Eastman Cogeneration Facility
Bldg 121, 2290 Callahan Road, Longview, TX 75602Plant Summary Information
Eastman Cogeneration Facility is ranked #50 out of 774 power plants in Texas in terms of total annual net electricity generation.
Eastman Cogeneration Facility is comprised of 3 generators and generated 810.1 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Eastman Cogeneration Facility |
---|---|
Utility Name | Eastman Cogeneration LP |
Location | Harrison County, TX |
Initial Operation Date | April 2001 |
Last Update | Jan 2025 |
Annual Generation | 2.9 TWh |
Annual Consumption | 28.2 M MMBtu |
Ranked #405 out of 11,979 Power Plants Nationwide | |
Ranked #246 out of 2,255 Natural Gas Power Plants Nationwide | |
Ranked #50 out of 774 Texas Power Plants | |
Ranked #37 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Eastman Cogeneration Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Eastman Cogeneration Facility.
Monthly Net Generation for Eastman Cogeneration Facility
Eastman Cogeneration Facility Details
Summary Information | |
---|---|
Plant Name | Eastman Cogeneration Facility (55176) |
Plant Address | Bldg 121, 2290 Callahan Road, Longview, TX 75602 |
Utility | Eastman Cogeneration LP (49791) |
Latitude, Longitude | 32.4481, -94.6903 |
Generation Dates on File | Jan 2002 to Jan 2025 |
Initial Operation Date | April 2001 |
Annual Generation | 2.9 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 01-080-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP CHP (3) |
Water Source | Ferguson Lake |
Ash Impoundment | |
Transmission / Distribution Owner | Southwestern Electric Power Co (17698) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name |
KINDER MORGAN TEJAS PIPELINE LLC GULF SOUTH PIPELINE COMPANY LP TEXAS EASTERN TRANSMISSION LP |
Pipeline Notes | ENBRIDGE PIPELINES EAST TEXAS |
Natural Gas Storage | No |
Generator GEN1 Details Operating April 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | CSWEASTMAN |
RTO ISO Location Designation For Reporting Wholesale Sales Data | CSWEASTMAN |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 153.7 MW |
Winter Capacity | 168.3 MW |
Minimum Load | 75 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2001 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN2 Details Operating July 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | CSWEASTMAN |
RTO ISO Location Designation For Reporting Wholesale Sales Data | CSWEASTMAN |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 153.7 MW |
Winter Capacity | 168.3 MW |
Minimum Load | 65 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2001 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN3 Details Operating July 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | CSWEASTMAN |
RTO ISO Location Designation For Reporting Wholesale Sales Data | CSWEASTMAN |
Nameplate Capacity | 127.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 109.8 MW |
Winter Capacity | 120 MW |
Minimum Load | 18 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2001 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | B |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Eastman Cogeneration Facility Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#236 | Cedar Bayou | Baytown, TX | 3.0 TWh |
#237 | Carville Energy LLC | St Gabriel, LA | 2.9 TWh |
#238 | Westbrook Energy Center Power Plant | Westbrook, ME | 2.9 TWh |
#239 | East River | New York, NY | 2.9 TWh |
#240 | High Bridge | St. Paul, MN | 2.9 TWh |
#241 | Rocky Mountain Energy Center | Keenesburg, CO | 2.9 TWh |
#242 | Grays Harbor Energy Facility | Elma, WA | 2.9 TWh |
#243 | Kleen Energy Systems Project | Middletown, CT | 2.9 TWh |
#244 | Nelson Energy Center | Rock Falls, IL | 2.9 TWh |
#245 | Northeastern | Oologah, OK | 4.2 TWh |
#247 | Empire Generating Co LLC | Rensselaer, NY | 2.9 TWh |
#248 | Currant Creek | Mona, UT | 2.8 TWh |
#249 | Silverhawk | North Las Vegas, NV | 2.8 TWh |
#250 | GREC | Chouteau, OK | 3.4 TWh |
#251 | Gateway Generating Station | Antioch, CA | 2.8 TWh |
#252 | Port Westward | Clatskanie, OR | 2.8 TWh |
#253 | Chattahoochee Energy Facility | Franklin, GA | 2.8 TWh |
#254 | Gulf Clean Energy Center | Pensacola, FL | 2.8 TWh |
#255 | Attala | Sallis, MS | 2.7 TWh |
#256 | Colusa Generating Station | Maxwell, CA | 2.7 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Eastman Cogeneration Facility.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arsenal Hill | Shreveport, LA | 188.6 GWh | 54.4 mi |
Delilah Solar Energy LLC | Bogota, TX | 64.4 GWh | 64 mi |
Harrison County Power Project | Marshall, TX | 3.2 TWh | 15.2 mi |
Hecate Energy Upshur Rural LLC | Ore City, TX | 4.8 GWh | 27.4 mi |
International Paper Texarkana Mill | Queen City, TX | 378.2 GWh | 66.4 mi |
J Lamar Stall Unit | Shreveport, LA | 3.3 TWh | 54.4 mi |
Kellam Solar | Ben Wheeler, TX | 108.9 GWh | 59.8 mi |
Knox Lee | Longview, TX | 476.6 GWh | 5.7 mi |
Lieberman | Mooringsport, LA | 155.8 GWh | 46.1 mi |
Mansfield Mill | Mansfield, LA | 737.2 GWh | 69.2 mi |
Martin Lake | Tatum, TX | 9.5 TWh | 14.7 mi |
Nacogdoches Power | Cushing, TX | 183.0 GWh | 44.3 mi |
Pirkey | Hallsville, TX | 3.4 TWh | 12 mi |
Samson Solar Energy | Cunningham, TX | 414.7 GWh | 62.7 mi |
Snider Industries | Marshall, TX | 11.5 GWh | 20.4 mi |
Stampede Solar Hybrid | Saltillo, TX | 101.3 GWh | 63.6 mi |
Stryker Creek | Jacksonville, TX | 1.1 TWh | 39.2 mi |
Tenaska Gateway Generating Station | Mt. Enterprise, TX | 1.4 TWh | 30 mi |
Welsh | Pittsburg, TX | 4.4 TWh | 42.8 mi |
Wilkes | Avinger, TX | 1.1 TWh | 28.9 mi |