Clearwater Wind II
245 Rock Spring Road East, Miles City, MT 59301Plant Summary Information
Clearwater Wind II is ranked #21 out of 70 power plants in Montana in terms of total annual net electricity generation.
Clearwater Wind II generated 79.4 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Clearwater Wind II |
---|---|
Utility Name | Clearwater Wind II, LLC |
Location | Rosebud County, MT |
Initial Operation Date | December 2023 |
Last Update | Sep 2024 |
Annual Generation | 305.3 GWh |
Annual Consumption | 1.0 M MMBtu |
Ranked #1,826 out of 11,852 Power Plants Nationwide | |
Ranked #549 out of 1,345 Wind Power Plants Nationwide | |
Ranked #21 out of 70 Montana Power Plants | |
Ranked #6 out of 22 Montana Wind Power Plants | |
Fuel Types | Wind |
Map of Clearwater Wind II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clearwater Wind II.
Monthly Net Generation for Clearwater Wind II
Clearwater Wind II Details
Summary Information | |
---|---|
Plant Name | Clearwater Wind II (66184) |
Plant Address | 245 Rock Spring Road East, Miles City, MT 59301 |
Utility | Clearwater Wind II, LLC (65312) |
Latitude, Longitude | 46.81883, -106.19458 |
Generation Dates on File | Dec 2023 to Sep 2024 |
Initial Operation Date | December 2023 |
Annual Generation | 305.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | NorthWestern Energy (NWMT) (NWMT) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | NorthWestern Energy LLC - (MT) (12825) MT |
Grid Voltage | 500.00 kV |
Energy Storage | No |
Generator CW2 Details Operating December 2023
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 102.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 102.8 MW |
Winter Capacity | 102.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 37 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 37 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.82-127 |
Design Wind Speed | 12 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 374 |
Clearwater Wind II Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#539 | Oakfield Wind Project | City of Oakfield, ME | 315.4 GWh |
#540 | Glenrock | Glenrock, WY | 314.1 GWh |
#541 | Sand Bluff Wind Farm | Big Spring, TX | 313.3 GWh |
#542 | Elkhorn Valley Wind Farm | Union, OR | 312.3 GWh |
#543 | Post Wind Farm LP | Fluvanna, TX | 311.7 GWh |
#544 | Little Elk Wind Project LLC | Cordell, OK | 310.4 GWh |
#545 | Paulding Wind Farm II | Payne, OH | 308.2 GWh |
#546 | Champion Wind Farm LLC | Roscoe, TX | 306.8 GWh |
#547 | Paulding Wind Farm III | Payne, OH | 305.5 GWh |
#548 | Rio Bravo Windpower, LLC | Roma, TX | 305.4 GWh |
#550 | Gray County Wind Energy | Montezuma, KS | 304.3 GWh |
#551 | Michigan Wind 2 | Minden City, MI | 303.9 GWh |
#552 | Alta Wind Energy Center III | Mojave, CA | 302.6 GWh |
#553 | Alta Wind Energy Center II | Mojave, CA | 299.7 GWh |
#554 | Black Oak Wind Farm | Sauk Centre, MN | 298.1 GWh |
#555 | Rosewater Wind Farm | Chalmers, IN | 297.8 GWh |
#556 | Minco Wind II, LLC | Minco, OK | 296.5 GWh |
#557 | Deerfield Wind Energy 2 | Port Hope, MI | 295.1 GWh |
#558 | Palouse | Oakesdale, WA | 294.9 GWh |
#559 | Blue Canyon Windpower VI LLC | Carnegie, OK | 294.7 GWh |
Nearby Power Plants
Below are closest 14 power plants surrounding Clearwater Wind II.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Clearwater Wind East | Miles City, MT | 548.6 GWh | 9.3 mi |
Clearwater Wind I | Miles City, MT | 1.3 TWh | 8.7 mi |
Clearwater Wind III | Miles City, MT | 29.2 GWh | 0 mi |
Colstrip | Colstrip, MT | 9.2 TWh | 67.7 mi |
Colstrip Energy LP | Colstrip, MT | 306.2 GWh | 62.3 mi |
Culbertson Generation Station | Culbertson, MT | 316.6 GWh | 127.7 mi |
Fort Peck | Fort Peck, MT | 701.2 GWh | 83.1 mi |
Glendive GT | Glendive, MT | 1.5 GWh | 70.5 mi |
Hardin Generator Project | Hardin, MT | 435.4 GWh | 99.4 mi |
Miles City GT | Miles City, MT | 202.0 MWh | 33.9 mi |
OREG 1 Inc | Culbertson, MT | 147.0 GWh | 127.8 mi |
OREG 2 Inc | Culbertson, MT | 106.4 GWh | 127.8 mi |
South Mills Solar, LLC | Hardin, MT | 5.7 GWh | 101.9 mi |
Yellowtail | Hardin, MT | 846.0 GWh | 134.3 mi |