Copper
651 Hawkins Blvd., El Paso, TX 79915Plant Summary Information
Copper is ranked #160 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
Copper is comprised of 1 generator and generated 8.0 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Copper |
---|---|
Utility Name | El Paso Electric Co |
Location | El Paso County, TX |
Initial Operation Date | July 1980 |
Last Update | Dec 2023 |
Annual Generation | 48.7 GWh |
Annual Consumption | 914.4 k MMBtu |
Ranked #3,892 out of 11,852 Power Plants Nationwide | |
Ranked #1,096 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #492 out of 754 Texas Power Plants | |
Ranked #160 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Copper
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Copper.
Monthly Net Generation for Copper
Copper Details
Summary Information | |
---|---|
Plant Name | Copper (9) |
Plant Address | 651 Hawkins Blvd., El Paso, TX 79915 |
Utility | El Paso Electric Co (5701) |
Latitude, Longitude | 31.7569, -106.375 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | July 1980 |
Annual Generation | 48.7 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | El Paso Electric Company (EPE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | |
Transmission / Distribution Owner | El Paso Electric Co (5701) TX |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | ONEOK WES TEX TRANSMISSION LLC |
Generator 1 Details Operating July 1980
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 86.9 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 63 MW |
Winter Capacity | 65 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1980 |
---|---|
Planned Retirement | December 2030 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Copper Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1086 | Amalgamated Sugar LLC Nampa | Nampa, ID | 49.3 GWh |
#1087 | Yuba City Energy Center | Yuba City, CA | 49.3 GWh |
#1088 | Fortistar North Tonawanda | North Tonawanda, NY | 49.3 GWh |
#1089 | Cambridge CT Hybrid | Cambridge, MN | 49.4 GWh |
#1090 | Genesis Alkali | Green River, WY | 264.4 GWh |
#1091 | International Paper Red River Mill | Campti, LA | 370.6 GWh |
#1092 | Weston RICE | Kronenwetter, WI | 48.9 GWh |
#1093 | International Paper Georgetown Mill | Georgetown, SC | 500.1 GWh |
#1094 | F B Culley | Newburgh, IN | 1.9 TWh |
#1095 | Dome Project | Fellows, CA | 48.7 GWh |
#1097 | Port Allen (LA) | Port Allen, LA | 48.6 GWh |
#1098 | Mars Wrigley Confectionery US, LLC | Hackettstown, NJ | 48.5 GWh |
#1099 | Canton North Carolina | Canton, NC | 281.5 GWh |
#1100 | Westside Energy Station | Rochester, MN | 48.4 GWh |
#1101 | MMSD Jones Island Wastewater | Milwaukee, WI | 61.0 GWh |
#1102 | Port Wentworth Mill | Port Wentworth, GA | 433.2 GWh |
#1103 | Tesoro Kenai Cogeneration Plant | Kenai, AK | 48.3 GWh |
#1104 | Newington | Newington, NH | 52.7 GWh |
#1105 | J Robert Massengale | Lubock, TX | 48.1 GWh |
#1106 | NY - Presbyt. Hospital - 525 E 68TH St | New York, NY | 48.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Copper.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Afton Generating Station | La Mesa, NM | 864.7 GWh | 37.1 mi |
Alamogordo Solar Energy Center | Alamogordo, NM | 11.3 GWh | 79.7 mi |
Buena Vista Energy Center | Chaparral, NM | 389.1 GWh | 22 mi |
Columbus Solar Project | Columbus, NM | 5.3 GWh | 71.6 mi |
Deming Solar Energy Center | Deming, NM | 19.4 GWh | 85.4 mi |
Fort Bliss (DEA EPIC) | El Paso, TX | 4.7 GWh | 5.1 mi |
Hatch Solar Energy Center I, LLC | Hatch, NM | 9.3 GWh | 79.5 mi |
Holloman Solar Facility | Holloman Air Force Ba, NM | 6.5 GWh | 82.4 mi |
Montana Power Station | El Paso, TX | 1.2 TWh | 10.6 mi |
Montana Solar Facility | El Paso, TX | 3.9 GWh | 10 mi |
New Mexico State University | Las Cruces, NM | 30.1 GWh | 28.5 mi |
Newman | El Paso, TX | 3.4 TWh | 16 mi |
Newman Solar | El Paso, TX | 15.5 GWh | 15.6 mi |
NMSU Solar and Storage | Las Cruces, NM | 7.7 GWh | 42.5 mi |
Nodal Power | Salt Lake City, UT | 15.8 GWh | 13.4 mi |
Phelps Dodge Refining | El Paso, TX | 62.5 GWh | 1.1 mi |
Rio Grande | SunLand Park, NM | 904.9 GWh | 10.6 mi |
Roadrunner Solar | Santa Teresa, NM | 72.6 GWh | 17.7 mi |
SunE EPE1 LLC | Chaparral, NM | 25.6 GWh | 19.3 mi |
SunE EPE2 LLC | Las Cruces, NM | 26.3 GWh | 46.5 mi |