Cricket Valley Energy
2241 Route NY 22, Dover, NY 12522Plant Summary Information
Cricket Valley Energy is ranked #8 out of 832 power plants in New York in terms of total annual net electricity generation.
Cricket Valley Energy is comprised of 6 generators and generated 1.1 TWh during the 3-month period between May 2024 to August 2024.
Plant Name | Cricket Valley Energy |
---|---|
Utility Name | Cricket Valley Energy Center LLC |
Location | Dutchess County, NY |
Initial Operation Date | April 2020 |
Last Update | Aug 2024 |
Annual Generation | 4.3 TWh |
Annual Consumption | 34.2 M MMBtu |
Ranked #255 out of 11,835 Power Plants Nationwide | |
Ranked #136 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #8 out of 832 New York Power Plants | |
Ranked #3 out of 116 New York Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Cricket Valley Energy
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cricket Valley Energy.
Monthly Net Generation for Cricket Valley Energy
Cricket Valley Energy Details
Summary Information | |
---|---|
Plant Name | Cricket Valley Energy (57185) |
Plant Address | 2241 Route NY 22, Dover, NY 12522 |
Utility | Cricket Valley Energy Center LLC (56534) |
Latitude, Longitude | 41.67611, -73.58111 |
Generation Dates on File | Mar 2020 to Aug 2024 |
Initial Operation Date | April 2020 |
Annual Generation | 4.3 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Dry cooling system |
Ash Impoundment | No |
Transmission / Distribution Owner | Consolidated Edison Co-NY Inc (4226) NY |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | IROQUOIS GAS TRANSMISSION SYS LP |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator U001 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CCG1 |
Ownership | Wholly Owned by Other Entity |
Duct Burners | Yes |
Nameplate Capacity | 174.2 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 143.3 MW |
Winter Capacity | 150.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2020 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator U002 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CCG2 |
Ownership | Wholly Owned by Other Entity |
Duct Burners | Yes |
Nameplate Capacity | 174.2 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 143.3 MW |
Winter Capacity | 150.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator U003 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CCG3 |
Ownership | Wholly Owned by Other Entity |
Duct Burners | Yes |
Nameplate Capacity | 174.2 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 143.3 MW |
Winter Capacity | 150.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator U004 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CCG1 |
Ownership | Wholly Owned by Other Entity |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 263.3 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 195.4 MW |
Winter Capacity | 229.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator U005 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CCG2 |
Ownership | Wholly Owned by Other Entity |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 263.3 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 195.4 MW |
Winter Capacity | 229.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator U006 Details Operating April 2020
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CCG3 |
Ownership | Wholly Owned by Other Entity |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 263.3 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 195.4 MW |
Winter Capacity | 229.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Cricket Valley Energy Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U001 | 100.00% |
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U002 | 100.00% |
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U003 | 100.00% |
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U004 | 100.00% |
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U005 | 100.00% |
Cricket Valley Energy Holdings LLC | 31 Milk St, Boston, MA 2109 | Generator U006 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#126 | Hillabee Energy Center | Alexander City, AL | 4.5 TWh |
#127 | Fox Energy Center | Wrightstown, WI | 4.5 TWh |
#128 | Morgan Energy Center | Decatur, AL | 4.5 TWh |
#129 | Lower Mount Bethel Energy | Bangor, PA | 4.4 TWh |
#130 | Channel Energy Center LLC | Pasadena, TX | 4.9 TWh |
#131 | Hill Top Energy Center, LLC | Carmichaels, PA | 4.4 TWh |
#132 | Dresden Energy Facility | Dresden, OH | 4.4 TWh |
#133 | Lowman Energy Center | Leroy, AL | 4.3 TWh |
#134 | Cane Run | Louisville, KY | 4.3 TWh |
#135 | Bosque County Peaking | Laquna Park, TX | 4.3 TWh |
#137 | Buck | Salisbury, NC | 4.3 TWh |
#138 | Central Alabama Generating Station | Billingsley, AL | 4.3 TWh |
#139 | Astoria Energy | New York, NY | 4.3 TWh |
#140 | ExxonMobil Beaumont Refinery | Beaumont, TX | 4.4 TWh |
#141 | Astoria Energy II | Astoria, NY | 4.2 TWh |
#142 | Woodbridge Energy Center | Keasbey, NJ | 4.2 TWh |
#143 | Rowan | Salisbury, NC | 4.2 TWh |
#144 | Allegheny Energy Units 3 4 & 5 | Springdale, PA | 4.2 TWh |
#145 | Ratcliffe | De Kalb, MS | 4.2 TWh |
#146 | Hunterstown Power Plant | Gettysburg, PA | 4.2 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cricket Valley Energy.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bulls Bridge | New Milford, CT | 41.8 GWh | 4.7 mi |
County of Dutchess, NY (Airport) | Wappinger Falls, NY | 2.9 GWh | 15.6 mi |
Cream Street Solar | Hyde Park, NY | 3.6 GWh | 16.1 mi |
DOCCS Greenhaven | Stormville, NY | 5.9 GWh | 9.9 mi |
Dover CSG | Dover Plains, NY | 3.7 GWh | 0.4 mi |
Dutchess Cnty Resource Recovery Facility | Poughkeepsie, NY | 10.0 GWh | 18.8 mi |
East Fishkill CSG | East Fishkill, NY | 3.5 GWh | 14.7 mi |
JB-Tobin 2 | La Grange, NY | 1.9 GWh | 11.6 mi |
Kimberly Clark-Unit 1,2,3 | New Milford, CT | 217.4 GWh | 11.9 mi |
Lightstar Renewables - Project 1001 | Hyde Park, NY | 5.8 GWh | 16.7 mi |
Lightstar Renewables - Project 1002 | Hyde Park, NY | 2.3 GWh | 18.9 mi |
Millbrook School | Millbrook, NY | 1.8 GWh | 11.9 mi |
New Milford Gas Recovery | New Milford, CT | 5.4 GWh | 12 mi |
Phillips Route 82 Solar LLC | East Fishkill, NY | 8.3 GWh | 8.9 mi |
Rocky River (CT) | New Milford, CT | 12.5 GWh | 9.9 mi |
Salt Point Solar (Hybrid) | Poughkeepsie, NY | 2.1 GWh | 16.2 mi |
Stanford | Stanfordville, NY | 9.4 GWh | 14.5 mi |
Underhill | Poughkeepsie, NY | 3.9 GWh | 15.9 mi |
Union Vale | Lagrangeville, NY | 2.1 GWh | 8.4 mi |
Wappinger Falls Hydroelectric | Wappinger Falls, NY | 11.8 GWh | 18.4 mi |