Choctaw County
2446 Highway 407, French Camp, MS 39745Plant Summary Information
Choctaw County is ranked #3 out of 54 power plants in Mississippi in terms of total annual net electricity generation.
Choctaw County is comprised of 4 generators and generated 1.8 TWh during the 3-month period between October 2024 to January 2025.
Plant Name | Choctaw County |
---|---|
Utility Name | Entergy Mississippi LLC |
Location | Choctaw County, MS |
Initial Operation Date | July 2003 |
Last Update | Jan 2025 |
Annual Generation | 6.0 TWh |
Annual Consumption | 46.0 M MMBtu |
Ranked #167 out of 11,979 Power Plants Nationwide | |
Ranked #74 out of 2,255 Natural Gas Power Plants Nationwide | |
Ranked #3 out of 54 Mississippi Power Plants | |
Ranked #2 out of 31 Mississippi Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
NRG Wholesale Generation LP (2013 to 2018) Entergy Mississippi LLC (2019 to 2023) |
Map of Choctaw County
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Choctaw County.
Monthly Net Generation for Choctaw County
Choctaw County Details
Summary Information | |
---|---|
Plant Name | Choctaw County (55706) |
Plant Address | 2446 Highway 407, French Camp, MS 39745 |
Utility | Entergy Mississippi LLC (12685) |
Latitude, Longitude | 33.2881, -89.4201 |
Generation Dates on File | Aug 2003 to Jan 2025 |
Initial Operation Date | July 2003 |
Annual Generation | 6.0 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 04-77-000 |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Tennessee Valley Authority (TVA) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | Tennessee Valley Authority (18642) MS |
Grid Voltage | 500.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | TEXAS EASTERN TRANSMISSION LP |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator CTG1 Details Operating July 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 179 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 164 MW |
Winter Capacity | 186 MW |
Minimum Load | 75 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG2 Details Operating July 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 179 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 164 MW |
Winter Capacity | 186 MW |
Minimum Load | 75 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG3 Details Operating July 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 179 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 164 MW |
Winter Capacity | 186 MW |
Minimum Load | 75 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG1 Details Operating July 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 362 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 289 MW |
Winter Capacity | 326 MW |
Minimum Load | 140 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Choctaw County Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#64 | Oregon Clean Energy Center | Oregon, OH | 6.3 TWh |
#65 | P L Bartow | St. Petersburg, FL | 6.2 TWh |
#66 | Sithe Independence Station | Oswego, NY | 6.2 TWh |
#67 | Port Everglades | Ft. Lauderdale, FL | 6.1 TWh |
#68 | Cottonwood Energy Project | Deweyville, TX | 6.1 TWh |
#69 | Indeck Niles Energy Center | Niles, MI | 6.1 TWh |
#70 | Montgomery County | Willis, TX | 6.1 TWh |
#71 | Lake Side Power Plant | Vineyard, UT | 6.1 TWh |
#72 | Hunterstown Power Plant | Gettysburg, PA | 6.1 TWh |
#73 | Hickory Run Energy Station | New Castle, PA | 6.0 TWh |
#75 | Lamar Power Project | Paris, TX | 6.0 TWh |
#76 | Lake Charles Power | West Lake, LA | 5.9 TWh |
#77 | Hamilton Liberty | Towanda, PA | 5.9 TWh |
#78 | Bethlehem Power Plant | Bethlehem, PA | 5.9 TWh |
#79 | Lake Road Generating Plant | Dayville, CT | 5.8 TWh |
#80 | Polk | Mulberry, FL | 5.8 TWh |
#81 | Santan | Gilbert, AZ | 5.8 TWh |
#82 | Channelview Cogeneration Plant | Channelview, TX | 5.8 TWh |
#83 | W S Lee | Williamston, SC | 5.6 TWh |
#84 | Doswell Energy Center | Ashland, VA | 5.6 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Choctaw County.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Attala | Sallis, MS | 2.7 TWh | 24 mi |
Caledonia | Steens, MS | 5.1 TWh | 70.7 mi |
CF Industries Yazoo City Complex | Yazoo City, MS | 143.1 GWh | 61.5 mi |
Columbus MS | Columbus, MS | 443.1 GWh | 55.7 mi |
Delta's Edge Solar | Greenwood, MS | 210.5 GWh | 41.9 mi |
Harvest Gold Solar | Indianola, MS | 96.8 GWh | 71.7 mi |
Kemper County | De Kalb, MS | 3.4 GWh | 58.1 mi |
Meridian | Meridian, MS | 434.0 MWh | 69.4 mi |
Meridian II | Meridian, MS | 7.6 GWh | 70.4 mi |
Meridian III | Meridian, MS | 119.6 GWh | 76.6 mi |
OE_MS6 | St.Artesia, MS | 220.4 GWh | 46.9 mi |
Pearl River Solar Park LLC | Morton, MS | 198.6 GWh | 54 mi |
Prairie Bluff | Houston, MS | 7.8 GWh | 52.2 mi |
Quantum Choctaw Power LLC | Ackerman, MS | 4.3 TWh | 13.7 mi |
Ragsdale Solar LLC | Canton, MS | 35.3 GWh | 61.3 mi |
Ratcliffe | De Kalb, MS | 4.3 TWh | 58 mi |
Red Hills Generating Facility | Ackerman, MS | 1.8 TWh | 13.1 mi |
SR Houston | Houston, MS | 2.2 GWh | 50.4 mi |
Sunflower County | Ruleville, MS | 107.1 GWh | 72 mi |
Walnut Grove Demonstration Plant | Walnut Grove, MS | 1.3 GWh | 49 mi |