Fremont - Kato Rd
47400 Kato Rd, Fremont, CA 94538Plant Summary Information
Fremont - Kato Rd is ranked #598 out of 799 solar farms in California in terms of total annual net electricity generation.
Fremont - Kato Rd generated 339.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Fremont - Kato Rd |
---|---|
Utility Name | Tesla Inc. |
Location | Alameda County, CA |
Initial Operation Date | December 2016 |
Last Update | Dec 2023 |
Annual Generation | 2.3 GWh |
Annual Consumption | 8.3 k MMBtu |
Ranked #9,509 out of 11,835 Power Plants Nationwide | |
Ranked #4,277 out of 5,643 Solar Power Plants Nationwide | |
Ranked #1,325 out of 1,569 California Power Plants | |
Ranked #598 out of 799 California Solar Power Plants | |
Fuel Types | Solar |
Map of Fremont - Kato Rd
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fremont - Kato Rd.
Monthly Net Generation for Fremont - Kato Rd
Fremont - Kato Rd Details
Summary Information | |
---|---|
Plant Name | Fremont - Kato Rd (65131) |
Plant Address | 47400 Kato Rd, Fremont, CA 94538 |
Utility | Tesla Inc. (57313) |
Latitude, Longitude | 37.47919, -121.93226 |
Generation Dates on File | Jan 2021 to Dec 2023 |
Initial Operation Date | December 2016 |
Annual Generation | 2.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
Grid Voltage | 0.48 kV |
Energy Storage | No |
Generator PV1 Details Operating December 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2016 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 155 |
Tilt Angle | 8 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator PV2 Details Operating December 2017
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.9 MW |
Summer Capacity | 0.9 MW |
Winter Capacity | 0.9 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 335 |
DC Net Capacity | 1.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Fremont - Kato Rd Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#4267 | Theodore Drive Community Solar | Westminster, MA | 2.4 GWh |
#4268 | Villa Roma Rd #3 CSG | Delaware, NY | 2.4 GWh |
#4269 | Calibrant Bakersfield LLC | Bakersfield, CA | 2.4 GWh |
#4270 | CA Institute for Women | Chino, CA | 2.4 GWh |
#4271 | USS Viceroy Solar LLC CSG | Brooten, MN | 2.4 GWh |
#4272 | BWC Pocasset River | Wareham, MA | 2.3 GWh |
#4273 | Montgomery County Correctional Facility | Boyds, MD | 2.3 GWh |
#4274 | CDCR (CA) - Solano State Prison | Vacaville, CA | 2.3 GWh |
#4275 | Diamond Valley Solar Project | Winchester, CA | 2.3 GWh |
#4276 | Douglas Pike Solar, LLC | Burrillville, RI | 2.3 GWh |
#4278 | IGS AKC1 | Akron, OH | 2.3 GWh |
#4279 | Berkshire 1 | Sheffield, MA | 2.3 GWh |
#4280 | Winchendon Solar | Winchendon, MA | 2.3 GWh |
#4281 | Liberty HS Solar Project | Bakersfield, CA | 2.3 GWh |
#4282 | Schull CSG | Mapleton, MN | 2.3 GWh |
#4283 | Chambers 3 - Lewis County | Lowville, NY | 2.3 GWh |
#4284 | Santa Fe Springs Rooftop Solar BLDG M | Santa Fe Springs, CA | 2.3 GWh |
#4285 | Novel Shelly Solar LLC (CSG) | Cottonwood, MN | 2.3 GWh |
#4286 | Oneida - South | Whitestown, NY | 2.3 GWh |
#4287 | Sullivan County - Adult Care Solar | Liberty, NY | 2.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fremont - Kato Rd.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Agnews Power Plant | San Jose, CA | 35.7 GWh | 5.1 mi |
AT&T Holger | San Jose, CA | 7.2 GWh | 4.3 mi |
Beckton Dickenson - San Jose | San Jose, CA | 5.8 GWh | 6.2 mi |
CST001 McCarthy Fuel Cell | Milpitas, CA | 8.3 GWh | 5.2 mi |
Equinix Lundy Ave. Fuel Cell | San Jose, CA | 27.8 GWh | 6.7 mi |
EQX011 Duane Fuel Cell | Santa Clara, CA | 20.6 GWh | 7.1 mi |
FLEX Gibraltar | Milpitas, CA | 8.7 GWh | 4.8 mi |
Fremont CA AutoFactory | Fremont, CA | 532.0 MWh | 1.1 mi |
Gianera | Santa Clara, CA | 9.9 GWh | 5.8 mi |
Google Moffett Park Solar Project | Sunnyvale, CA | 2.7 GWh | 6.9 mi |
Intel Santa Clara | Santa Clara, CA | 7.3 GWh | 6.8 mi |
JSR000 N Mathilda Fuel Cell | Sunnyvale, CA | 8.8 GWh | 6.8 mi |
Life Technologies - Fremont | Fremont, CA | 9.9 GWh | 0.7 mi |
Los Esteros Critical Energy Center | San Jose, CA | 218.4 GWh | 3.7 mi |
Maxim | San Jose, CA | 6.6 GWh | 5.2 mi |
Mission College Blvd. Fuel Cell | Santa Clara, CA | 38.2 GWh | 6.6 mi |
SJ/SC WPCP | San Jose, CA | 81.5 GWh | 3.2 mi |
Sunnyvale City of WPCP | Sunnyvale, CA | 9.7 GWh | 6.1 mi |
Yahoo! - HQ | Sunnyvale, CA | 4.1 GWh | 6.8 mi |
Zero Waste Energy Development Co LLC | San Jose, CA | 2.3 GWh | 3.4 mi |