Fresno Bullard High School Hybrid

5445 N Palm Avenue, Fresno, CA 93704

Plant Summary Information

Fresno Bullard High School Hybrid is ranked #618 out of 799 solar farms in California in terms of total annual net electricity generation.

Fresno Bullard High School Hybrid generated 356.0 MWh during the 3-month period between September 2023 to December 2023.

Plant NameFresno Bullard High School Hybrid
Utility NameForefront Power, LLC
LocationFresno County, CA
Initial Operation DateMarch 2020
Last Update Dec 2023
Annual Generation 2.2 GWh
Annual Consumption 7.7 k MMBtu
Ranked #9,733 out of 11,852 Power Plants Nationwide
Ranked #4,463 out of 5,655 Solar Power Plants Nationwide
Ranked #1,348 out of 1,570 California Power Plants
Ranked #618 out of 799 California Solar Power Plants
Fuel Types Solar

Map of Fresno Bullard High School Hybrid

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fresno Bullard High School Hybrid.

Create Your Account Today

Monthly Net Generation for Fresno Bullard High School Hybrid

Fresno Bullard High School Hybrid Details

Summary Information
Plant NameFresno Bullard High School Hybrid (63420)
Plant Address5445 N Palm Avenue, Fresno, CA 93704
UtilityForefront Power, LLC (62856)
Latitude, Longitude36.81865, -119.81041
Generation Dates on FileMar 2020 to Dec 2023
Initial Operation DateMarch 2020
Annual Generation 2.2 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number22-385-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerPacific Gas & Electric Co. (14328) CA
Grid Voltage 21.00 kV
Energy StorageYes

Generator 903 Details Operating March 2020

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity1.2 MW
Summer Capacity1.2 MW
Winter Capacity1.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMarch 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo
Solar Details
Single Axis TrackingNo
Fixed TiltYes
East West Fixed TiltNo
Azimuth Angle180
Tilt Angle7
DC Net Capacity1.4 MW
Crystalline SiliconYes
Net Metering AgreementYes
Net Metering DC Capacity1.4 MW
Virtual Net Metering AgreementNo

Generator BA903 Details Operating March 2020

TechnologyBatteries
Prime MoverBattery
OwnershipSingle Owner
Nameplate Capacity0.4 MW
Summer Capacity0.4 MW
Winter Capacity0.4 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMarch 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceElectricity used for energy storage
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo
Energy Storage Details
Nameplate Energy Capacity MWH0.4
Maximum Charge Rate0.4 MW
Maximum Discharge Rate0.4 MW
Storage TechnologyLIB
Nameplate Reactive Power Rating0.2
Storage Enclosure TypeCS
System Peak ShavingP
Excess Wind And Solar GenerationYes
Ac CoupledYes
Direct Support Of Another UnitYes
Direct Support Plant Id63420
Direct Support Gen Id903
Support T D AssetNo

Fresno Bullard High School Hybrid Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#4453USS Water City Solar LLC CSGWaterville, MN2.2 GWh
#4454Pipestone City Solar LLC CSGPipestone, MN2.2 GWh
#4455Merrimac SolarMerrimac, MA2.2 GWh
#4456Hyacinth Solar, LLCNorthfield, MN2.2 GWh
#4457Greenwood Solar FarmAvoca, MI2.2 GWh
#4458West Boylston Community Shared SolarWest Boylston, MA2.2 GWh
#4459Marigold Community Solar Garden, LLCWaterville, MN2.2 GWh
#4460USS King 2 CSGWaconia, MN2.2 GWh
#4461Novel Stavem Solar LLC CSGGlenwood, MN2.2 GWh
#4462ER Bison Solar CSGLewisburg, PA2.2 GWh
#4464Novel Sunnyfield Farms Solar LLC CSGMazeppa, MN2.2 GWh
#4465FELPS 3 - Floresville SouthFloresville, TX2.2 GWh
#4466FELPS 4 - Floresville SouthFloresville, TX2.2 GWh
#4467FELPS 5- Floresville SouthFloresville, TX2.2 GWh
#4468Rancho Cordova Medical OfficesRancho Cordova, CA2.2 GWh
#4469Atlantic Coast Freezers Solar FacilityVineland, NJ2.2 GWh
#4470Homer Street WestOlean, NY2.2 GWh
#4471Barre II Solar ProjectBarre, MA2.2 GWh
#4472Dubois Solar (Hybrid)Pine Bush, NY2.1 GWh
#4473AC PowerDelanco Township, NJ2.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Fresno Bullard High School Hybrid.

Plant NamePlant LocationAnnual GenerationDistance
Borden Solar FarmMadera, CA117.4 GWh11.8 mi
CA - Fresno County - Juvenile HallFresno, CA5.4 GWh11.8 mi
CA - Madera USD - Madera South HSMadera, CA462.0 MWh16.1 mi
Clovis East High SchoolClovis, CA1.4 GWh9.5 mi
Clovis High SchoolClovis, CA1.3 GWh7.1 mi
Clovis North High SchoolFresno, CA1.4 GWh6.4 mi
CSU Fresno Solar ProjectFresno, CA1.1 GWh3.9 mi
Fresno Hoover High School HybridFresno, CA2.1 GWh2.2 mi
Fresno Sunnyside High School HybridFresno, CA2.5 GWh7.8 mi
Friant Hydro FacilityFriant, CA106.2 GWh13.7 mi
La Joya Del SolFresno, CA89.3 MWh9.7 mi
Madera Community HospitalMadera, CA1.8 GWh15.6 mi
Malaga Power LLCFresno, CA10.8 GWh9.7 mi
National RaisinFowler, CA4.8 GWh15.4 mi
OK Produce Fresno CarportFresno, CA3.1 GWh6.9 mi
Pacific Ethanol Madera Solar ArrayMadera, CA1.4 GWh11.2 mi
Rio Bravo FresnoFresno, CA145.1 GWh10.2 mi
Saint Agnes Medical CenterFresno, CA25.5 GWh2.7 mi
SCCCD - Clovis Community CollegeFresno, CA2.0 GWh6.3 mi
SCCCD - Fresno Community CollegeFresno, CA3.8 GWh3.7 mi