Collins Pine Project
500 Main Street, Chester, CA 96020Plant Summary Information
Collins Pine Project is ranked #20 out of 20 wood/wood waste solids power plants in California in terms of total annual net electricity generation.
Collins Pine Project is comprised of 1 generator and generated 9.9 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Collins Pine Project |
---|---|
Utility Name | Collins Pine Co |
Location | Plumas County, CA |
Initial Operation Date | December 1985 |
Last Update | Dec 2022 |
Annual Generation | 25.8 GWh |
Annual Consumption | 940.8 k MMBtu |
Ranked #4,641 out of 11,249 Power Plants Nationwide | |
Ranked #138 out of 165 Wood/Wood Waste Solids Power Plants Nationwide | |
Ranked #651 out of 1,501 California Power Plants | |
Ranked #20 out of 20 California Wood/Wood Waste Solids Power Plants | |
Fuel Types | Wood/Wood Waste Solids |
Map of Collins Pine Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Collins Pine Project.
Monthly Net Generation for Collins Pine Project
Collins Pine Project Details
Summary Information | |
---|---|
Plant Name | Collins Pine Project (10661) |
Plant Address | 500 Main Street Chester, CA 96020 |
Utility | Collins Pine Co (3953) |
Latitude, Longitude | 40.30342, -121.24443 |
Generation Dates on File | Jan 2001 to Dec 2022 |
Initial Operation Date | December 1985 |
Annual Generation | 25.8 GWh |
Fuel Types | Wood/Wood Waste Solids |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 94-101-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Wood Product Manufacturing (321) |
Sector | Industrial CHP (7) |
Water Source | Chester PUD |
Ash Impoundment | Yes Not Lined Operating |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 60.00 kV |
Energy Storage | No |
Generator GEN5 Details Operating September 2021
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2021 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
---|---|
Topping Or Bottoming | T |
Energy Source | Wood/Wood Waste Solids |
Startup Source | Wood/Wood Waste Solids / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | OVER |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Collins Pine Project Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wood/Wood Waste Solids.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#128 | International Paper Vicksburg Mill | Vicksburg, MS | 226.8 GWh |
#129 | TES Filer City Station | Filer City, MI | 290.7 GWh |
#130 | French Island | La Cross, WI | 64.8 GWh |
#131 | Pixelle Specialty Solutions LLC - Chillicothe Facility | Chillicothe, OH | 276.0 GWh |
#132 | Woodland Pulp, LLC | Baileyville, ME | 402.5 GWh |
#133 | Interstate Paper LLC Riceboro | Riceboro, GA | 108.5 GWh |
#134 | Pixelle Specialty Solutions LLC - Spring Grove Facility | Spring Grove, PA | 444.7 GWh |
#135 | Finch Paper | Glen Falls, NY | 137.4 GWh |
#136 | Indeck West Enfield Energy Center | West Enfield, ME | 28.1 GWh |
#137 | Douglas County Forest Products | Roseburg, OR | 27.6 GWh |
#139 | POET Biorefining - Chancellor | Chancellor, SD | 34.5 GWh |
#140 | NE Renewable Springfield, LLC | Springfield, NH | 25.0 GWh |
#141 | Stoltze CoGen1 | Columbia Falls, MT | 20.0 GWh |
#142 | KapStone Kraft Paper Corp | Roanoke Rapids, NC | 197.8 GWh |
#143 | Darrington | Darrington, WA | 17.8 GWh |
#144 | Cosmo Specialty Fibers Plant | Cosmopolis, WA | 106.0 GWh |
#145 | Hibbing | Hibbing, MN | 46.7 GWh |
#146 | Tamarack Energy Partnership | New Meadows, ID | 14.2 GWh |
#147 | Snider Industries | Marshall, TX | 14.1 GWh |
#148 | Georgia-Pacific Big Island | Big Island, VA | 56.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Collins Pine Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bear Creek | Shingletown, CA | 1.7 GWh | 40.8 mi |
Belden | Belden, CA | 250.2 GWh | 20.5 mi |
Bidwell Ditch Project | Hat Creek, CA | 11.7 GWh | 36 mi |
Bucks Creek | Storrie, CA | 68.9 GWh | 27.5 mi |
Butt Valley | Belden, CA | 75.7 GWh | 9.3 mi |
Caribou 1 | Belden, CA | 59.9 GWh | 15.9 mi |
Caribou 2 | Belden, CA | 449.9 GWh | 15.8 mi |
Cresta | Storrie, CA | 162.4 GWh | 34.1 mi |
De Sabla | Magalia, CA | 59.1 GWh | 36.3 mi |
Forks of Butte Hydro Project | Magalia, CA | 10.7 GWh | 36.3 mi |
High Sierra Cogeneration Plant | Susanville, CA | 36.1 GWh | 41.1 mi |
Lost Creek I | Burney, CA | 5.2 GWh | 32.6 mi |
Poe | Storrie, CA | 737.3 GWh | 41.8 mi |
Ponderosa Bailey Creek | Manton, CA | 379.6 MWh | 33.2 mi |
Rock Creek | Storrie, CA | 551.8 GWh | 28 mi |
Sierra Pacific Quincy Facility | Quincy, CA | 184.7 GWh | 30.7 mi |
South | Manton, CA | 17.9 GWh | 34 mi |
Toadtown | Magalia, CA | 3.3 GWh | 33.8 mi |
Volta 1 | Manton, CA | 7.0 GWh | 34.5 mi |
Volta 2 | Manton, CA | 2.4 GWh | 34.1 mi |