GMP Solar - Williston
479 Mountain View Road, Williston, VT 5495Plant Summary Information
GMP Solar - Williston is ranked #45 out of 111 power plants in Vermont in terms of total annual net electricity generation.
GMP Solar - Williston generated 2.2 GWh during the 3-month period between July 2024 to October 2024.
Plant Name | GMP Solar - Williston |
---|---|
Utility Name | Green Mountain Power Corp |
Location | Chittenden County, VT |
Initial Operation Date | November 2016 |
Last Update | Oct 2024 |
Annual Generation | 6.9 GWh |
Annual Consumption | 24.9 k MMBtu |
Ranked #7,012 out of 11,866 Power Plants Nationwide | |
Ranked #2,353 out of 5,672 Solar Power Plants Nationwide | |
Ranked #45 out of 111 Vermont Power Plants | |
Ranked #9 out of 50 Vermont Solar Power Plants | |
Fuel Types | Solar |
Map of GMP Solar - Williston
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for GMP Solar - Williston.
Monthly Net Generation for GMP Solar - Williston
GMP Solar - Williston Details
Summary Information | |
---|---|
Plant Name | GMP Solar - Williston (60875) |
Plant Address | 479 Mountain View Road, Williston, VT 5495 |
Utility | Green Mountain Power Corp (7601) |
Latitude, Longitude | 44.46549, -73.10324 |
Generation Dates on File | Nov 2016 to Oct 2024 |
Initial Operation Date | November 2016 |
Annual Generation | 6.9 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | QF16-768 |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | NPCC |
Balancing Authority | ISO New England Inc. (ISNE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Green Mountain Power Corp (7601) VT |
Grid Voltage | 12.47 kV |
Energy Storage | No |
Generator GMPSW Details Operating November 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 4.7 MW |
Summer Capacity | 4.7 MW |
Winter Capacity | 4.7 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | November 2016 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 6.8 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
GMP Solar - Williston Plant Owners
Owner Name | Address | Ownership |
---|---|---|
GMP VT Solar LLC | 163 Acorn Lane Colchester, Colchester, VT 5446 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2343 | Vuelta Solar | East Brookfield, MA | 6.9 GWh |
#2344 | Townline Community Solar | Batavia, NY | 6.9 GWh |
#2345 | American Goldfinch SCS ACY2 NJ, LLC | Burlington, NJ | 6.9 GWh |
#2346 | PopeSun CSG, LLC | Starbuck, MN | 6.9 GWh |
#2347 | Solar Photovoltaic Project #42 | Tulare, CA | 6.9 GWh |
#2348 | Fiddler's Canyon #1 | Cedar City, UT | 6.9 GWh |
#2349 | CSU Long Beach Lots 7 & 14 | Long Beach, CA | 6.9 GWh |
#2350 | 71 Charlotte Furnace Rd Hybrid(CSG) | Wareham, MA | 6.8 GWh |
#2351 | Blackjack Solar | King City, CA | 6.9 GWh |
#2352 | Sweden 1 | Sweden, NY | 6.9 GWh |
#2354 | Ravenbrook | Carver, MA | 6.9 GWh |
#2355 | Hemings Solar | Warsaw, VA | 6.9 GWh |
#2356 | True North | Salisbury, MA | 6.9 GWh |
#2357 | Pine Tree Solar Project | Owenyo, CA | 6.9 GWh |
#2358 | Upper Blackstone (MA) Treasure Valley | Rutland, MA | 6.9 GWh |
#2359 | Montrose Solar | Montrose, MN | 6.9 GWh |
#2360 | South Goshen Community Solar | Goshen, NY | 6.7 GWh |
#2361 | Elizabeth Mines Solar 1 | So. Strafford, VT | 6.9 GWh |
#2362 | Athens AT01 | Athens, ME | 6.9 GWh |
#2363 | 3232 Batavia Solar | Batavia, NY | 6.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding GMP Solar - Williston.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
158th Fighter Wing Solar Farm | South Burlington, VT | 1.3 GWh | 2.6 mi |
Burlington GT | Burlington, VT | 472.0 MWh | 6 mi |
Chace Mill Winooski One | Winooski, VT | 36.3 GWh | 4.5 mi |
Charlotte Solar LLC VT | Charlotte, VT | 2.8 GWh | 11 mi |
Chittenden County Solar Partners | South Burlington, VT | 2.8 GWh | 2.9 mi |
Claire Solar Farm | South Burlington, VT | 3.0 GWh | 3.8 mi |
Clark Falls | Milton, VT | 19.8 GWh | 11.8 mi |
Colchester 16 | Colchester, VT | 4.0 MWh | 3.7 mi |
Essex Junction 19 | Essex Junction, VT | 45.6 GWh | 1.3 mi |
Georgia Mountain Community Wind Farm | Milton, VT | 26.1 GWh | 13.7 mi |
GMP Solar - Richmond | Richmond, VT | 2.9 GWh | 5.4 mi |
GMP Solar/Storage-Essex Hybrid | Essex, VT | 7.7 GWh | 13 mi |
GMP Solar/Storage-Milton Hybrid | Milton, VT | 8.7 GWh | 5.1 mi |
Gorge 18 | South Burlington, VT | 20.5 GWh | 3.7 mi |
J C McNeil | Burlington, VT | 179.9 GWh | 5.5 mi |
Limerick Road Solar Farm | Shelburne, VT | 3.0 GWh | 9.7 mi |
Milton | Milton, VT | 48.3 GWh | 12.2 mi |
Peterson | Milton, VT | 36.3 GWh | 12.3 mi |
VEC Magee Hill Solar | Hinesburgh, VT | 1.6 GWh | 7 mi |
Whitcomb Solar Farm | Essex Junction, VT | 2.7 GWh | 2.2 mi |