Fulton (MO)
2101 Power Lane, Fulton, MO 65251Plant Summary Information
Fulton (MO) is ranked #34 out of 37 natural gas power plants in Missouri in terms of total annual net electricity generation.
Fulton (MO) is comprised of 3 generators and generated 388.9 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Fulton (MO) |
---|---|
Utility Name | City of Fulton - (MO) |
Location | Callaway County, MO |
Initial Operation Date | September 1966 |
Last Update | Dec 2022 |
Annual Generation | 1.2 GWh |
Annual Consumption | 23.9 k MMBtu |
Ranked #10,219 out of 11,249 Power Plants Nationwide | |
Ranked #1,847 out of 2,188 Natural Gas Power Plants Nationwide | |
Ranked #97 out of 116 Missouri Power Plants | |
Ranked #34 out of 37 Missouri Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.9% |
Map of Fulton (MO)
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fulton (MO).
Monthly Net Generation for Fulton (MO)
Fulton (MO) Details
Summary Information | |
---|---|
Plant Name | Fulton (MO) (2126) |
Plant Address | 2101 Power Lane Fulton, MO 65251 |
Utility | City of Fulton - (MO) (6839) |
Latitude, Longitude | 38.8681, -91.94778 |
Generation Dates on File | Jan 2001 to Dec 2022 |
Initial Operation Date | September 1966 |
Annual Generation | 1.2 GWh |
Fuel Types | Natural Gas : 99.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Associated Electric Cooperative, Inc. (AECI) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality / Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Fulton - (MO) (6839) MO |
Grid Voltage | 13.80 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | Other - See pipeline notes. |
Pipeline Notes | Panhandle Eastern Pipeline Company |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator IC1 Details Operating September 1966
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 4.1 MW |
Winter Capacity | 4.5 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1966 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 4 MW |
Net Winter Capacity With Natural Gas | 4.4 MW |
Net Summer Capacity With Oil | 4 MW |
Net Winter Capacity With Oil | 4.4 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Generator GT4 Details Operating August 1972
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 21.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 15 MW |
Winter Capacity | 19.6 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1972 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | DFO / NG |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 15 MW |
Net Winter Capacity With Natural Gas | 19.6 MW |
Net Summer Capacity With Oil | 15 MW |
Net Winter Capacity With Oil | 19.6 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Generator IC3 Details Operating May 1975
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 7 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 6.2 MW |
Winter Capacity | 6.8 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 1975 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 6 MW |
Net Winter Capacity With Natural Gas | 6.2 MW |
Net Summer Capacity With Oil | 6 MW |
Net Winter Capacity With Oil | 6.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | No |
Fulton (MO) Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1837 | Cleveland Thermal | Cleveland, OH | 1.5 GWh |
#1838 | Wygen 2 | Gillette, WY | 784.6 GWh |
#1839 | Sinclair Oil Refinery | Sinclair, WY | 1.5 GWh |
#1840 | Amherst College Co Gen | Amherst, MA | 1.4 GWh |
#1841 | GenConn Middletown LLC | Middletown, CT | 4.9 GWh |
#1842 | Wilmarth | Mankato, MN | 94.0 GWh |
#1843 | Hillburn | Hillburn, NY | 1.4 GWh |
#1844 | Tom G Smith | Lake Worth, FL | 1.5 GWh |
#1845 | McClure | Modesto, CA | 2.3 GWh |
#1846 | Pratt | Pratt, KS | 1.3 GWh |
#1848 | Rariton OMP | Raritan, NJ | 2.7 GWh |
#1849 | Water Street Station | Bay City, MI | 1.3 GWh |
#1850 | Henry Station | Bay City, MI | 1.3 GWh |
#1851 | Carthage | Carthage, MO | 2.1 GWh |
#1852 | Osceola Generating Station (FL) | St. Cloud, FL | 1.2 GWh |
#1853 | MacArthur Waste to Energy Facility | Ronkonkoma, NY | 57.2 GWh |
#1854 | Northeast (WA) | Spokane, WA | 1.2 GWh |
#1855 | Palm Beach Renewable Energy Facility 1 | West Palm Beach, FL | 336.3 GWh |
#1856 | Falling Spring | Chambersburg, PA | 1.3 GWh |
#1857 | Custer Energy Center | Manitowoc, WI | 1.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fulton (MO).
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Ameresco Jefferson City | Jefferson City, MO | 26.2 GWh | 22.4 mi |
Audrain Generating Station | Vandalia, MO | 243.6 GWh | 37.6 mi |
Callaway | Fulton, MO | 9.9 TWh | 11.8 mi |
Clarence Cannon | Monroe City, MO | 38.6 GWh | 48.2 mi |
Columbia (MO) | Columbia, MO | 19.7 GWh | 20.9 mi |
Columbia Energy Center | Columbia, MO | 47.7 GWh | 19.9 mi |
Fairgrounds | Jefferson City, MO | 1.9 GWh | 24 mi |
Mexico | Mexico, MO | 2.2 GWh | 20.3 mi |
MJMEUC Generating Station #1 | Laddonia, MO | 109.2 GWh | 31.2 mi |
Moberly | Moberly, MO | 165.6 MWh | 48 mi |
Montgomery County Community Solar Center | New Florence, MO | 9.8 GWh | 28.3 mi |
Moreau | Moreau, MO | 2.7 GWh | 23.1 mi |
MU Combined Heat and Power Plant | Columbia, MO | 198.9 GWh | 21.4 mi |
Osage Dam | Eldon, MO | 629.0 GWh | 58.6 mi |
Peno Creek | Bowling Green, MO | 135.2 GWh | 51 mi |
Shelbina Power #1 | Shelbina, MO | 28.2 MWh | 57.4 mi |
Shelbina Power #2 | Shelbina, MO | 106.3 MWh | 57.4 mi |
Shelbina Power #3 | Shelbina, MO | 10.2 MWh | 57.6 mi |
Thomas Hill | Clifton Hill, MO | 6.3 TWh | 60 mi |
Truman Solar | Colombia, MO | 24.6 GWh | 17 mi |