Four Corners Windfarm LLC
28821 Madison Rd., Echo, OR 97826Plant Summary Information
Four Corners Windfarm LLC is ranked #38 out of 49 wind farms in Oregon in terms of total annual net electricity generation.
Four Corners Windfarm LLC generated 4.9 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Four Corners Windfarm LLC |
---|---|
Utility Name | Echo 2 |
Location | Umatilla County, OR |
Initial Operation Date | June 2009 |
Last Update | Dec 2022 |
Annual Generation | 19.2 GWh |
Annual Consumption | 72.2 k MMBtu |
Ranked #5,010 out of 11,249 Power Plants Nationwide | |
Ranked #1,057 out of 1,329 Wind Power Plants Nationwide | |
Ranked #138 out of 254 Oregon Power Plants | |
Ranked #38 out of 49 Oregon Wind Power Plants | |
Fuel Types | Wind |
Map of Four Corners Windfarm LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Four Corners Windfarm LLC.
Monthly Net Generation for Four Corners Windfarm LLC
Four Corners Windfarm LLC Details
Summary Information | |
---|---|
Plant Name | Four Corners Windfarm LLC (56969) |
Plant Address | 28821 Madison Rd. Echo, OR 97826 |
Utility | Echo 2 (56803) |
Latitude, Longitude | 45.7286, -119.4181 |
Generation Dates on File | Jun 2009 to Dec 2022 |
Initial Operation Date | June 2009 |
Annual Generation | 19.2 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 08-372-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - West (PACW) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | PacifiCorp (1738) OR |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Generator 1 Details Operating June 2009
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
RTO ISO LMP Node Designation | HINKLE_NODET |
RTO ISO Location Designation For Reporting Wholesale Sales Data | HINKLE_NODET |
Nameplate Capacity | 8 MW |
Summer Capacity | 8 MW |
Winter Capacity | 8 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 4 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 4 |
---|---|
Predominant Turbine Manufacturer | REpower |
Predominant Turbine Model Number | MM92 |
Design Wind Speed | 13 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 257.5 |
Four Corners Windfarm LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1047 | Minot Wind Project | Minot, ND | 21.6 GWh |
#1048 | Threemile Canyon | Boardman, OR | 21.5 GWh |
#1049 | Sand Ranch Windfarm LLC | Echo, OR | 21.4 GWh |
#1050 | Coram Energy LLC | Tehachapi, CA | 21.3 GWh |
#1051 | Four Mile Canyon Windfarm LLC | Echo, OR | 20.6 GWh |
#1052 | Oregon Trail Windfarm LLC | Echo, OR | 20.4 GWh |
#1053 | Jersey-Atlantic Wind Farm | Atlantic City, NJ | 20.3 GWh |
#1054 | Cisco | Brewster, MN | 19.6 GWh |
#1055 | Wind Turbine | Casco, WI | 19.5 GWh |
#1056 | GPS Cabazon Wind LLC | North Palm Springs, CA | 19.3 GWh |
#1058 | Orchard Windfarm 4, LLC | Lexington, OR | 19.0 GWh |
#1059 | Lakota Ridge LLC | Hendricks, MN | 19.0 GWh |
#1060 | Cassia Wind | Hagerman, ID | 18.9 GWh |
#1061 | Medicine Bow | Medicine Bow, WY | 18.2 GWh |
#1062 | Orchard Windfarm 3, LLC | Lexington, OR | 18.0 GWh |
#1063 | Fairmont Wind | Fairmont, MN | 17.9 GWh |
#1064 | Orchard Windfarm 2, LLC | Lexington, OR | 17.8 GWh |
#1065 | Buffalo Mountain Energy Center | Oliver Springs, TN | 17.7 GWh |
#1066 | Jericho Power | Berlin, NH | 17.7 GWh |
#1067 | Pacific Canyon Windfarm LLC | Echo, OR | 17.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Four Corners Windfarm LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Big Top LLC | Echo, OR | 3.4 GWh | 5.6 mi |
Butter Creek Power LLC | Echo, OR | 11.2 GWh | 1.9 mi |
Carty Generating Station | Boardman, OR | 3.3 TWh | 19.2 mi |
Coyote Springs | Boardman, OR | 2.1 TWh | 14.8 mi |
Coyote Springs II | Boardman, OR | 2.5 TWh | 14.8 mi |
Finley Buttes Landfill Gas | Boardman, OR | 40.4 GWh | 9.6 mi |
Four Mile Canyon Windfarm LLC | Echo, OR | 20.6 GWh | 6 mi |
Hermiston Generating Plant | Hermiston, OR | 3.3 TWh | 5.7 mi |
Hermiston Power Partnership | Hermiston, OR | 4.3 TWh | 6.8 mi |
McNary | Umatilla, OR | 5.1 TWh | 15.7 mi |
McNary Dam Fish Attraction Project | Plymouth, WA | 66.2 GWh | 15.7 mi |
NorWest Energy 9 LLC | Pendleton, OR | 11.7 GWh | 13.5 mi |
Oregon Trail Windfarm LLC | Echo, OR | 20.4 GWh | 1.3 mi |
Pacific Canyon Windfarm LLC | Echo, OR | 17.4 GWh | 6.1 mi |
Sand Ranch Windfarm LLC | Echo, OR | 21.4 GWh | 6.5 mi |
Threemile Digester | Boardman, OR | 37.7 GWh | 23.3 mi |
Wagon Trail LLC | Echo, OR | 6.4 GWh | 5.6 mi |
Ward Butte Windfarm LLC | Echo, OR | 14.8 GWh | 2.2 mi |
Wheatridge 1 | Lexington, OR | 295.9 GWh | 15.6 mi |
Wheatridge Hybrid | Morrow, OR | 733.4 GWh | 15.6 mi |