Foote Creek IV
1567 Wyoming Highway 13, Rock River, WY 82083Plant Summary Information
Foote Creek IV is ranked #25 out of 27 wind farms in Wyoming in terms of total annual net electricity generation.
Foote Creek IV generated 11.6 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Foote Creek IV |
---|---|
Utility Name | PacifiCorp |
Location | Carbon County, WY |
Initial Operation Date | August 2000 |
Last Update | Dec 2023 |
Annual Generation | 11.6 GWh |
Annual Consumption | 39.7 k MMBtu |
Ranked #5,667 out of 11,852 Power Plants Nationwide | |
Ranked #1,102 out of 1,345 Wind Power Plants Nationwide | |
Ranked #57 out of 69 Wyoming Power Plants | |
Ranked #25 out of 27 Wyoming Wind Power Plants | |
Fuel Types | Wind |
Previous Operators |
Terra-Gen Operating Co LLC (2013 to 2017) Terra-Gen Operating Co-Wind (2018 to 2021) PacifiCorp (2022 to 2023) |
Map of Foote Creek IV
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Foote Creek IV.
Monthly Net Generation for Foote Creek IV
Foote Creek IV Details
Summary Information | |
---|---|
Plant Name | Foote Creek IV (55610) |
Plant Address | 1567 Wyoming Highway 13, Rock River, WY 82083 |
Utility | PacifiCorp (14354) |
Latitude, Longitude | 41.6744, -106.1805 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | August 2000 |
Annual Generation | 11.6 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 00-168-000 |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | PacifiCorp (14354) WY |
Grid Voltage | 134.00 kV |
Energy Storage | No |
Generator GEN1 Details Operating August 2000
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 16.8 MW |
Summer Capacity | 16.8 MW |
Winter Capacity | 16.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 2000 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 5 |
Turbine Details | |
Number Of Turbines | 5 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V136-4.2 |
Design Wind Speed | 22.4 MPH |
Wind Quality Class | 1 - High Wind |
Turbine Hub Height Feet | 446 |
Foote Creek IV Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1092 | Lakota Ridge LLC | Hendricks, MN | 13.3 GWh |
#1093 | Greensburg | Greensburg, KS | 13.0 GWh |
#1094 | Tehachapi Wind Resource I | Tehachapi, CA | 12.6 GWh |
#1095 | Fort Hays State University Wind Farm | Hays, KS | 12.6 GWh |
#1096 | Huerfano River Wind | Walsenburg, CO | 12.4 GWh |
#1097 | Uilk Wind LLC | Pipestone, MN | 12.3 GWh |
#1098 | Future Generation Wind | Plymouth, MA | 12.2 GWh |
#1099 | Fairmont Wind | Fairmont, MN | 11.9 GWh |
#1100 | Haviland Plastic Products | Haviland, OH | 11.7 GWh |
#1101 | Coastal Energy Project | Aberdeen, WA | 11.6 GWh |
#1103 | Lamar Plant | Lamar, CO | 11.6 GWh |
#1104 | Cooper Farms VW Project | Van Wert, OH | 11.5 GWh |
#1105 | Western Plains Wind | Oakley, KS | 11.3 GWh |
#1106 | Leonardo Wind 1 LLC | Alden, IA | 11.2 GWh |
#1107 | LafargeHolcim - Paulding Wind Project | Paulding, OH | 11.2 GWh |
#1108 | Ralls Wind Farm | Ralls, TX | 11.0 GWh |
#1109 | Medicine Bow | Medicine Bow, WY | 10.9 GWh |
#1110 | Madison Windpower LLC | Madison, NY | 10.8 GWh |
#1111 | Edom Hills Project 1 LLC | Cathedral City, CA | 10.8 GWh |
#1112 | Lincoln Heights II | Lake Benton, MN | 10.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Foote Creek IV.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alcova | Alcova, WY | 68.1 GWh | 66.4 mi |
Corriedale Wind Energy | Cheyenne, WY | 202.5 GWh | 73.1 mi |
Dunlap | Medicine Bow, WY | 432.0 GWh | 25.5 mi |
Ekola Flats | Hanna, WY | 740.1 GWh | 20 mi |
Foote Creek I | McFadden, WY | 215.5 GWh | 3.4 mi |
Foote Creek III | McFadden, WY | 14.6 GWh | 0.6 mi |
Fremont Canyon | Alcova, WY | 176.3 GWh | 63.8 mi |
Happy Jack Windpower Project | Cheyenne, WY | 55.8 GWh | 71.6 mi |
High Plains | Rock River, WY | 342.1 GWh | 8.7 mi |
Kortes | Sinclair, WY | 146.2 GWh | 49.9 mi |
Laramie River Station | Wheatland, WY | 7.0 TWh | 73.2 mi |
McFadden Ridge | Rock River, WY | 104.3 GWh | 10.4 mi |
Medicine Bow | Medicine Bow, WY | 10.9 GWh | 11.6 mi |
Roundhouse Wind Energy Project | Cheyenne, WY | 832.9 GWh | 68.5 mi |
Seminoe | Sinclair, WY | 140.7 GWh | 50.1 mi |
Seven Mile Hill | Medicine Bow, WY | 463.2 GWh | 19.7 mi |
Silver Sage Windpower | Cheyenne, WY | 107.6 GWh | 70.8 mi |
Sinclair Oil Refinery | Sinclair, WY | 5.5 GWh | 48.5 mi |
TB Flats | Medicine Bow, WY | 1.4 TWh | 34.9 mi |
Whiskey Hill Solar | Walden, CO | 2.4 GWh | 59.8 mi |