Domtar Paper Co LLC Plymouth NC
NC Hwy 149 N, Plymouth, NC 27962Plant Summary Information
Domtar Paper Co LLC Plymouth NC is ranked #48 out of 85 black liquor power plants nationwide in terms of total annual net electricity generation.
Domtar Paper Co LLC Plymouth NC is comprised of 2 generators and generated 107.5 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Domtar Paper Co LLC Plymouth NC |
---|---|
Utility Name | Domtar Paper Company LLC |
Location | Martin County, NC |
Initial Operation Date | September 1952 |
Last Update | Dec 2023 |
Annual Generation | 344.1 GWh |
Annual Consumption | 20.0 M MMBtu |
Ranked #1,669 out of 11,835 Power Plants Nationwide | |
Ranked #48 out of 85 Black Liquor Power Plants Nationwide | |
Ranked #23 out of 862 North Carolina Power Plants | |
Ranked #3 out of 5 North Carolina Black Liquor Power Plants | |
Fuel Types | Black Liquor : 49.7% Wood/Wood Waste Solids : 39.0% Natural Gas : 10.1% Distillate Fuel Oil : 1.2% |
Map of Domtar Paper Co LLC Plymouth NC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Domtar Paper Co LLC Plymouth NC.
Monthly Net Generation for Domtar Paper Co LLC Plymouth NC
Domtar Paper Co LLC Plymouth NC Details
Summary Information | |
---|---|
Plant Name | Domtar Paper Co LLC Plymouth NC (50189) |
Plant Address | NC Hwy 149 N, Plymouth, NC 27962 |
Utility | Domtar Paper Company LLC (55903) |
Latitude, Longitude | 35.8628, -76.7831 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | September 1952 |
Annual Generation | 344.1 GWh |
Fuel Types | Black Liquor : 49.7% Wood/Wood Waste Solids : 39.0% Natural Gas : 10.1% Distillate Fuel Oil : 1.2% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 86-594-001 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Paper Manufacturing (322) |
Sector | Industrial CHP (7) |
Water Source | Roanoke River |
Ash Impoundment | No |
Transmission / Distribution Owner | Virginia Electric & Power Co (19876) NC |
Grid Voltage | 13.80 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | PIEDMONT NATURAL GAS |
Natural Gas Storage | No |
Generator TG9 Details Operating September 1976
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 42 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 40.8 MW |
Winter Capacity | 40.8 MW |
Minimum Load | 14 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1976 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
---|---|
Topping Or Bottoming | T |
Energy Source | Black Liquor / Distillate Fuel Oil / Wood/Wood Waste Solids / Residual Fuel Oil / Natural Gas |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Pulverized Coal Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | BLQ / DFO / WDS / RFO / NG |
---|
Generator TG10 Details Operating June 1978
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 72 MW |
Nameplate Power Factor | 0.97 |
Summer Capacity | 74 MW |
Winter Capacity | 74 MW |
Minimum Load | 14 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 1978 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
---|---|
Topping Or Bottoming | T |
Energy Source | Wood/Wood Waste Solids / Natural Gas / Sludge Waste / Distillate Fuel Oil |
Startup Source | Natural Gas / Residual Fuel Oil / Black Liquor |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Pulverized Coal Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | WDS / RFO / SLW / NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 43.94 MW |
Net Winter Capacity With Natural Gas | 43.94 MW |
Net Summer Capacity With Oil | 38.77 MW |
Net Winter Capacity With Oil | 38.77 MW |
Time To Switch From Gas To Oil | UNK |
Time To Switch From Oil To Gas | UNK |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Domtar Paper Co LLC Plymouth NC Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Black Liquor.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#38 | PCA-Valdosta Mill | Valdosta, GA | 306.6 GWh |
#39 | DeRidder Mill | DeRidder, LA | 389.0 GWh |
#40 | Billerud Quinnesec Mill | Norway, MI | 288.8 GWh |
#41 | Pixelle Specialty Solutions LLC - Spring Grove Facility | Spring Grove, PA | 387.5 GWh |
#42 | International Paper Texarkana Mill | Queen City, TX | 378.2 GWh |
#43 | Alabama River Pulp | Perdue Hill, AL | 302.9 GWh |
#44 | WestRock Demopolis Mill | Demopolis, AL | 290.7 GWh |
#45 | Escanaba Mill | Escanaba, MI | 411.8 GWh |
#46 | Georgia-Pacific Palatka Operations | Palatka, FL | 320.3 GWh |
#47 | International Paper Co. - New Bern Mill | New Bern, NC | 205.1 GWh |
#49 | International Paper Pensacola | Cantonment, FL | 336.2 GWh |
#50 | Riverwood International Macon Mill | Macon, GA | 359.3 GWh |
#51 | Georgia-Pacific Consr Prods LP-Naheola | Pennington, AL | 258.8 GWh |
#52 | Woodland Pulp, LLC | Baileyville, ME | 366.6 GWh |
#53 | Buckeye Florida LP | Perry, FL | 270.5 GWh |
#54 | International Paper - Orange | Orange, TX | 238.6 GWh |
#55 | Inland Paperboard Packaging Rome | Rome, GA | 358.0 GWh |
#56 | Nippon Dynawave Packaging Longview WA | Longview, WA | 291.9 GWh |
#57 | Plant 31 Paper Mill | West Monroe, LA | 490.9 GWh |
#58 | Hopewell Mill | Hopewell, VA | 284.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Domtar Paper Co LLC Plymouth NC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Albemarle Beach Solar | Roper, NC | 217.5 GWh | 10.2 mi |
Davis Lane Solar, LLC | Edenton, NC | 9.2 GWh | 22.1 mi |
Edenton Solar | Edenton, NC | 9.6 GWh | 18.8 mi |
Everetts Wildcat Solar, LLC | Williamston, NC | 7.4 GWh | 18.4 mi |
Hardison Farm Solar, LLC | Williamston, NC | 10.2 GWh | 13.6 mi |
Jakana Solar | Williamston, NC | 9.5 GWh | 16.7 mi |
Jamesville Road Solar, LLC | Jamesville, NC | 11.0 GWh | 1.6 mi |
MC1 Solar | Williamston, NC | 7.5 GWh | 20 mi |
Meadows PV 1 | Williamston, NC | 18.2 GWh | 19.3 mi |
Mill Pond Solar, LLC | Jamesville, NC | 10.5 GWh | 2.3 mi |
Modlin Solar Farm | Williamston, NC | 9.6 GWh | 18.3 mi |
Plymouth Solar LLC | Plymouth, NC | 2.0 GWh | 4.1 mi |
Rose Acre Solar Energy Storage | Currituck, NC | 1.5 GWh | 20.8 mi |
Wilkinson Solar LLC | Pantego, NC | 131.4 GWh | 18.4 mi |
Williamston Solar | Williamston, NC | 9.4 GWh | 16.3 mi |
Williamston Speight Solar, LLC | Williamston, NC | 30.9 GWh | 21.4 mi |
Williamston West Farm, LLC | Williamston, NC | 4.3 GWh | 18.3 mi |
Windsor Cooper HIill Solar, LLC | Windsor, NC | 8.7 GWh | 11.2 mi |
Windsor Hwy 17 Solar | Windsor, NC | 10.4 GWh | 12 mi |
Windsor Solar | Windsor, NC | 9.2 GWh | 12 mi |