FreeState Crooked Post Solar I
4006 SW Auburn Rd, Topeka, KS 66610Plant Summary Information
FreeState Crooked Post Solar I is ranked #4 out of 14 solar farms in Kansas in terms of total annual net electricity generation.
FreeState Crooked Post Solar I generated 517.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | FreeState Crooked Post Solar I |
---|---|
Utility Name | Evergy Kansas Central, Inc |
Location | Shawnee County, KS |
Initial Operation Date | March 2023 |
Last Update | Dec 2023 |
Annual Generation | 3.4 GWh |
Annual Consumption | 11.7 k MMBtu |
Ranked #8,615 out of 11,835 Power Plants Nationwide | |
Ranked #3,531 out of 5,643 Solar Power Plants Nationwide | |
Ranked #86 out of 152 Kansas Power Plants | |
Ranked #4 out of 14 Kansas Solar Power Plants | |
Fuel Types | Solar |
Map of FreeState Crooked Post Solar I
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for FreeState Crooked Post Solar I.
Monthly Net Generation for FreeState Crooked Post Solar I
FreeState Crooked Post Solar I Details
Summary Information | |
---|---|
Plant Name | FreeState Crooked Post Solar I (66883) |
Plant Address | 4006 SW Auburn Rd, Topeka, KS 66610 |
Utility | Evergy Kansas Central, Inc (22500) |
Latitude, Longitude | 38.9935, -95.81564 |
Generation Dates on File | Feb 2023 to Dec 2023 |
Initial Operation Date | March 2023 |
Annual Generation | 3.4 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | FreeState Electric Coop (10019) KS |
Grid Voltage | 12.47 kV |
Energy Storage | No |
Generator FCS1 Details Operating March 2023
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2023 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 2.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
FreeState Crooked Post Solar I Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3521 | Williams-Sonoma Solar Facility | Jamesburg, NJ | 3.5 GWh |
#3522 | Syncarpha Still River, LLC CSG | Bolton, MA | 3.5 GWh |
#3523 | EBZ Solar | Shirley, MA | 3.4 GWh |
#3524 | Weld 1 Community Solar Array | Platteville, CO | 3.4 GWh |
#3525 | Interstate Solar | Gervais, OR | 3.4 GWh |
#3526 | SCH County - (2D) 98 Cheltingham Ave Sch | Schenectady, NY | 3.4 GWh |
#3527 | North Adams Landfill | North Adams, MA | 3.4 GWh |
#3528 | Nautilus Lindstrom Solar (CSG) | Lindstrom, MN | 3.4 GWh |
#3529 | Friendship I | West Friendship, MD | 3.4 GWh |
#3530 | White Horse Solar A | Greenville, SC | 3.4 GWh |
#3532 | Coronus Adelanto West 2 | Adelanto, CA | 3.4 GWh |
#3533 | Norcap South | East Windsor, CT | 3.4 GWh |
#3534 | Braley Road 2 | Freetown, MA | 3.4 GWh |
#3535 | Gas City 2 | Gas City, IN | 3.4 GWh |
#3536 | Charlemont A | Charlemont, MA | 3.4 GWh |
#3537 | Czub CSG | Schagticoke, NY | 3.4 GWh |
#3538 | East Bridgewater Solar | East Bridgewater, MA | 3.4 GWh |
#3539 | Old Court Rd Solar | Woodstock, MD | 3.4 GWh |
#3540 | Logan 1 Community Solar Array | Sterling, CO | 3.4 GWh |
#3541 | Oak Leaf Solar XXVII LLC | Greely, CO | 3.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding FreeState Crooked Post Solar I.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Americus | Emporia, KS | 2.4 GWh | 35.5 mi |
Baldwin City Plant No 1 | Baldwin City, KS | 19.0 MWh | 37.1 mi |
Baldwin City Plant No 2 | Baldwin City, KS | 145.0 MWh | 37.1 mi |
Burlingame | Burlingame, KS | 46.1 MWh | 16.5 mi |
Emporia Energy Center | Emporia, KS | 1.5 TWh | 40.2 mi |
FreeState Kiro Solar I | Silver Lake, KS | 2.2 GWh | 8.1 mi |
FreeState Stull Solar I | LeCompton, KS | 215.0 MWh | 20.8 mi |
Holton | City of Holton, KS | 1.0 GWh | 33.5 mi |
Jeffrey Energy Center | St. Mary's, KS | 5.4 TWh | 25.9 mi |
Kansas River Project | Lawrence, KS | 19.0 GWh | 31.2 mi |
Lawrence Energy Center | Lawrence, KS | 1.6 TWh | 29.4 mi |
Ottawa | Ottawa, KS | 377.0 MWh | 38.9 mi |
Reading Wind Project | Reading, KS | 687.4 GWh | 36.7 mi |
Sharpe | Waverly, KS | 1.1 GWh | 50.2 mi |
Soldier Creek Wind | Corning, KS | 1.1 TWh | 47.3 mi |
Thunderbird Generator (Tbird) | Emporia, KS | 106.0 MWh | 43.3 mi |
Waste Management Rolling Meadows LFGTE | Topeka, KS | 45.4 GWh | 13.3 mi |
Waverly Wind Farm LLC | Waverly, KS | 712.0 GWh | 50.9 mi |
West Gardner | Johnson, KS | 262.6 GWh | 46.8 mi |
Wolf Creek Generator | Burlington, KS | 106.0 MWh | 50.2 mi |