H Allen Franklin Combined Cycle
6109 Lee Road 249, Smiths, AL 36877Plant Summary Information
H Allen Franklin Combined Cycle is ranked #45 out of 11,866 power plants nationwide in terms of total annual net electricity generation.
H Allen Franklin Combined Cycle is comprised of 9 generators and generated 3.0 TWh during the 3-month period between July 2024 to October 2024.
Plant Name | H Allen Franklin Combined Cycle |
---|---|
Utility Name | Southern Power Co |
Location | Lee County, AL |
Initial Operation Date | June 2002 |
Last Update | Oct 2024 |
Annual Generation | 11.9 TWh |
Annual Consumption | 90.2 M MMBtu |
Ranked #45 out of 11,866 Power Plants Nationwide | |
Ranked #6 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #5 out of 75 Alabama Power Plants | |
Ranked #2 out of 36 Alabama Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of H Allen Franklin Combined Cycle
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for H Allen Franklin Combined Cycle.
Monthly Net Generation for H Allen Franklin Combined Cycle
H Allen Franklin Combined Cycle Details
Summary Information | |
---|---|
Plant Name | H Allen Franklin Combined Cycle (7710) |
Plant Address | 6109 Lee Road 249, Smiths, AL 36877 |
Utility | Southern Power Co (17650) |
Latitude, Longitude | 32.6078, -85.0975 |
Generation Dates on File | Jun 2002 to Oct 2024 |
Initial Operation Date | June 2002 |
Annual Generation | 11.9 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Chattahoochee River |
Ash Impoundment | No |
Transmission / Distribution Owner | Georgia Power Co (7140) GA |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | SOUTHERN NATURAL GAS COMPANY |
Natural Gas Storage | No |
Generator CT1A Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G481 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 177.5 MW |
Winter Capacity | 188.5 MW |
Minimum Load | 115 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT1B Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G481 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 177.5 MW |
Winter Capacity | 188.5 MW |
Minimum Load | 115 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT2A Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G501 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 177.8 MW |
Winter Capacity | 190.3 MW |
Minimum Load | 125 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT2B Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G501 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 177.8 MW |
Winter Capacity | 190.3 MW |
Minimum Load | 125 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST1 Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | G481 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 213.3 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 240 MW |
Winter Capacity | 240 MW |
Minimum Load | 120 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST2 Details Operating June 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | G501 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 281.9 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 293 MW |
Winter Capacity | 293 MW |
Minimum Load | 130 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2002 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT3A Details Operating May 2008
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G100 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 182.6 MW |
Winter Capacity | 196.6 MW |
Minimum Load | 109 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2008 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT3B Details Operating May 2008
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G100 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 203.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 182.6 MW |
Winter Capacity | 196.6 MW |
Minimum Load | 109 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2008 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST3 Details Operating May 2008
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | G100 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 281.9 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 293 MW |
Winter Capacity | 293 MW |
Minimum Load | 112 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2008 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
H Allen Franklin Combined Cycle Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1 | West County Energy Center | Loxahatchee, FL | 20.8 TWh |
#2 | Jack McDonough | Smyrna, GA | 18.2 TWh |
#3 | Barry | Bucks, AL | 13.9 TWh |
#4 | Crystal River | Crystal River, FL | 16.2 TWh |
#5 | Hines Energy Complex | Bartow, FL | 12.0 TWh |
#7 | Greensville County Power Station | Emporia, VA | 11.4 TWh |
#8 | Okeechobee Clean Energy Center | Okeechobee, FL | 11.4 TWh |
#9 | Union Power Station | El Dorado, AR | 11.3 TWh |
#10 | Guernsey Power Station | Byesville, OH | 10.9 TWh |
#11 | Midland Cogeneration Venture | Midland, MI | 10.9 TWh |
#12 | Warren County | Front Royal, VA | 10.3 TWh |
#13 | Lackawanna Energy Center | Jessup, PA | 10.1 TWh |
#14 | Fort Myers | Ft. Myers, FL | 9.9 TWh |
#15 | Forney Energy Center | Forney, TX | 9.8 TWh |
#16 | Hanging Rock Energy Facility | Ironton, OH | 9.6 TWh |
#17 | York Energy Center | Delta, PA | 9.5 TWh |
#18 | Sherwood H Smith Jr Energy Complex | Hamlet, NC | 9.2 TWh |
#19 | Sanford | DeBary, FL | 8.7 TWh |
#20 | South Field Energy | Wellsville, OH | 8.7 TWh |
#21 | Nine Mile Point | Westwego, LA | 8.6 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding H Allen Franklin Combined Cycle.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bartletts Ferry | Salem, AL | 397.0 GWh | 3.8 mi |
Camp Solar Plant | Woodbury, GA | 3.2 GWh | 40.5 mi |
Fort Benning Solar Facility | Fort Benning, GA | 51.2 GWh | 19.2 mi |
Goat Rock | Smiths, AL | 99.4 GWh | 1.1 mi |
Greenville | Greenville, GA | 1.4 GWh | 37.6 mi |
Harris Shiloh | Shiloh, GA | 4.3 GWh | 26.7 mi |
Kimberly-Clark Solar | LaGrange, GA | 2.7 GWh | 27.3 mi |
LaFayette Solar Farm | LaFayette, AL | 166.2 GWh | 25.1 mi |
Mead Coated Board | Mahrt, AL | 747.0 GWh | 30.1 mi |
Meriwether Jackson | Machester, GA | 5.9 GWh | 32.3 mi |
Muscogee Public Works | Columbus, GA | 2.9 GWh | 15.9 mi |
North Highlands | Columbus, GA | 98.0 GWh | 9.5 mi |
Oliver Dam | Columbus, GA | 134.4 GWh | 8.5 mi |
Richland | Columbus, GA | 1.5 GWh | 43.9 mi |
Talbot County Energy | Box Springs, GA | 521.8 GWh | 23.7 mi |
Taylor | Mauk, GA | 31.7 GWh | 42.8 mi |
Troup RC50 | Pine Mountain, GA | 4.6 GWh | 24.6 mi |
Troup RC50 II | Pine Mountain, GA | 2.9 GWh | 23.3 mi |
Walton Discover Power Facility | Smiths, AL | 195.0 MWh | 5.7 mi |
West Point (GA) | West Point, GA | 198.7 GWh | 22.1 mi |