Fort Detrick Solar PV
Fort Detrick USAG Area B , Mon, Frederick, MD 21702Plant Summary Information
Fort Detrick Solar PV is ranked #35 out of 162 power plants in Maryland in terms of total annual net electricity generation.
Fort Detrick Solar PV generated 6.5 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Fort Detrick Solar PV |
---|---|
Utility Name | Montevue Lane Solar, LLC |
Location | Frederick County, MD |
Initial Operation Date | February 2016 |
Last Update | Dec 2022 |
Annual Generation | 23.3 GWh |
Annual Consumption | 84.7 k MMBtu |
Ranked #4,776 out of 11,249 Power Plants Nationwide | |
Ranked #1,035 out of 5,158 Solar Power Plants Nationwide | |
Ranked #35 out of 162 Maryland Power Plants | |
Ranked #8 out of 124 Maryland Solar Power Plants | |
Fuel Types | Solar |
Map of Fort Detrick Solar PV
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fort Detrick Solar PV.
Monthly Net Generation for Fort Detrick Solar PV
Fort Detrick Solar PV Details
Summary Information | |
---|---|
Plant Name | Fort Detrick Solar PV (61552) |
Plant Address | Fort Detrick USAG Area B , Mon Frederick, MD 21702 |
Utility | Montevue Lane Solar, LLC (61153) |
Latitude, Longitude | 39.44, -77.45 |
Generation Dates on File | Jan 2017 to Dec 2022 |
Initial Operation Date | February 2016 |
Annual Generation | 23.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | The Potomac Edison Co (15263) MD |
Grid Voltage | 34.50 kV |
Energy Storage | Yes |
Generator FDSPV Details Operating February 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
RTO ISO LMP Node Designation | 5021574 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | NA |
Nameplate Capacity | 15.7 MW |
Summer Capacity | 15.7 MW |
Winter Capacity | 12.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 15 |
DC Net Capacity | 18.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Fort Detrick Solar PV Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1025 | SPS1 Dollarhide | Jal, NM | 23.6 GWh |
#1026 | Santa Fe Solar Energy Center | Santa Fe, NM | 23.6 GWh |
#1027 | SPS2 Jal | Jal, NM | 23.6 GWh |
#1028 | Wallingford Solar | Wallingford, CT | 23.5 GWh |
#1029 | Yemassee Solar | Yemassee, SC | 23.5 GWh |
#1030 | Tinton Falls Solar Farm | Tinton Falls, NJ | 23.5 GWh |
#1031 | Open Range Solar Center, LLC | Nyssa, OR | 23.4 GWh |
#1032 | Riley | Riley, OR | 23.4 GWh |
#1033 | SPS4 Monument | Monument, NM | 23.4 GWh |
#1034 | Marin Clean Energy Solar One | Richmond, CA | 23.4 GWh |
#1036 | SEPV9 Power Plant | Twentynine Palms, CA | 23.3 GWh |
#1037 | Turkey Creek PV1 | Kirby, NC | 23.3 GWh |
#1038 | Adams Solar Center | Madras, OR | 23.3 GWh |
#1039 | SR Camden | Camden, AR | 23.3 GWh |
#1040 | Oak Solar | NC | 23.1 GWh |
#1041 | OSLH, LLC | Bend, OR | 23.1 GWh |
#1042 | DG AMP Solar Piqua Manier | Piqua, OH | 23.0 GWh |
#1043 | Calverton Solar Energy Center | Calverton, NY | 22.9 GWh |
#1044 | South Valley Solar Energy Center | Albuquerque, NM | 22.8 GWh |
#1045 | Midway Green Solar | Union, SC | 22.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fort Detrick Solar PV.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Baker Point | Thurmont, MD | 14.0 GWh | 10.1 mi |
Blake Solar Plant | Charles Town, WV | 12.8 GWh | 23.8 mi |
CES VMT Solar | Hagerstown, MD | 1.5 GWh | 22.2 mi |
Dam No. 4 Hydro Station | Shepherdstown, WV | 8.0 GWh | 20.4 mi |
Dickerson Power | Dickerson, MD | 295.4 GWh | 15.9 mi |
Emmitsburg Solar Arrays | Emmitsburg, MD | 3.1 GWh | 19 mi |
Francis Scott Key Mall | Frederick, MD | 633.4 MWh | 4.3 mi |
Frederick County - Landfill | Frederick, MD | 3.8 GWh | 7.1 mi |
Hostetter Solar One, LLC | Hagerstown, MD | 4.0 GWh | 20.5 mi |
Maryland Solar | Hagerstown, MD | 35.1 GWh | 16.7 mi |
Millville Hydro Station | Millville, WV | 7.9 GWh | 21.3 mi |
MNCPPC Germantown Solar | Boyds, MD | 1.7 GWh | 21.3 mi |
MO33 CSG | Gaithersburg, MD | 1.7 GWh | 24.8 mi |
Montgomery County Correctional Facility | Boyds, MD | 2.5 GWh | 16.3 mi |
Montgomery County Resource Recovery | Dickerson, MD | 279.2 GWh | 16.5 mi |
Mount Saint Mary's | Emmitsburg, MD | 19.7 GWh | 17.2 mi |
Shepherds Mill CSG | Union Bridge, MD | 3.3 GWh | 17.5 mi |
Solar Hagerstown | Hagerstown, MD | 18.4 GWh | 18.9 mi |
Spruce - WCMD - Rubble I | Williamsport, MD | 2.0 GWh | 23.4 mi |
Spruce - WCMD - Rubble II | Williamsport, MD | 2.8 GWh | 23.6 mi |