Cloverdale Solar Center
1255 Hiatt Road, Cloverdale, CA 95425Plant Summary Information
Cloverdale Solar Center is ranked #577 out of 747 solar farms in California in terms of total annual net electricity generation.
Cloverdale Solar Center generated 624.4 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Cloverdale Solar Center |
---|---|
Utility Name | Adapture Renewables, Inc. |
Location | Sonoma County, CA |
Initial Operation Date | May 2019 |
Last Update | Dec 2022 |
Annual Generation | 2.4 GWh |
Annual Consumption | 8.8 k MMBtu |
Ranked #9,155 out of 11,249 Power Plants Nationwide | |
Ranked #3,990 out of 5,158 Solar Power Plants Nationwide | |
Ranked #1,274 out of 1,501 California Power Plants | |
Ranked #577 out of 747 California Solar Power Plants | |
Fuel Types | Solar |
Previous Operators |
Enerparc CA2, LLC (2016 to 2017) Enerparc Inc. (2018 to 2019) Adapture Renewables, Inc. (2020 to 2022) |
Map of Cloverdale Solar Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cloverdale Solar Center.
Monthly Net Generation for Cloverdale Solar Center
Cloverdale Solar Center Details
Summary Information | |
---|---|
Plant Name | Cloverdale Solar Center (60813) |
Plant Address | 1255 Hiatt Road Cloverdale, CA 95425 |
Utility | Adapture Renewables, Inc. (60496) |
Latitude, Longitude | 38.76958, -123.02072 |
Generation Dates on File | May 2019 to Dec 2022 |
Initial Operation Date | May 2019 |
Annual Generation | 2.4 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF15-259-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Generator ECA02 Details Operating May 2019
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | May 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 1.3 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Cloverdale Solar Center Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3980 | Sheldon Solar | Sheldon Springs, VT | 2.5 GWh |
#3981 | GWCC PV Solar Farm | Beltsville, MD | 2.5 GWh |
#3982 | Natick Mall | Natick, MA | 2.4 GWh |
#3983 | RV CSU Power LLC | Fort Collins, CO | 2.4 GWh |
#3984 | Mashpee Landfill Solar | Mashpee, MA | 2.4 GWh |
#3985 | Antelope Expansion 1B | Lancaster, CA | 2.4 GWh |
#3986 | Building G | Santa Fe Springs, CA | 2.4 GWh |
#3987 | Lower Cape May HS | Cape May, NJ | 2.4 GWh |
#3988 | Lisbon Street Solar | Lewiston, ME | 2.4 GWh |
#3989 | St. Albans SPEED Project | St. Albans, VT | 2.4 GWh |
#3991 | Washington St Community Solar Farm #3 | Ogden, NY | 2.4 GWh |
#3992 | Calabro Airport South Solar Project | Shirley, NY | 2.4 GWh |
#3993 | Bed Bath & Beyond DC Port Reading NJ | Port Reading, NJ | 2.4 GWh |
#3994 | Springer Solar 1 | Springer, NM | 2.4 GWh |
#3995 | Whately Solar | Whately, MA | 2.4 GWh |
#3996 | Lane Ave Solar LLC | North Brookfield, MA | 2.4 GWh |
#3997 | IKEA Westhampton 061 | Westampton, NJ | 2.4 GWh |
#3998 | USS Itasca Clean Energy Solar LLC | Grand Rapids, MN | 2.4 GWh |
#3999 | Corvias - Fort Riley II | Fort Riley, KS | 2.4 GWh |
#4000 | Epic Verona | Verona, WI | 2.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cloverdale Solar Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Aidlin Geothermal Power Plant | Middletown, CA | 93.8 GWh | 8.7 mi |
ASTI | Cloverdale, CA | 1.5 GWh | 2.5 mi |
Beringer | Saint Helena, CA | 1.7 GWh | 34.2 mi |
Bodega Avenue Solar LLC | Petaluma, CA | 4.9 GWh | 38.3 mi |
Calistoga Power Plant | Middletown, CA | 501.4 GWh | 15 mi |
Dissigno Healdsburg FPV, LLC | Healdsburg, CA | 6.5 GWh | 15.3 mi |
Geothermal 1 | Middletown, CA | 241.4 GWh | 16.3 mi |
Geothermal 2 | Middletown, CA | 284.6 GWh | 16.7 mi |
Geysers Unit 5-20 | Middletown, CA | 4.8 TWh | 14.9 mi |
Keysight - Santa Rosa | Santa Rosa, CA | 35.6 GWh | 26 mi |
Laguna Water Reclamation Facility | Santa Rosa, CA | 15.0 GWh | 30.9 mi |
Lake Mendocino | Ukiah, CA | 2.5 GWh | 30.8 mi |
Lavio Solar | Petaluma, CA | 2.0 GWh | 44.2 mi |
Santa Rosa Junior College Petaluma Solar | Petaluma, CA | 17.4 MWh | 26.3 mi |
Sonoma California Geothermal | Middletown, CA | 291.4 GWh | 14.3 mi |
Sonoma Central Landfill Phase I | Petaluma, CA | 9.9 GWh | 35.5 mi |
Sonoma Central Landfill Phase II | Petaluma, CA | 10.1 GWh | 35.5 mi |
Stage Gulch Solar | Petaluma, CA | 1.9 GWh | 46.1 mi |
Waste Mangement Redwood LFGTE | Novato, CA | 22.4 GWh | 48.8 mi |
Windsor Floating Solar | Windsor, CA | 2.8 GWh | 19.4 mi |