #8 out of 34 Nebraska Wind Power Plants | |
Fuel Types | Wind |
Map of Haystack Wind Project, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Haystack Wind Project, LLC.
Monthly Net Generation for Haystack Wind Project, LLC
Haystack Wind Project, LLC Details
Summary Information | |
---|---|
Plant Name | Haystack Wind Project, LLC (64139) |
Plant Address | 81613 569th Avenue, Carroll, NE 68723 |
Utility | Haystack Wind Project, LLC (63764) |
Latitude, Longitude | 42.26303, -97.19566 |
Generation Dates on File | Mar 2022 to Sep 2024 |
Initial Operation Date | March 2022 |
Annual Generation | 811.7 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Nebraska Public Power District (13337) NE |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator 4444 Details Operating March 2022
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 298 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 298 MW |
Winter Capacity | 298 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 69 |
Turbine Details | |
Number Of Turbines | 69 |
---|---|
Predominant Turbine Manufacturer | Siemens Gamesa |
Predominant Turbine Model Number | SG 5.0-145 |
Design Wind Speed | 19.5 MPH |
Wind Quality Class | 1 - High Wind |
Turbine Hub Height Feet | 336.3 |
Haystack Wind Project, LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#117 | O'Brien Wind | Primghar, IA | 834.6 GWh |
#118 | Pioneer Prairie Wind Farm | McIntire, IA | 834.2 GWh |
#119 | Roundhouse Wind Energy Project | Cheyenne, WY | 832.9 GWh |
#120 | Blazing Star Wind Farm 1 | Hendricks, MN | 830.9 GWh |
#121 | Plum Creek Wind Project (NE) | Winside, NE | 823.2 GWh |
#122 | Tecolote Wind LLC | Duran, NM | 822.8 GWh |
#123 | Horse Creek Wind Farm | Weinert, TX | 818.8 GWh |
#124 | Cimarron Bend Wind Project II, LLC | Minneola, KS | 817.7 GWh |
#125 | Burke Wind, LLC | Bowbells, ND | 813.0 GWh |
#126 | Upstream Wind Energy LLC | Neligh, NE | 812.6 GWh |
#128 | Crocker Wind Farm | Conde, SD | 811.3 GWh |
#129 | Golden West Power Partners LLC | Calhan, CO | 810.9 GWh |
#130 | Southern Hills Wind Farm | Creston, IA | 809.5 GWh |
#131 | Sunflower Energy Center, LLC | Peabody, KS | 808.8 GWh |
#132 | Ninnescah Wind Energy, LLC | Cunningham, KS | 806.6 GWh |
#133 | Lundgren Wind Project | Otho, IA | 805.8 GWh |
#134 | Crowned Ridge Wind II Energy Center | Watertown, SD | 804.3 GWh |
#135 | Cedar Bluff Wind, LLC | Brownwell, KS | 802.5 GWh |
#136 | Freeborn Wind Farm | Glenville, MN | 799.1 GWh |
#137 | Ledyard Windpower, LLC | Lakota, IA | 797.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Haystack Wind Project, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Creston Ridge II, LLC | Creston, NE | 24.6 GWh | 41.7 mi |
Creston Ridge Wind Farm | Creston, NE | 26.1 GWh | 41.6 mi |
Crofton Bluffs Wind LLC | Bloomfield, NE | 119.0 GWh | 35.9 mi |
Cuming County Renewables, LLC | Wisner, NE | 10.0 GWh | 24 mi |
Elkhorn Ridge Wind LLC | Bloomfield, NE | 157.2 GWh | 37 mi |
Emerson | Emerson, NE | 7.0 MWh | 23.9 mi |
George Neal North | Sergeant Bluff, IA | 798.7 GWh | 41.9 mi |
Laurel | Laurel, NE | 3.0 MWh | 12.8 mi |
Madison Utilities | Madison, NE | 26.0 MWh | 32.8 mi |
Pender | Pender, NE | 46.0 MWh | 27.1 mi |
Plum Creek Wind Project (NE) | Winside, NE | 823.2 GWh | 7 mi |
Rattlesnake Creek Wind Project | Dixon, NE | 897.3 GWh | 20.3 mi |
Sholes Wind Energy Center | Randolph, NE | 721.6 GWh | 9.3 mi |
South 49th 013445 SCS Norfolk, LLC | Norfolk, NE | 18.2 GWh | 21.7 mi |
South Sioux City Solar | Dakota, NE | 4.1 GWh | 40.9 mi |
Upstream Wind Energy LLC | Neligh, NE | 812.6 GWh | 39.7 mi |
Wakefield | Wakefield, NE | 14.0 MWh | 17.1 mi |
Wayne IC | Wayne, NE | 45.0 MWh | 9.4 mi |
West Point Municipal | West Point, NE | 139.0 MWh | 38 mi |
Wisner | Wisner, NE | 58.0 MWh | 23.8 mi |