Gulf Coast Solar Center III
E Fence Road, Bellview, FL 32526Plant Summary Information
Gulf Coast Solar Center III is ranked #119 out of 172 solar farms in Florida in terms of total annual net electricity generation.
Gulf Coast Solar Center III generated 25.0 GWh during the 3-month period between July 2024 to October 2024.
Plant Name | Gulf Coast Solar Center III |
---|---|
Utility Name | Arevon Energy, Inc. |
Location | Escambia County, FL |
Initial Operation Date | November 2017 |
Last Update | Oct 2024 |
Annual Generation | 91.6 GWh |
Annual Consumption | 324.2 k MMBtu |
Ranked #3,295 out of 11,866 Power Plants Nationwide | |
Ranked #651 out of 5,672 Solar Power Plants Nationwide | |
Ranked #194 out of 279 Florida Power Plants | |
Ranked #119 out of 172 Florida Solar Power Plants | |
Fuel Types | Solar |
Previous Operators |
Coronal Development Services (2014 to 2015) Gulf Coast Solar Center III (CA) (2016 to 2019) CD Arevon USA, Inc. (2020 to 2021) Arevon Energy, Inc. (2022 to 2023) |
Map of Gulf Coast Solar Center III
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Gulf Coast Solar Center III.
Monthly Net Generation for Gulf Coast Solar Center III
Gulf Coast Solar Center III Details
Summary Information | |
---|---|
Plant Name | Gulf Coast Solar Center III (59691) |
Plant Address | E Fence Road, Bellview, FL 32526 |
Utility | Arevon Energy, Inc. (61230) |
Latitude, Longitude | 30.47035, -87.33519 |
Generation Dates on File | Nov 2017 to Oct 2024 |
Initial Operation Date | November 2017 |
Annual Generation | 91.6 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Florida Power & Light Co (6452) FL |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator GCSC3 Details Operating November 2017
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 50 MW |
Summer Capacity | 50 MW |
Winter Capacity | 50 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 220 |
Tilt Angle | 20 |
DC Net Capacity | 68.7 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Gulf Coast Solar Center III Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#641 | Buckleberry Solar | Grifton, NC | 95.7 GWh |
#642 | Platteview Solar LLC | Ashland, NE | 95.0 GWh |
#643 | Live Oak Solar, LLC | Metter, GA | 94.6 GWh |
#644 | Red Rock | Red Rock, AZ | 93.5 GWh |
#645 | CM48 | Boulder City, NV | 93.3 GWh |
#646 | Beacon Solar Plant Site 5 | Cantil, CA | 92.9 GWh |
#647 | RE Gaskell West 2 LLC | Rosamond, CA | 91.8 GWh |
#648 | ID Solar | Kuna, ID | 91.7 GWh |
#649 | Waipio Solar | Waipio, HI | 91.7 GWh |
#650 | Hattiesburg Solar Farm | Hattiesburg, MS | 91.6 GWh |
#652 | Troy Solar | Troy, IN | 91.3 GWh |
#653 | Nevada Solar One | Boulder City, NV | 92.9 GWh |
#654 | Big Juniper Solar | TBD, FL | 90.8 GWh |
#655 | Beaver Dam Solar | Dodge, WI | 90.7 GWh |
#656 | Crawfish River | Jefferson, WI | 90.5 GWh |
#657 | Prineville Solar Energy LLC | Prineville, OR | 90.4 GWh |
#658 | Sanford Solar | Sanford, ME | 90.3 GWh |
#659 | Peace Creek Solar | Bartow, FL | 90.3 GWh |
#660 | Cassville Solar | Cassville, WI | 90.0 GWh |
#661 | Lake Hancock Solar | Bartow, FL | 89.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Gulf Coast Solar Center III.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Big Juniper Solar | TBD, FL | 90.8 GWh | 27 mi |
Blackwater River Solar Energy Center | Milton, FL | 141.1 GWh | 26.6 mi |
Canoe | Holt, FL | 131.3 GWh | 36 mi |
Cotton Creek Solar Energy Center | McDavid, FL | 142.4 GWh | 25.7 mi |
First City Solar Energy Center | McDavid, FL | 123.6 GWh | 31.1 mi |
Georgia-Pacific Brewton Mill | Brewton, AL | 490.5 GWh | 44 mi |
Gulf Clean Energy Center | Pensacola, FL | 2.7 TWh | 9.3 mi |
Gulf Coast Solar Center I | Valparaiso, FL | 57.3 GWh | 48.7 mi |
Gulf Coast Solar Center II | Navarre, FL | 78.4 GWh | 26.3 mi |
Hog Bayou Energy Center | Mobile, AL | 936.2 GWh | 47 mi |
International Paper Pensacola | Cantonment, FL | 336.2 GWh | 8.7 mi |
Kimberly Clark Mobile - CHP Plant | Mobile, AL | 365.5 GWh | 46.3 mi |
Pea Ridge | Pace, FL | 88.4 GWh | 14.6 mi |
Pensacola Florida Plant | Cantonment, FL | 431.0 GWh | 10 mi |
Perdido | Pensacola, FL | 17.4 GWh | 7.6 mi |
Santa Rosa Energy Center | Pace, FL | 1.5 TWh | 14.7 mi |
Sparkleberry | Molino, FL | 119.9 GWh | 21.1 mi |
Standby Generation Plant | Pensacola, FL | 9.0 MWh | 5.9 mi |
Theodore Cogen Facility | Theodore, AL | 1.6 TWh | 47.4 mi |
W&T Onshore Treating Facility (OTF) | Theodore, AL | 47.6 GWh | 50.5 mi |