11160 Seneca Lane, Byesville, OH 43723Plant Summary Information
Guernsey Power Station is ranked #49 out of 11,852 power plants nationwide in terms of total annual net electricity generation.
Guernsey Power Station is comprised of 3 generators and generated 3.4 TWh during the 3-month period between June 2024 to September 2024.
Plant Name | Guernsey Power Station |
---|---|
Utility Name | Guernsey Power Station LLC |
Location | Guernsey County, OH |
Initial Operation Date | February 2023 |
Last Update | Sep 2024 |
Annual Generation | 11.6 TWh |
Annual Consumption | 82.4 M MMBtu |
Ranked #49 out of 11,852 Power Plants Nationwide | |
Ranked #8 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #2 out of 183 Ohio Power Plants | |
Ranked #1 out of 54 Ohio Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Guernsey Power Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Guernsey Power Station.
Monthly Net Generation for Guernsey Power Station
Guernsey Power Station Details
Summary Information | |
---|---|
Plant Name | Guernsey Power Station (62949) |
Plant Address | 11160 Seneca Lane, Byesville, OH 43723 |
Utility | Guernsey Power Station LLC (62806) |
Latitude, Longitude | 39.9364, -81.5354 |
Generation Dates on File | Feb 2023 to Sep 2024 |
Initial Operation Date | February 2023 |
Annual Generation | 11.6 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Town of Byesville, Ohio |
Ash Impoundment | No |
Transmission / Distribution Owner | Ohio Power Co (14006) OH |
Grid Voltage | 765.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | ROCKIES EXPRESS PIPELINE LLC |
Natural Gas Storage | No |
Generator GPS1 Details Operating February 2023
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | Yes |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO Location Designation For Reporting Wholesale Sales Data | PJM |
Nameplate Capacity | 685 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 594 MW |
Winter Capacity | 625 MW |
Minimum Load | 275 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | February 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator GPS2 Details Operating February 2023
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | Yes |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 685 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 594 MW |
Winter Capacity | 625 MW |
Minimum Load | 275 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | February 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator GPS3 Details Operating April 2023
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | Yes |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 685 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 594 MW |
Winter Capacity | 625 MW |
Minimum Load | 275 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Guernsey Power Station Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1 | West County Energy Center | Loxahatchee, FL | 21.0 TWh |
#2 | Jack McDonough | Smyrna, GA | 18.1 TWh |
#3 | Barry | Bucks, AL | 13.0 TWh |
#4 | Crystal River | Crystal River, FL | 16.3 TWh |
#5 | H Allen Franklin Combined Cycle | Smiths, AL | 12.1 TWh |
#6 | Greensville County Power Station | Emporia, VA | 12.0 TWh |
#7 | Hines Energy Complex | Bartow, FL | 11.6 TWh |
#9 | Okeechobee Clean Energy Center | Okeechobee, FL | 11.3 TWh |
#10 | Union Power Station | El Dorado, AR | 11.1 TWh |
#11 | Midland Cogeneration Venture | Midland, MI | 10.8 TWh |
#12 | Lackawanna Energy Center | Jessup, PA | 10.3 TWh |
#13 | Forney Energy Center | Forney, TX | 9.9 TWh |
#14 | Hanging Rock Energy Facility | Ironton, OH | 9.6 TWh |
#15 | Warren County | Front Royal, VA | 9.3 TWh |
#16 | York Energy Center | Delta, PA | 9.0 TWh |
#17 | Fort Myers | Ft. Myers, FL | 9.0 TWh |
#18 | Sherwood H Smith Jr Energy Complex | Hamlet, NC | 8.8 TWh |
#19 | Lawrenceburg Power, LLC | Lawrenceburg, IN | 8.7 TWh |
#20 | Nine Mile Point | Westwego, LA | 8.7 TWh |
#21 | Sanford | DeBary, FL | 8.6 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Guernsey Power Station.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Anadarko | Woodsfield, OH | 16.0 MWh | 25.5 mi |
Axiall Natrium Plant | New Martinsville, WV | 723.7 GWh | 38.4 mi |
Belleville Dam | Belleville, WV | 272.2 GWh | 57.5 mi |
Cardinal | Brillant, OH | 9.8 TWh | 51.7 mi |
Carroll County Energy | Carrollton, OH | 5.3 TWh | 52.5 mi |
Denison Solar Array | Granville, OH | 2.3 GWh | 52.9 mi |
DG AMP Solar Brewster | Brewster, OH | 2.2 GWh | 53 mi |
Dover | Dover, OH | 78.0 GWh | 40.5 mi |
Dover Peaking | Dover, OH | 134.0 MWh | 41.9 mi |
Dresden Energy Facility | Dresden, OH | 4.5 TWh | 28.2 mi |
Long Ridge Energy Generation | Hannibal, OH | 3.6 TWh | 40 mi |
Mitchell (WV) | Captina, WV | 3.3 TWh | 38.9 mi |
New Martinsville Hannibal Hydro | New Martinsville, WV | 173.4 GWh | 40.2 mi |
Pleasants Energy LLC | St Mary's, WV | 2.4 TWh | 42.7 mi |
Pleasants Power Station | Willow Island, WV | 1.7 TWh | 41.4 mi |
Progress Drive Generation Station | Shelby, OH | 38.0 MWh | 61.3 mi |
Suburban Landfill Gas Recovery | Glenford, OH | 30.5 GWh | 37.6 mi |
Washington Energy Facility | Beverly, OH | 5.1 TWh | 25.4 mi |
Waterford Power, LLC | Waterford, OH | 6.6 TWh | 29.5 mi |
Willow Island Hydroelectric Plant | Willow Island, WV | 220.4 GWh | 41.6 mi |