CML&P Generating Facility No. 2
2601 N. 5th Industrial Street, Coffeyville, KS 67337Plant Summary Information
CML&P Generating Facility No. 2 is ranked #11 out of 58 natural gas power plants in Kansas in terms of total annual net electricity generation.
CML&P Generating Facility No. 2 is comprised of 3 generators and generated 21.8 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | CML&P Generating Facility No. 2 |
---|---|
Utility Name | City of Coffeyville - (KS) |
Location | Montgomery County, KS |
Initial Operation Date | January 2017 |
Last Update | Dec 2023 |
Annual Generation | 93.2 GWh |
Annual Consumption | 899.9 k MMBtu |
Ranked #3,247 out of 11,836 Power Plants Nationwide | |
Ranked #919 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #60 out of 152 Kansas Power Plants | |
Ranked #11 out of 58 Kansas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of CML&P Generating Facility No. 2
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for CML&P Generating Facility No. 2.
Monthly Net Generation for CML&P Generating Facility No. 2
CML&P Generating Facility No. 2 Details
Summary Information | |
---|---|
Plant Name | CML&P Generating Facility No. 2 (59726) |
Plant Address | 2601 N. 5th Industrial Street, Coffeyville, KS 67337 |
Utility | City of Coffeyville - (KS) (3892) |
Latitude, Longitude | 37.09298, -95.58515 |
Generation Dates on File | Jan 2017 to Dec 2023 |
Initial Operation Date | January 2017 |
Annual Generation | 93.2 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Coffeyville - (KS) (3892) KS |
Grid Voltage | 138.00 kV / 69.00 kV / 12.47 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator 10 Details Operating January 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | GRDACOFFEYGRUNCOFF10 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | GRDACOFFEYGRUNCOFF10 |
Nameplate Capacity | 18.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.7 MW |
Winter Capacity | 18.7 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2017 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 8 Details Operating January 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | GRDACOFFGRUNCOFF8 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | GRDACOFFEYGRUNCOFF8 |
Nameplate Capacity | 18.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.7 MW |
Winter Capacity | 18.7 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2017 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 9 Details Operating January 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | GRDACOFFEYGRUNCOFF9 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | GRDACOFFEYGRUNCOFF9 |
Nameplate Capacity | 18.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.7 MW |
Winter Capacity | 18.7 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2017 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
CML&P Generating Facility No. 2 Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#909 | Bob Glanzer Generating Station | Huron, SD | 96.4 GWh |
#910 | Mont Belvieu Cogeneration Unit | Mont Belvieu, TX | 96.3 GWh |
#911 | McCartney | Strafford, MO | 96.1 GWh |
#912 | Lockport Energy Associates LP | Lockport, NY | 96.0 GWh |
#913 | Southeast Kern River Cogen | Bakersfield, CA | 95.7 GWh |
#914 | DeBary | DeBary, FL | 105.5 GWh |
#915 | Black Mountain Generating Station | Golden Valley, AZ | 94.9 GWh |
#916 | Terry Bundy Generating Station | Lincoln, NE | 118.5 GWh |
#917 | Vanderbilt University Power Plant | Nashville, TN | 94.3 GWh |
#918 | West Marinette | Peshtigo, WI | 93.8 GWh |
#920 | Mariposa Energy Project | Byron, CA | 92.8 GWh |
#921 | Oak Point Cogen | Belle Chasse, LA | 92.8 GWh |
#922 | Harlem River Yard | Bronx, NY | 92.5 GWh |
#923 | Greens Bayou | Houston, TX | 92.3 GWh |
#924 | University of Notre Dame | Notre Dame, IN | 92.2 GWh |
#925 | Pixelle Specialty Solutions LLC - Spring Grove Facility | Spring Grove, PA | 387.5 GWh |
#926 | Bellingham Cogeneration Facility | Bellingham, MA | 102.2 GWh |
#927 | Anson County Generation Facility | Lilesville, NC | 92.2 GWh |
#928 | Castleton Energy Center | Castleton, NY | 89.9 GWh |
#929 | Archbald Power Station | Archbald, PA | 112.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding CML&P Generating Facility No. 2.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Caney River Wind Project | Howard, KS | 709.3 GWh | 52.4 mi |
Chanute 2 | Chanute, KS | 79.2 GWh | 42.2 mi |
Chanute 3 | Chanute, KS | 694.0 MWh | 38.2 mi |
Chouteau | Pryor, OK | 6.9 TWh | 62.6 mi |
Coffeyville | Coffeyville, KS | 10.9 GWh | 4.1 mi |
Elk River Wind | Beaumont, KS | 287.8 GWh | 62.8 mi |
Erie | Erie, KS | 7.0 MWh | 37.9 mi |
Erie Energy Center | Erie, KS | 1.9 GWh | 38.3 mi |
Fredonia | Fredonia, KS | 15.0 MWh | 33.8 mi |
Girard | Girard, KS | 185.0 MWh | 50 mi |
Iola | Iola, KS | 909.0 MWh | 58 mi |
Jayhawk Wind Energy Center | Hepler, KS | 687.0 GWh | 52.1 mi |
Neosho Ridge Wind Energy Center | Galesburg, KS | 1.2 TWh | 29.4 mi |
North Fork Ridge Wind Energy Center | Mindenmines, MO | 547.2 GWh | 62.6 mi |
Northeastern | Oologah, OK | 4.0 TWh | 46.1 mi |
Pawhuska | Pawhuska, OK | 375.0 MWh | 51.3 mi |
Pensacola | Langley, OK | 228.0 GWh | 52.7 mi |
Prosperity Solar Farm CSG | Joplin, MO | 4.0 GWh | 63.5 mi |
Riverton | Riverton, KS | 1.1 TWh | 48.9 mi |
State Line Combined Cycle | Joplin, MO | 2.7 TWh | 53.6 mi |