Conception
33513 State Hwy J, Stanberry, MO 64499Plant Summary Information
Conception is ranked #43 out of 120 power plants in Missouri in terms of total annual net electricity generation.
Conception generated 12.2 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Conception |
---|---|
Utility Name | CR Clearing, LLC |
Location | Nodaway County, MO |
Initial Operation Date | April 2008 |
Last Update | Aug 2024 |
Annual Generation | 79.9 GWh |
Annual Consumption | 286.2 k MMBtu |
Ranked #3,428 out of 11,835 Power Plants Nationwide | |
Ranked #899 out of 1,343 Wind Power Plants Nationwide | |
Ranked #43 out of 120 Missouri Power Plants | |
Ranked #13 out of 14 Missouri Wind Power Plants | |
Fuel Types | Wind |
Previous Operator |
Conception (2013 to 2015) CR Clearing, LLC (2016 to 2023) |
Map of Conception
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Conception.
Monthly Net Generation for Conception
Conception Details
Summary Information | |
---|---|
Plant Name | Conception (56537) |
Plant Address | 33513 State Hwy J, Stanberry, MO 64499 |
Utility | CR Clearing, LLC (55735) |
Latitude, Longitude | 40.2572, -94.6722 |
Generation Dates on File | Apr 2008 to Aug 2024 |
Initial Operation Date | April 2008 |
Annual Generation | 79.9 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 07-248-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Associated Electric Cooperative, Inc. (AECI) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Associated Electric Coop, Inc (924) |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Generator 1 Details Operating April 2008
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 50.4 MW |
Summer Capacity | 50.4 MW |
Winter Capacity | 50.4 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2008 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 24 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 24 |
---|---|
Predominant Turbine Manufacturer | Suzlon |
Predominant Turbine Model Number | S88-2100 |
Design Wind Speed | 15.5 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262.4 |
Conception Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#889 | Whirlwind Energy Center | Floydada, TX | 83.9 GWh |
#890 | Greenfield Wind - MT | Fairfield, MT | 83.7 GWh |
#891 | Auwahi Wind Energy Hybrid | Kula, HI | 83.6 GWh |
#892 | Mojave 3/4/5 | Mojave, CA | 83.2 GWh |
#893 | G McNeilus Wind Farm Dodge Center | Dodge Center, MN | 83.1 GWh |
#894 | Brazos Wind Farm | Fluvanna, TX | 82.9 GWh |
#895 | Saddleback Ridge Wind Farm | Carthage, ME | 82.5 GWh |
#896 | Diamond Willow Wind Facility | Baker, MT | 82.1 GWh |
#897 | Bull Hill Wind Project | Eastbrook, ME | 81.6 GWh |
#898 | Patton Wind Farm | Patton, PA | 81.2 GWh |
#900 | Rolling Thunder Wind Farm Hybrid | Miller, SD | 79.7 GWh |
#901 | Dutch Hill Wind Project | Cohocton, NY | 79.5 GWh |
#902 | Rock Aetna Power Partners | Woodstock, MN | 79.3 GWh |
#903 | Ridgewind | Woodstock, MN | 78.9 GWh |
#904 | Fair Wind | Oakland, MD | 78.6 GWh |
#905 | South Dakota Wind Energy Cente | Highmore, SD | 78.5 GWh |
#906 | Moraine II Wind LLC | Woodstock, MN | 78.0 GWh |
#907 | Munnsville Wind Farm LLC | Madison, NY | 75.7 GWh |
#908 | Sleeping Bear LLC | Woodward, OK | 75.4 GWh |
#909 | Century Oak Wind Project, LLC | Cisco, TX | 75.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Conception.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Adams Wind | Lenox, IA | 440.1 GWh | 45.8 mi |
Atchison County Wind | Westboro, MO | 901.5 GWh | 40.6 mi |
August Wind Farm | Clearfield, IA | 6.8 GWh | 36.6 mi |
Birch | Clearfield, IA | 6.6 GWh | 36.8 mi |
Bluegrass Ridge | King City, MO | 84.1 GWh | 14.6 mi |
Clear Creek Wind | Maryville, MO | 632.8 GWh | 14 mi |
Contrail Wind Farm | Bedford, IA | 354.7 GWh | 29.6 mi |
Cow Branch | Tarkio, MO | 88.4 GWh | 44.1 mi |
Lake Road (MO) | St Joseph, MO | 47.7 GWh | 38.4 mi |
Lamoni Municipal Utilities | Lamoni, IA | 135.0 MWh | 46.3 mi |
Lenox | Lenox, IA | 12.0 MWh | 43.4 mi |
Loess Hills | Rock Port, MO | 6.6 GWh | 47 mi |
Lost Creek Wind Energy Facility | King City, MO | 401.8 GWh | 20.7 mi |
Nodaway | Conception Junction, MO | 16.0 GWh | 6.6 mi |
Osborn Wind Energy | Stewartsville, MO | 665.4 GWh | 36.7 mi |
POET Biorefining LLC - Corning | Corning, IA | 15.0 GWh | 49.4 mi |
Rock Creek Wind Project | Tarkio, MO | 1.1 TWh | 29.5 mi |
St Joseph Landfill Generating Station | St Joseph, MO | 2.9 GWh | 40.6 mi |
Villisca Municipal Power Plant | Villisca, IA | 13.0 MWh | 49.4 mi |
White Cloud Wind Project, LLC | Tarkio, MO | 873.2 GWh | 15.8 mi |