FirstEnergy Bay Shore
4701 Bay Shore Road, Oregon, OH 43616Plant Summary Information
FirstEnergy Bay Shore is ranked #2 out of 13 petroleum coke power plants nationwide in terms of total annual net electricity generation.
FirstEnergy Bay Shore is comprised of 2 generators and generated 163.8 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | FirstEnergy Bay Shore |
---|---|
Utility Name | Walleye Power, LLC |
Location | Lucas County, OH |
Initial Operation Date | August 1955 |
Last Update | Dec 2023 |
Annual Generation | 938.3 GWh |
Annual Consumption | 12.9 M MMBtu |
Ranked #771 out of 11,852 Power Plants Nationwide | |
Ranked #2 out of 13 Petroleum Coke Power Plants Nationwide | |
Ranked #23 out of 183 Ohio Power Plants | |
Ranked #1 out of 2 Ohio Petroleum Coke Power Plants | |
Fuel Types | Petroleum Coke : 99.5% |
Previous Operator |
FirstEnergy Generation Corp (2013 to 2017) Walleye Power, LLC (2018 to 2023) |
Map of FirstEnergy Bay Shore
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for FirstEnergy Bay Shore.
Monthly Net Generation for FirstEnergy Bay Shore
FirstEnergy Bay Shore Details
Summary Information | |
---|---|
Plant Name | FirstEnergy Bay Shore (2878) |
Plant Address | 4701 Bay Shore Road, Oregon, OH 43616 |
Utility | Walleye Power, LLC (62031) |
Latitude, Longitude | 41.6917, -83.4378 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | August 1955 |
Annual Generation | 938.3 GWh |
Fuel Types | Petroleum Coke : 99.5% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Utilities (22) |
Sector | IPP CHP (3) |
Water Source | Lake Erie |
Ash Impoundment | No |
Transmission / Distribution Owner | American Transmission Systems Inc (56162) OH |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator 1 Details Operating August 1955
Technology | Petroleum Coke |
---|---|
Prime Mover | Steam Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | BAYSHOR218 KV BS10 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | BAYSHOR218 KV BS10 |
Nameplate Capacity | 171 MW |
Nameplate Power Factor | 0.88 |
Summer Capacity | 139.5 MW |
Winter Capacity | 137 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1955 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
---|---|
Topping Or Bottoming | T |
Energy Source | Petroleum Coke / Distillate Fuel Oil / Bituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | OVER |
Fluidized Bed Technology | Yes |
Pulverized Coal Technology | No |
Subcritical Technology | Yes |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | PC / BIT |
---|
Generator CT Details Operating August 1967
Technology | Petroleum Liquids |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | BAYSHOR2138 KV BS81 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | BAYSHOR2138 KV BS81 |
Nameplate Capacity | 16 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 14.2 MW |
Winter Capacity | 16.2 MW |
Minimum Load | 5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 1967 |
Combined Heat & Power | No |
Sector Name | IPP CHP (3) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Other Combustion Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
FirstEnergy Bay Shore Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Orca Acquisitions, LLC | 19 Headquarters Plaza, West Tower-8th Floor, Morristown, NJ 7960 | Generator 1 | 100.00% |
Orca Acquisitions, LLC | 19 Headquarters Plaza, West Tower-8th Floor, Morristown, NJ 7960 | Generator 2 | 100.00% |
Orca Acquisitions, LLC | 19 Headquarters Plaza, West Tower-8th Floor, Morristown, NJ 7960 | Generator 3 | 100.00% |
Orca Acquisitions, LLC | 19 Headquarters Plaza, West Tower-8th Floor, Morristown, NJ 7960 | Generator 4 | 100.00% |
Orca Acquisitions, LLC | 19 Headquarters Plaza, West Tower-8th Floor, Morristown, NJ 7960 | Generator CT | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Petroleum Coke.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1 | Monroe (MI) | Monroe, MI | 12.9 TWh |
#3 | Northside Generating Station | Jacksonville, FL | 3.0 TWh |
#4 | Yellowstone Energy LP | Billings, MT | 441.5 GWh |
#5 | Alpena Cement Plant | Alpena, MI | 176.1 GWh |
#6 | Brame Energy Center | Lena, LA | 3.0 TWh |
#7 | Savannah River Mill | Rincon, GA | 86.3 GWh |
#8 | Valero Refinery Corpus Christi West | Corpus Christi, TX | 98.6 GWh |
#9 | Seadrift Coke LP | Port Lavaca, TX | 18.7 GWh |
#10 | Manitowoc | Manitowoc, WI | 137.2 GWh |
#11 | University of Northern Iowa | Cedar Falls, IA | 19.6 GWh |
#12 | Toledo Ref Power Recovery Train | Oregon, OH | 1.8 GWh |
#13 | Roquette America | Keokuk, IA | 207.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding FirstEnergy Bay Shore.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Anthony Wayne Solar #1 | Toledo, OH | 1.5 GWh | 8.4 mi |
Bay View Backup Power Facility | Toledo, OH | 424.0 MWh | 2.4 mi |
Bowling Green Generating Station | Bowling Green, OH | 2.1 GWh | 22.9 mi |
Bowling Green Peaking | Bowling Green, OH | 1.5 GWh | 23.4 mi |
Bowling Green Wind | Bowling Green, OH | 4.6 GWh | 26.6 mi |
Davis Besse | Oak Harbor, OH | 7.4 TWh | 19.3 mi |
DG AMP Solar Bowling Green | Bowling Green, OH | 39.4 GWh | 21.7 mi |
Fermi | Frenchtown Twp, MI | 8.3 TWh | 20.9 mi |
Fremont Energy Center | Fremont, OH | 3.6 TWh | 26 mi |
Genoa Diesel Generating Station | Genoa, OH | 130.0 MWh | 13.2 mi |
IGS PCW1 | Rossford, OH | 906.0 MWh | 12.3 mi |
Monroe (MI) | Monroe, MI | 12.9 TWh | 14.5 mi |
Oregon Clean Energy Center | Oregon, OH | 6.6 TWh | 1.7 mi |
Owens Corning Headquarters | Toledo, OH | 1.4 GWh | 6 mi |
PNA Rossford Solar Array | Rossford, OH | 2.4 GWh | 8.1 mi |
Sumpter Energy Associates | Belleville, MI | 58.0 GWh | 28.8 mi |
Temperance Solar, LLC | Erie, MI | 41.3 GWh | 6.1 mi |
Toledo Ref Power Recovery Train | Oregon, OH | 1.8 GWh | 5.3 mi |
Troy Energy LLC | Luckey, OH | 821.7 GWh | 14.9 mi |
Woodville RTO BTM | Woodville, OH | 75.0 MWh | 16.5 mi |