Gopher Creek Wind Farm
TBD, Fluvanna, TX 79517Plant Summary Information
Gopher Creek Wind Farm is ranked #72 out of 218 wind farms in Texas in terms of total annual net electricity generation.
Gopher Creek Wind Farm generated 130.6 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Gopher Creek Wind Farm |
---|---|
Utility Name | Fluvanna Wind Energy 2 LLC |
Location | Borden County, TX |
Initial Operation Date | September 2019 |
Last Update | Sep 2024 |
Annual Generation | 613.9 GWh |
Annual Consumption | 2.2 M MMBtu |
Ranked #1,069 out of 11,852 Power Plants Nationwide | |
Ranked #238 out of 1,345 Wind Power Plants Nationwide | |
Ranked #190 out of 754 Texas Power Plants | |
Ranked #72 out of 218 Texas Wind Power Plants | |
Fuel Types | Wind |
Map of Gopher Creek Wind Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Gopher Creek Wind Farm.
Monthly Net Generation for Gopher Creek Wind Farm
Gopher Creek Wind Farm Details
Summary Information | |
---|---|
Plant Name | Gopher Creek Wind Farm (61417) |
Plant Address | TBD, Fluvanna, TX 79517 |
Utility | Fluvanna Wind Energy 2 LLC (61054) |
Latitude, Longitude | 32.87507, -101.20896 |
Generation Dates on File | Sep 2019 to Sep 2024 |
Initial Operation Date | September 2019 |
Annual Generation | 613.9 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator GCWF Details Operating September 2019
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 158 MW |
Summer Capacity | 158 MW |
Winter Capacity | 158 MW |
Minimum Load | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Turbines/Hydrokinetic Buoys | 76 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 76 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V110-2.0 |
Design Wind Speed | 19 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262 |
Gopher Creek Wind Farm Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#228 | Brady II Wind Energy Center | Dickinson, ND | 634.1 GWh |
#229 | North Bend Wind Project, LLC | Highmore, SD | 633.8 GWh |
#230 | FPL Energy Illinois Wind LLC Hybrid | Shabbona, IL | 628.9 GWh |
#231 | Glacier Sands Wind Power, LLC | Mason City, IL | 627.9 GWh |
#232 | BMP Wind (TX) | Baird, TX | 626.9 GWh |
#233 | King Creek Wind Farm 2, LLC | Throckmorton, TX | 623.4 GWh |
#234 | Headwaters Wind Farm LLC | Winchester, IN | 622.9 GWh |
#235 | Frontier Windpower II | Blackwell, OK | 622.3 GWh |
#236 | Brady Wind Energy Center | Dickinson, ND | 615.5 GWh |
#237 | Route 66 Wind Plant | Panhandle, TX | 614.8 GWh |
#239 | Logans Gap Wind LLC | Comanche, TX | 613.6 GWh |
#240 | El Algodon Alto Wind Farm, LLC | Mathis, TX | 613.0 GWh |
#241 | Maple Ridge Wind Farm | Lowville, NY | 612.7 GWh |
#242 | Raymond Wind Farm, LLC | Lyford, TX | 611.8 GWh |
#243 | Boiling Springs Wind Farm | Woodward, OK | 610.5 GWh |
#244 | Coyote Wind LLC | Snyder, TX | 609.9 GWh |
#245 | Foxtail Wind, LLC | Forbes, ND | 608.9 GWh |
#246 | Bison 4 Wind Energy Center | New Salem, ND | 608.4 GWh |
#247 | South Plains Wind Phase I | Floydada, TX | 601.3 GWh |
#248 | Cedar Creek II | New Raymer, CO | 600.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Gopher Creek Wind Farm.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Brazos Wind Farm | Fluvanna, TX | 82.9 GWh | 6.2 mi |
Bull Creek Wind | O'Donnell, TX | 269.0 GWh | 21.8 mi |
Canyon Wind Project, LLC | Scurry, TX | 752.9 GWh | 20.5 mi |
Coyote Wind LLC | Snyder, TX | 609.9 GWh | 20 mi |
Dermott Wind | Snyder, TX | 889.4 GWh | 13.6 mi |
EG178 Facility | Snyder, TX | 686.9 GWh | 17.2 mi |
ENGIE Long Draw Solar LLC | Gail, TX | 528.7 GWh | 25.7 mi |
Fluvanna | Fluvanna, TX | 525.2 GWh | 5.5 mi |
Juno Solar Project | Lamesa, TX | 793.4 GWh | 12.7 mi |
Lumina II Solar Project | Snyder, TX | 553.5 GWh | 26.8 mi |
Lumina Solar Project | Snyder, TX | 573.9 GWh | 13.2 mi |
Mesquite Creek Wind | Lamesa, TX | 356.6 GWh | 33.2 mi |
Post Wind Farm LP | Fluvanna, TX | 311.7 GWh | 3.5 mi |
Scurry County Wind II | Snyder, TX | 201.1 GWh | 26.5 mi |
Scurry County Wind LP | Snyder, TX | 233.6 GWh | 16.4 mi |
Stephens Ranch Wind Energy LLC | O'Donnell, TX | 1.1 TWh | 25.7 mi |
Tahoka Wind | Tahoka, TX | 1.1 TWh | 33.2 mi |
Texas Solar Nova 1 | Spur, TX | 666.4 GWh | 33.5 mi |
Texas Solar Nova 2 | Spur, TX | 375.9 GWh | 33.5 mi |
WAL1272 | Snyder, TX | 287.0 MWh | 21.2 mi |