Plant Summary Information

Girard is ranked #43 out of 58 natural gas power plants in Kansas in terms of total annual net electricity generation.

Girard is comprised of 4 generators and generated 44.6 MWh during the 3-month period between September 2023 to December 2023.

Plant NameGirard
Utility NameCity of Girard - (KS)
LocationCrawford County, KS
Initial Operation DateSeptember 1955
Last Update Dec 2023
Annual Generation 185.0 MWh
Annual Consumption 2.5 k MMBtu
Ranked #11,323 out of 11,852 Power Plants Nationwide
Ranked #2,142 out of 2,254 Natural Gas Power Plants Nationwide
Ranked #114 out of 152 Kansas Power Plants
Ranked #43 out of 58 Kansas Natural Gas Power Plants
Fuel Types Natural Gas : 56.0% Distillate Fuel Oil : 44.0%

Map of Girard

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Girard.

Create Your Account Today

Monthly Net Generation for Girard

Girard Details

Summary Information
Plant NameGirard (1279)
Plant Address307 East Buffalo, Girard, KS 66743
UtilityCity of Girard - (KS) (7257)
Latitude, Longitude37.50771, -94.83932
Generation Dates on FileJan 2002 to Dec 2023
Initial Operation DateSeptember 1955
Annual Generation 185.0 MWh
Fuel Types Natural Gas : 56.0% Distillate Fuel Oil : 44.0%
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionMRO
Balancing AuthoritySouthwest Power Pool (SWPP)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water SourceMunicipality
Ash Impoundment No
Transmission / Distribution OwnerWestar Energy Inc (22500) KS
Grid Voltage 69.00 kV
Energy StorageNo
 
Natural Gas Information
Pipeline Name SOUTHERN STAR CENTRAL GAS PIPELINE
Natural Gas StorageNo

Generator 1 Details Operating September 1955

TechnologyNatural Gas Internal Combustion Engine
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationSPP
RTO ISO Location Designation For Reporting Wholesale Sales DataSPP
Nameplate Capacity1.4 MW
Nameplate Power Factor0.8
Summer Capacity1.1 MW
Winter Capacity1.1 MW
Minimum Load1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateSeptember 1955
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceNG / DFO

Generator 4 Details Operating September 1962

TechnologyNatural Gas Internal Combustion Engine
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationSPP
RTO ISO Location Designation For Reporting Wholesale Sales DataSPP
Nameplate Capacity2.2 MW
Nameplate Power Factor0.8
Summer Capacity1.8 MW
Winter Capacity1.8 MW
Minimum Load1.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateSeptember 1962
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceNG / DFO

Generator 7 Details Operating April 1997

TechnologyNatural Gas Internal Combustion Engine
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationSPP
RTO ISO Location Designation For Reporting Wholesale Sales DataSPP
Nameplate Capacity3.7 MW
Nameplate Power Factor0.8
Summer Capacity3.4 MW
Winter Capacity3.4 MW
Minimum Load3.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 1997
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceNG / DFO

Generator 6 Details Operating May 1997

TechnologyNatural Gas Internal Combustion Engine
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationSPP
RTO ISO Location Designation For Reporting Wholesale Sales DataSPP
Nameplate Capacity3.5 MW
Nameplate Power Factor0.8
Summer Capacity3.2 MW
Winter Capacity3.3 MW
Minimum Load3 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 1997
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceNG / DFO

Girard Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Natural Gas.

RankPlant NamePlant LocationAnnual Generation
#2132BellevilleBelleville, KS178.0 MWh
#2133Northeast (WA)Spokane, WA112.0 MWh
#2134Brookville Smart Bus Depot MicrogridSilver Spring, MD2.2 GWh
#2135Cherry StreetHudson, MA417.0 MWh
#2136Preston (MN)Preston, MN130.0 MWh
#2137LitchfieldLitchfield, MN185.0 MWh
#2138OTHERBenEKDallasDallas, TX107.0 MWh
#2139Waverly Municipal Electric North PlantWaverly, IA224.0 MWh
#2140Falls CityFalls City, NE161.0 MWh
#2141AtlanticAtlantic, IA115.0 MWh
#2143BeloitBeloit, KS114.0 MWh
#2144HallamHallam, NE2.4 GWh
#2145Whitemarsh Central Utility PlantLafayette Hill, PA97.0 MWh
#2146HEB00776Katy, TX96.0 MWh
#2147GenConn Devon LLCMilford, CT2.3 GWh
#2148WAL3226Katy, TX93.0 MWh
#2149Regional Wastewater Control FacilityStockton, CA4.1 GWh
#2150L L WilkinsClarksdale, MS90.0 MWh
#2151MeadeMeade, KS105.0 MWh
#2152CCSU Co-Gen-STBY GenNew Britain, CT88.2 MWh

Nearby Power Plants

Below are closest 20 power plants surrounding Girard.

Plant NamePlant LocationAnnual GenerationDistance
CarthageCarthage, MO1.7 GWh37.5 mi
Chanute 2Chanute, KS79.2 GWh36.3 mi
Chanute 3Chanute, KS694.0 MWh35.7 mi
CML&P Generating Facility No. 2Coffeyville, KS93.2 GWh50 mi
CoffeyvilleCoffeyville, KS10.9 GWh53.5 mi
El Dorado Springs Solar FarmEl Dorado Springs, MO4.4 GWh51.8 mi
Empire Energy CenterSarcoxie, MO239.0 GWh47.8 mi
ErieErie, KS7.0 MWh22.2 mi
Erie Energy CenterErie, KS1.9 GWh22.3 mi
IolaIola, KS909.0 MWh43 mi
Jayhawk Wind Energy CenterHepler, KS685.5 GWh17.1 mi
Kings Point Wind Energy CenterGolden City, MO585.4 GWh46.2 mi
Neosho Ridge Wind Energy CenterGalesburg, KS1.3 TWh29.5 mi
NevadaNevada, MO1.1 GWh36 mi
North Fork Ridge Wind Energy CenterMindenmines, MO544.8 GWh19.8 mi
Oak Grove Power ProducersArcadia, KS20.2 GWh13.7 mi
Prairie Queen Wind FarmMoran, KS638.6 GWh38.8 mi
Prosperity Solar Farm CSGJoplin, MO4.0 GWh34.5 mi
RivertonRiverton, KS1.2 TWh31 mi
State Line Combined CycleJoplin, MO2.6 TWh32.9 mi