CP Kelco San Diego Plant
2025 E Harbor Dr, San Diego, CA 92113Plant Summary Information
CP Kelco San Diego Plant is ranked #81 out of 346 natural gas power plants in California in terms of total annual net electricity generation.
CP Kelco San Diego Plant is comprised of 3 generators and generated 19.6 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | CP Kelco San Diego Plant |
---|---|
Utility Name | CP Kelco US Inc. |
Location | San Diego County, CA |
Initial Operation Date | October 1983 |
Last Update | Sep 2024 |
Annual Generation | 78.1 GWh |
Annual Consumption | 1.1 M MMBtu |
Ranked #3,470 out of 11,852 Power Plants Nationwide | |
Ranked #965 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #393 out of 1,570 California Power Plants | |
Ranked #81 out of 346 California Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
CPKelco U S Inc (2013 to 2022) CP Kelco US Inc. (2023 to 2023) |
Map of CP Kelco San Diego Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for CP Kelco San Diego Plant.
Monthly Net Generation for CP Kelco San Diego Plant
CP Kelco San Diego Plant Details
Summary Information | |
---|---|
Plant Name | CP Kelco San Diego Plant (52147) |
Plant Address | 2025 E Harbor Dr, San Diego, CA 92113 |
Utility | CP Kelco US Inc. (3221) |
Latitude, Longitude | 32.6947, -117.1436 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | October 1983 |
Annual Generation | 78.1 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 81-40-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Food Manufacturing (311) |
Sector | Industrial CHP (7) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | San Diego Gas & Electric Co (16609) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | SAN DIEGO GAS AND ELECTRIC COMPANY |
Natural Gas Storage | Yes |
Liquefied Natural Gas Storage | No |
Generator GEN1 Details Operating October 1983
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 9.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 9.2 MW |
Winter Capacity | 9.2 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1983 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN2 Details Operating October 1983
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1983 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN3 Details Out of Service October 1983
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Out of Service |
First Operation Date | October 1983 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
CP Kelco San Diego Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#955 | Elk Hills Cogen | Tupman, CA | 80.7 GWh |
#956 | Carson Ice-Gen Project | Sacramento, CA | 80.7 GWh |
#957 | Clearwater Paper IPP Lewiston | Lewiston, ID | 371.6 GWh |
#958 | Garden City | Garden City, KS | 79.5 GWh |
#959 | Phillips 66 Rodeo Refinery | Rodeo, CA | 291.0 GWh |
#960 | Chanute 2 | Chanute, KS | 79.2 GWh |
#961 | Lakefield Junction | Trimont, MN | 79.0 GWh |
#962 | Androscoggin Energy Center | Jay, ME | 82.0 GWh |
#963 | Colbert | Tuscumbia, AL | 78.7 GWh |
#964 | Rokeby | Lincoln, NE | 80.3 GWh |
#966 | Cleveland Works | Cleveland, OH | 232.6 GWh |
#967 | DeRidder Mill | DeRidder, LA | 389.0 GWh |
#968 | Chino Mines | Hurley, NM | 77.4 GWh |
#969 | Sowega Power | Baconton, GA | 77.2 GWh |
#970 | Wolf Hills Energy | Bristol, VA | 77.1 GWh |
#971 | Fountain Valley Power Facility | Fountain, CO | 77.0 GWh |
#972 | Cargill Corn Milling Division | Eddyville, IA | 76.3 GWh |
#973 | Camden Plant Holding LLC | Camden, NJ | 76.0 GWh |
#974 | AES Huntington Beach LLC | Huntington Beach, CA | 75.9 GWh |
#975 | Gibson City Energy Center LLC | Gibson City, IL | 75.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding CP Kelco San Diego Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Childrens Hospital | San Diego, CA | 26.8 GWh | 7.2 mi |
Chula Vista Energy Center | Chula Vista, CA | 1.7 GWh | 8.7 mi |
County of San Diego COC Hybrid | San Diego, CA | 3.1 GWh | 9.6 mi |
County of San Diego SBRC | Chula Vista, CA | 2.3 GWh | 5.7 mi |
Cuyamaca Peak Energy Plant | El Cajon, CA | 12.1 GWh | 12.2 mi |
El Cajon Energy Center | El Cajon, CA | 7.6 GWh | 12.2 mi |
Gas Utilization Facility | San Diego, CA | 32.6 GWh | 6.1 mi |
Grossmont Hospital | La Mesa, CA | 27.5 GWh | 9.9 mi |
Grossmont HS Solar Project | El Cajon, CA | 2.1 GWh | 11.9 mi |
Kyocera International Inc.(San Diego) | San Diego, CA | 8.8 GWh | 8.6 mi |
Lindberg FIeld Solar | San Diego, CA | 4.6 GWh | 4.4 mi |
Lindberg Field Solar 2 | San Diego, CA | 3.5 GWh | 4.3 mi |
Miramar Energy Facility | San Diego, CA | 12.4 GWh | 12.7 mi |
MM San Diego-Miramar | San Diego, CA | 35.9 GWh | 10.4 mi |
Naval Hospital Medical Center | San Diego, CA | 21.5 GWh | 2.2 mi |
PFMG Solar Grossmont Helix LLC | La Mesa, CA | 2.0 GWh | 7.5 mi |
San Diego Community College | San Diego, CA | 6.5 GWh | 7.8 mi |
San Diego State University | San Diego, CA | 55.9 GWh | 7.2 mi |
SeaWorld Aquatica | Chula Vista, CA | 1.9 GWh | 11 mi |
University of San Diego | San Diego, CA | 6.2 GWh | 6 mi |