Fort Green Solar Power Plant
N County Road 663, Bowling Green, FL 33834Plant Summary Information
Fort Green Solar Power Plant is ranked #19 out of 185 solar farms in Florida in terms of total annual net electricity generation.
Fort Green Solar Power Plant generated 34.6 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Fort Green Solar Power Plant |
---|---|
Utility Name | Duke Energy Florida, LLC |
Location | Hardee County, FL |
Initial Operation Date | August 2022 |
Last Update | Dec 2024 |
Annual Generation | 158.9 GWh |
Annual Consumption | 575.7 k MMBtu |
Ranked #2,627 out of 11,949 Power Plants Nationwide | |
Ranked #378 out of 5,739 Solar Power Plants Nationwide | |
Ranked #90 out of 293 Florida Power Plants | |
Ranked #19 out of 185 Florida Solar Power Plants | |
Fuel Types | Solar |
Map of Fort Green Solar Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fort Green Solar Power Plant.
Monthly Net Generation for Fort Green Solar Power Plant
Fort Green Solar Power Plant Details
Summary Information | |
---|---|
Plant Name | Fort Green Solar Power Plant (64533) |
Plant Address | N County Road 663, Bowling Green, FL 33834 |
Utility | Duke Energy Florida, LLC (6455) |
Latitude, Longitude | 27.64113, -81.94158 |
Generation Dates on File | May 2022 to Dec 2024 |
Initial Operation Date | August 2022 |
Annual Generation | 158.9 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Florida Inc (FPC) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Duke Energy Florida, LLC (6455) FL |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Generator PV1 Details Operating August 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 74.9 MW |
Summer Capacity | 74.9 MW |
Winter Capacity | 74.9 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | August 2022 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Tilt Angle | 15 |
DC Net Capacity | 126.7 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Fort Green Solar Power Plant Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#368 | Southfork Solar | Parrish, FL | 161.7 GWh |
#369 | Southampton Solar, LLC | Newsoms, VA | 161.4 GWh |
#370 | Alpine Solar | Lancaster, CA | 161.0 GWh |
#371 | Lily Solar | Martin, SC | 160.7 GWh |
#372 | FPL Saw Palmetto Solar Energy Center | Youngstown, FL | 160.4 GWh |
#373 | Assembly Solar III | Lennon, MI | 160.4 GWh |
#374 | Desert Harvest II LLC | Desert Center, CA | 156.5 GWh |
#375 | SR Cedar Springs, LLC | Blakely, GA | 160.3 GWh |
#376 | Mule Creek Renewable Energy Center | Panama City, FL | 160.1 GWh |
#377 | Grizzly Ridge Solar | Hamilton County, TX | 159.6 GWh |
#379 | Terrill Creek | Green Cove Springs, FL | 158.8 GWh |
#380 | FPL Etonia Creek | Palatka, FL | 158.6 GWh |
#381 | Cabin Creek Solar, LLC | Biscoe, NC | 158.3 GWh |
#382 | Bulldog Solar LLC | Warrenton, GA | 158.2 GWh |
#383 | Bluegrass Solar | Church Hill, MD | 158.1 GWh |
#384 | Fence Post Solar Hybrid Project, LLC | Corsicana, TX | 156.0 GWh |
#385 | Willow Solar Energy Center | Myakka City, FL | 156.7 GWh |
#386 | Apex Solar | Dillon, MT | 156.7 GWh |
#387 | Twin Rivers Solar Power Plant | Jasper, FL | 156.6 GWh |
#388 | Spring Grove I | Spring Grove, VA | 156.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fort Green Solar Power Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alafia Solar | Mulberry, FL | 119.6 GWh | 7.7 mi |
Duette Solar Power Plant | Parrish, FL | 155.8 GWh | 8.3 mi |
Durrance | Mulberry, FL | 88.6 GWh | 9.9 mi |
Grange Hall Solar | Wimauma, FL | 104.4 GWh | 13.9 mi |
Hardee Power Station | Bowling Green, FL | 946.3 GWh | 1.4 mi |
Hines Energy Complex | Bartow, FL | 12.4 TWh | 11.1 mi |
Jamison Solar (FL) | Mulberry, FL | 142.7 GWh | 11.5 mi |
Lake Hancock Solar | Bartow, FL | 92.2 GWh | 7.8 mi |
Lithia Solar | Lithia, FL | 127.8 GWh | 15.7 mi |
Midulla Generating Station | Bowling Green, FL | 2.9 TWh | 1.3 mi |
Mosaic New Wales Operations | Mulberry, FL | 396.2 GWh | 14.9 mi |
Mosaic South Pierce Operations | Mulberry, FL | 120.4 GWh | 8.6 mi |
Mulberry Cogeneration Facility | Bartow, FL | 399.7 GWh | 14.9 mi |
Payne Creek Solar | Bowling Green, FL | 121.1 GWh | 2.1 mi |
Polk | Mulberry, FL | 5.8 TWh | 6.7 mi |
Sambucus | Myakka City, FL | 151.5 GWh | 15.3 mi |
Southfork Solar | Parrish, FL | 161.7 GWh | 16 mi |
Tiger Bay | Ft. Meade, FL | 1.1 TWh | 9.2 mi |
Vandolah Power Station | Wauchula, FL | 723.8 GWh | 8.2 mi |
Willow Solar Energy Center | Myakka City, FL | 156.7 GWh | 15.8 mi |